About this file

This document is an addendum to the statement of work for a design-build project to repair Building 907 Annex at Yokota Air Base in Japan. The project has an estimated cost between 139.1635 million and 695.817500 million Japanese yen and a performance period of 570 calendar days, with 210 days for design and 360 days for construction. The contractor must purchase and deliver ground-fault circuit interrupter receptacles, an advanced meter reading system, fire alarm and mass notification systems, and a fire alarm reporting system from the United States. Liquidated damages of 88,966 yen per day will be assessed for the first day of delay and 70,888 yen for each additional day until completion. Warranties will be for 10 years for metal roofing, 3 years for HVAC, and 1 year for all other items. The opportunity is for an indefinite-delivery/indefinite-quantity multiple award construction contract for the U.S. Army installations within Honshu, Japan and Yokota Air Base and its geographically separated units, issued by the Department of the Air Force Pacific Air Forces.

View the file

Other files

File Type Posted
Amendment FA520919RA0060010.pdf PDF
34 RFP Atch J11 Questions and Answers (Added by Amendment 0010).pdf PDF
23 RFP Atch J4a(PPQCoverletter) Amend 0009.pdf PDF
33 RFP Atch J10 Questions and Answers (Added by Amendment 0009).pdf PDF
Amendment FA520919RA0060009.pdf PDF
Amendment FA520919RA0060008.pdf PDF
32 RFP Atch J9 Questions and Answers (Added by Amendment 0008).pdf PDF
Attachment 3. Q and A No. 6 and 7 - Yokota Composite utilities 20.PDF PDF
Pre-proposal Conf Minutes FA520919RA006 19 Dec 23.pdf PDF
Attachment 1. MACC PreProposal Briefing Slides 18 Dec 23 - 2nd ON RAMP.pdf PDF
Attachment 2. Q and A No. 6 and 7 - Utility Map from Geobase.pdf PDF
29 Atch J7c Question No. 40 AMRS spec.pdf PDF
30 Atch J7d Question No. 38 MACC Mock Project Comm.jpg JPG image
25 RFP Atch J5 EnvelopeLabel(OF-17).pdf PDF
19 RFP AtcJ3d11_B907AnnexConceptPlan(Com).pdf PDF
9 RFP AtcJ3d1_Spec15011.pdf PDF
21 RFP AtcJ3d13_B907LeadPaintReport.pdf PDF
31 RFP Atch J8 Questions and Answers (Added by Amendment 0006).pdf PDF
16 RFP AtcJ3d8_B907AsBuilt (Sprinkler).pdf PDF
20 RFP AtcJ3d12_B907WaterFlowTR.pdf PDF
17 RFP AtcJ3d9_B907AnnexDemoPlan.pdf PDF
8.RFP AtcJ3c2(TaxExemp_Mock).docx DOCX document
22 RFP AtcJ3d14_AbestosSurveyReport.pdf PDF
1 Solicitation Amendment - FA520919RA0060007.pdf PDF
18 RFP AtcJ3d10_B907AnnexConceptPlan.pdf PDF
27 Atch J7a Question No. 48 Geotechnical Investigation Report for B906.pdf PDF
11.RFP AtcJ3d3_DispRec.xlsx XLSX spreadsheet
4 Atc J2b AFGP.pdf PDF
13 RFP AtcJ3d5_B907AnnexAsBuilt(Elec).pdf PDF
23 RFP Atch J4a(PPQCoverletter) Amend 0007.pdf PDF
14 RFP AtcJ3d6_B907AnnexAsBuild (Arch).pdf PDF
10 RFP AtcJ3d2_EnvProtection.pdf PDF
15 RFP AtcJ3d7_B906AsBuilt.pdf PDF
26 RFP Atch J6 QAs - FA520919RA006.pdf PDF
7.RFP AtcJ3c1(MockSectionB).xlsx XLSX spreadsheet
3 Atc J2a ArmyGP.pdf PDF
28 Atch J7b Question No. 33 Fire Alarm B907 Annex.pdf PDF
2 Atc J1 Other Req 30 Apr 21.pdf PDF
24 RFP Atch J4b(PPQ).docx DOCX document
5 RFP AtcJ3a MockSOW.pdf PDF
12 RFP AtcJ3d4_B907AnnexAsBuilt.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5209-19-R-A006

Attachment J-3.b

Addendum to Statement of Work for Mock Project

Project Number: ZNRE 19-1069

Project Title: Repair B907 Annex at Yokota, Air Base, Japan

1. Magnitude of Construction: Pursuant to FAR 36.204(f) the following is provided: The estimated amount of the project: Between ¥139,163,500 and ¥695,817,500 ($1.00 = ¥139.1635).

2. This project is Design-Build

3. The performance period will be 570 calendar days (210 calendar days for Design and 360 calendar days for construction) after Notice to Proceed is issued under the clause at 52.211-10 in

Section I of the contract. The time stated for completion shall include final cleanup of the premises.

4. Applicable Clauses:

(1) FAR 52.211-12 -- Liquidated Damages -- Construction (Sep 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ¥88,966 for the first day, and

¥70,888 for each additional day of delay until the work is completed and accepted. If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the

Termination clause.

(2) FAR 52.246-21 -- Warranty Of Construction (Mar 1994)

The words “One (1) year” in para (b) & (d) are modified to read 10 years for Metal roofing and 3 years for HVAC, and one (1) year for all other items.

(3) Identification of Contractor-Furnished U.S. Materials

(a) The Contractor shall purchase and deliver for use under this contract the following United States

Materials (CFUSM) (See Statement of Work, Paragraph VII.N.):

Item Item Description

1 Ground-Fault Circuit Interrupter (GFCI) receptacle

2 Advanced Meter Reading System (AMRS).

3 Fire Alarm and Mass Notification systems.

4 Fire Alarm Reporting system.

(b) Ocean transportation of the above items shall be in accordance with the clause at DFARS 252.247-

7023 in Section I. The Contractor shall notify the Contracting Officer in writing, within 30 calendar days after the receipt of the Notice to Proceed, of the name of importer and estimated date of arrival at the construction jobsite.

(c) In the event the Government and Contractor agree that the title to any surplus CFUSM, exempted from Japanese customs duty and taxes under the Status of Forces Agreement, will remain with the

FA5209-19-R-A006

Attachment J-3.b

Contractor, the disposition of such property accruing from the performance of this contract shall be the responsibility of the Contractor. The Contractor further agrees to make a full disclosure of such settlement to the Japanese Customs authorities for the payment of applicable duties and taxes.

5. Type of Task Order: Firm Fixed Price

6. Reference Documents

ATTACHMENT

NO.

TITLE DATE PAGE(S)

J-3.d.1 Specification Section 15011, Mechanical General Requirements

N/A 10

J-3.d.2 Specification Section 01410, Environmental Protection

N/A 12

J-3.d.3 Disposal and Recycling Data Sheet N/A 1 J-3.d.4 B907 Annex As-Built Drawings 12 Mar 1962 8 J-3.d.5 B907 Annex As-Built Drawing, Electrical 19 Dec 2014 1 J-3.d.6 B907 Annex As-Built Drawings, Architectural 2 Mar 1986 29 J-3.d.7 B906 As-Built Drawings 6 Apr 1994 20 J-3.d.8 B907 As-Built Drawings (Sprinkler) 16 Dec 1996 32 J-3.d.9 B907 Annex Demolition Plan N/A 1

J-3.d.10 B907 Annex Concept Plan N/A 1 J-3.d.11 B907 Annex Concept Plan (Communication) N/A 1 J-3.d.12 B907 Water Flow Test Report N/A 5 J-3.d.13 B907 Lead-based Paint Report 7 Jan 2019 1 J-3.d.14 Report Limited Asbestos Survey, Building 907 4 Apr 2019 58