QA_1-14-22.pdf

PDF 404 KB Posted

Attached to
WA PACIFIC 2015(2) Public Access Enhancement to Willapa National Wildlife Refuge Phase II
Solicitation number
69056721B000010
Issued by

About this file

This document contains questions and answers regarding a federal contract solicitation for public access enhancements to the Willapa National Wildlife Refuge Phase II. The solicitation is issued by the Department of Transportation Federal Highway Administration as number 69056721B000010. Questions from bidders clarify that a 120 lineal foot utility trench referenced in bid item A0640 is not explicitly shown on the project plans but will be addressed in Amendment A001. Additionally, bidders require confirmation if alkali-silica reactivity testing will be required for concrete and precast concrete wheel stops, which is answered in the affirmative.

View the file

Other files

File Type Posted
Tabulation of Bids Awarded.pdf PDF
Bid Opening Sign-in sheet.pdf PDF
BidSum.pdf PDF
Amendment A002.pdf PDF
Amendment A002.pdf PDF
QA_1-25-22.pdf PDF
QA2_1-21-22.pdf PDF
QA_1-21-22.pdf PDF
QA_1-20-22.pdf PDF
Amendment A001.pdf PDF
QA_1-13-22.pdf PDF
QA_1-12-22.pdf PDF
Corridor Reports Approach 1.pdf PDF
WA Pacific 2015 (2) IFB.pdf PDF
wa-a2015025_va.pdf PDF
wa-a2015025_Approach_Overflow_XS.pdf PDF
wa-a2015025_ha.pdf PDF
wa-a2015025_Approach1_XSReport.pdf PDF
xml and dxf files.zip ZIP file
Geotech Report_PBS.pdf PDF
Corridor Reports Overflow.pdf PDF
GM 12 19 Final Geotechnical and Construction Recommendaitons.pdf PDF
wa-a2015025_control_points.xlsx XLSX spreadsheet
final wa-a2015025_PlanSet.pdf PDF
Qunatities by Named Boundaries.pdf PDF
wa-a2015025_Overflow_XSReport.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA pacific 2015(2) Public Access Enhancement to Willapa National Wildlife Refuge Phase II

# General Technical Question Answer Date

1 X Please advise where the 120 lineal feet of utility trench reference in bid item A0640 is shown on the plans. See Section F of the plan set. Bid accordingly 1/12/22

2 X

Thank you for the quick response, but this does not answer my question. I will try to clarify below.

I am familiar with Section F of the plan set. To be more specific:

- 2” waterline is shown on plan sheet F.2 and paid under bid item A0340

- 4” sewer line is shown on plan sheet F.2 and paid under bid item A0360

- Cleanout is shown on plan sheet F.2 and paid under bid item A0380 *** the utility trench bid item A0640 of 120lf is not shown on the plans and I am trying to figure out what exactly this is for and where it is on the plans.

Will be address under Amendment A001 1/13/22

3 X I have been getting questions from our concrete subcontractors needing clarification if Alkali-silica reactivity (ASR) testing will be required for the concrete work and/or precast concrete wheel stops?

yes, please bid accordingly 1/14/22

Check General or Technical