About this file

This document contains questions and answers related to federal contract solicitation 69056721B000010 for public access enhancement work at the Willapa National Wildlife Refuge in Washington. The questions and answers provide clarification on aspects of the project plans, including the location of 120 linear feet of utility trench referenced in bid item A0640 to be addressed in Amendment A001, requirements for alkali-silica reactivity testing of concrete and precast concrete wheel stops, restrictions on placement of spoils and clarification on 40 hours of backhoe work. Specifications are also clarified disallowing one 3-inch lift of asphalt pavement instead of the required two 1.5-inch lifts. The agency is the Department of Transportation Federal Highway Administration.

View the file

Other files

File Type Posted
Tabulation of Bids Awarded.pdf PDF
Bid Opening Sign-in sheet.pdf PDF
BidSum.pdf PDF
Amendment A002.pdf PDF
Amendment A002.pdf PDF
QA_1-25-22.pdf PDF
QA2_1-21-22.pdf PDF
QA_1-21-22.pdf PDF
QA_1-14-22.pdf PDF
Amendment A001.pdf PDF
QA_1-13-22.pdf PDF
QA_1-12-22.pdf PDF
Corridor Reports Approach 1.pdf PDF
WA Pacific 2015 (2) IFB.pdf PDF
wa-a2015025_va.pdf PDF
wa-a2015025_Approach_Overflow_XS.pdf PDF
wa-a2015025_ha.pdf PDF
wa-a2015025_Approach1_XSReport.pdf PDF
xml and dxf files.zip ZIP file
Geotech Report_PBS.pdf PDF
Corridor Reports Overflow.pdf PDF
GM 12 19 Final Geotechnical and Construction Recommendaitons.pdf PDF
wa-a2015025_control_points.xlsx XLSX spreadsheet
final wa-a2015025_PlanSet.pdf PDF
Qunatities by Named Boundaries.pdf PDF
wa-a2015025_Overflow_XSReport.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA pacific 2015(2) Public Access Enhancement to Willapa National Wildlife Refuge Phase II

# General Technical Question Answer Date

1 X Please advise where the 120 lineal feet of utility trench reference in bid item A0640 is shown on the plans. See Section F of the plan set. Bid accordingly 1/12/22

2 X

Thank you for the quick response, but this does not answer my question. I will try to clarify below.

I am familiar with Section F of the plan set. To be more specific:

‐ 2” waterline is shown on plan sheet F.2 and paid under bid item A0340 ‐ 4” sewer line is shown on plan sheet F.2 and paid under bid item A0360 ‐ Cleanout is shown on plan sheet F.2 and paid under bid item A0380 *** the utility trench bid item A0640 of 120lf is not shown on the plans and I am trying to figure out what exactly this is for and where it is on the plans.

Will be address under Amendment A001 1/13/22

3 X I have been getting questions from our concrete subcontractors needing clarification if Alkali‐silica reactivity (ASR) testing will be required for the concrete work and/or precast concrete wheel stops?

yes, please bid accordingly 1/14/22

4 X Is it possible to place spoils over the north bank behind the existing buildings show on Sheet F‐2? No. See FP‐14 Subsection 204.14. 1/20/22

5 X Please provide clarification on the 40 hours of backhoe work?

See Subsection 622.01 of the Special Contract Requirements.

1/20/22

6 X Can one 3 inch lift of asphalt concrete pavement be placed instead of two 1.5 inch lifts of asphalt concrete pavement? No. See Sheets C.1 & C.2 of the plans. 1/20/22

7 X The specs call for paving the 3” of asphalt concrete pavement in two equal lifts. Will we be allowed to pave in 1 ‐ 3" lift?

No. See Sheets C.1 & C.2 of the plans. 1/20/22

Check General or Technical

File details come from the government source that posted it. Updated .