Enclosure No. 2 SGP_Remediation_SOW_IFSites_7.7.25.pdf
PDF 2 MB Posted
- Solicitation number
- 5-S176-P-00210-00
- Issued by
-
Department of Energy Office of Science
About this file
This document is a Statement of Work (SOW) for the Disassembly and Removal of ARM Climate Research Facility Southern Great Plains (SGP) Integrated Facility (IF) Radar Sites in Oklahoma. The project involves dismantling and removing 3 radars and remediating 4 sites across 5 specific locations: IF4, IF5, IF7, IF8, and IF10. The contractor will be responsible for completely disassembling radar components (including domes, dishes, pedestals, platforms, and instrument containers), removing infrastructure such as communication towers, concrete foundations, shipping containers, and fencing, and ensuring all radar components are recycled or destroyed.
Key technical requirements include: full site restoration with compacted fill dirt, grass seeding to prevent erosion, cutting underground conduits 24" below surface, removing buried electrical and communication lines, and adhering to strict safety protocols including OSHA fall protection standards. The project has a desired completion date of September 30, 2025, with a pre-proposal meeting scheduled for July 14, 2025, and an on-site visit planned for July 17, 2025. Contractors must provide all personnel, equipment, and supplies, and will be accompanied by a Laboratory representative during work. All radar components must be thoroughly destroyed and cannot be resold, with the contractor required to certify their disposal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum and Acknowledgement Doc No.003.doc | DOC document | |
| SGP_Remediation_SOW_IFSites_7.17.pdf | ||
| SGP_Remediation_SOW_IFSites_7.17.25_Rev2.pdf | ||
| Addendum and Acknowledgement Doc No.002.doc | DOC document | |
| Addendum and Acknowledgement Doc.doc | DOC document | |
| RV1 Instructions to Offerors_G5-149039.doc | DOC document | |
| Noble County Wage Determination.pdf | ||
| SGP_IF Sites_Pre-Proposal Meeting.pptx | PPTX presentation | |
| Enclosure No. 1 ANL-70 Request for Quotation.doc | DOC document | |
| Enclosure No. 3 Safety Oversight 7_1_2025.docx | DOCX document | |
| Arm SGP IF Sites Remediation Meeting Link.docx | DOCX document | |
| Enclosure No. 4 SCA Wage Determination - SGP IF Radar Sites.pdf | ||
| ANL-366O - LMH Risk Off-Site Non851 20221021.pdf | ||
| ANL-70B Reps and Certs Long-14-FEB-2025.PDF | ||
| Instructions to Offerors_G5-149039.doc | DOC document | |
| Enclosure No. 2 SGP_Remediation_SOW_IFSites_7.7.25.pdf | ||
| Appendix A-71COM-13-FEB-2023.PDF |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX B – Statement of Work
ARM Climate Research Facility Southern Great Plains (SGP) Site
Statement of Work
Disassembly and Removal of SGP IF Radar Sites
07/072025
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 2 of 7
Contents Contents
Background
Statutory and regulatory requirements
Scope
Safety
Period of Performance
Objectives
Applicable Documents
Site Specific Tasks
IF4 and IF5
Radar
Remediation
Structures
Underground Electrical
Civil
Fence
IF7
Radar
Remediation – Remains in Place
IF8 and IF10
Radar
Remediation
Structures
Underground Electrical
Civil
Fencing
Earth Work
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 3 of 7
Background The DOE ARM Climate Research Facility, Southern Great Plains (SGP) Main Site, located at
109596 Coal Road, Billings, Oklahoma, is disassembling and removing 3 radars and remediate 4 sites. The work will entail dismantling and recycling of the radars along with remediation of the sites by removing infrastructure such as concrete foundations, standard size shipping containers, trailers, and fencing.
Site Locations:
IF4: 6500 Dakota Road Billings, OK, (36.5786, -97.3638)
IF5: 19223 E. Robertson Rd Garber, OK (36.4911, -97.5939)
IF7: 22245 W. Ferguson Ave, Nardin, OK, (36.7961, -97.4490)
IF8: 18895 W. Highland Ave, Tonkawa, OK (36.4771 -97.4210)
IF10: 101752 Custard Road, Lamont, OK (36.6655, -97.6284)
Statutory and regulatory requirements
• OKIE dig prior to any excavation.
• OSHA Fall Protection: 29 CFR 1926.104, 1926.1053, CFR 1926 Subpart L, and 1926.450 through 454.
Scope The contractor shall provide all personnel, facilities, equipment, and general supplies necessary to complete all tasks for all sites along with coordinating efforts to be efficient and timely.
A Laboratory representative shall accompany the contractor while work is being performed and abide by all safety requirements.
Contractor shall disassemble all radars and parts to include the dome, dish, pedestal, elevated platform, and instrument container where noted.
Contractor shall remove structures (communication towers, enclosures), concrete and gravel foundations, and fencing where noted.
Contractor shall fill all holes where concrete was removed. All fill dirt shall be compacted to avoid sinking ground after the remediation. Earth shall be left in natural contour without holes.
All sites shall include grass to stabilize the soil and prevent evrosion.
All radar components must be recycled or destroyed and cannot be resold as a whole or as parts.
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 4 of 7
Safety Contractor shall comply with all applicable OSHA requirements to include but not limited to the following:
1. Assign and document an ESH representative on a JSA. Argonne boiler plate template JSA will be provided after the award for Contractor to fill out with task specifics. Those tasks not being performed shall be removed.
2. Contractor ESH representative must be physically present at the worksite anytime work is occurring.
3. Contractor’s ESH representative must provide a current OSHA 30-hour safety training in General Industry or Construction certification after award of contract to the Argonne Technical Representative.
4. Contractor’s ESH representative shall provide and document job site safety orientation training to all personnel working at the job site. Signature of orientation of each personnel shall be provided daily on the approved JSA.
5. Contractors ESH representative shall perform daily checks, as applicable, including, but not limited to the following:
a. Inspect tools and equipment.
b. Inspect and observe workers' PPE.
c. Inspect and verify qualifications for equipment such as powered industrial trucks and hoisting and rigging equipment.
d. Mark the work area, including proper signage.
e. Manage storage and laydown areas.
6. Contractor ESH representative will be the primary contact to the Argonne Technical Representative and shall provide periodic check-ins and report all incidents.
7. All after-hour work must be approved by Argonne.
8. Contractor shall follow appropriate OSHA standards for fall protection including but not limited to 29 CFR 1926.104, 1926.1053, CFR 1926 Subpart L, and 1926.450 through 454.
a. A full body harness with 100% fall protection is required at all times when working 6 feet above a lower level.
b. Fall protection is required when working on roofs within 15ft of a non-roofing operation.
c. Anchor points used for fall protection shall be capable of supporting a 5,000lb load.
d. Provide training certification for all personnel working at heights.
9. SDS sheets shall be available on site for all chemicals brought and/or used on site.
10. Contractor shall provide a simple lift plan to identify the system and components to be used in the lift, the expected total weights, and the placement of the equipment.
11. Prior to the start of any hauling or dumping operations, the contractor shall provide a spotter to avoid any overhead lines or other obstacles.
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 5 of 7
Period of Performance
Argonne desires for work to be completed by September 30, 2025, but requests the contractor propose their best schedule.
Objectives The objective of this project is to restore several DOE ARM satellite facilities to their natural condition or as requested by the Landowner. While the individual sites are similar, the
Contractor must recognize and understand the differences at each site before submitting a bid.
For instance, at some sites, radars have already been removed, so only site remediation is required. At another site, earth has been displaced to level a fenced-in area, and the Landowner wishes for this to be restored.
Applicable Documents
• Radar installation manual to help guide the dismantling of the radars in reverse order
• Site Drawings and Pictures
• Specification Matrix
Site Specific Tasks
IF4 and IF5
Radar Contractor shall disassemble, remove, and recycle/destroy the X-band radar components (Dome, dish, base, and pedestal) at both sites. The dome is in sections bolted together and then sealed with silicone and may be difficult to separate. Because the components are to be recycled/destroyed, the contractor may remove them in the most economical way possible.
Remediation Contractor shall perform the following:
Structures
• Disassemble and dispose of a 40’ communication towers at both sites. Communications equipment on the towers shall be retained by SGP Personnel.
• Disassemble and remove an 8.5’ x 9’ fiber glass electronics enclosure including the metal instrument rack inside.
• Disassemble and dispose of the steel radar platform.
• Remove and dispose of the 50’ aluminum flagpoles.
Note: Removal of all wiring and computer systems associated with the radars shall be done by
SGP personnel prior to removal of any structures.
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 6 of 7
Underground Electrical
• Remove wire inside of underground conduit from the service disconnect to the radar building and cut off the conduit 24” below the surface and abandon remaining conduit in place.
• Remove all buried grounding circuits and communication lines within the sites.
Civil
• Remove communication towers concrete foundation pads – 90” x 90” x 66” deep
• Remove flagpole foundation pads, 48” x 48” x 68” deep
• Remove radar foundation pads (includes the electronics enclosure foundation), see Radar
Foundation Detail drawing for dimensions (1,500 - 2,000 ft3)
• Remove all gravel within the fence line and dispose of properly
Fill and compact all holes appropriately.
Fence
• Remove and dispose of all 10ft. chain link fence, gates, and poles from each site:
o IF4 320ft (additional 100ft (6’) of fence is not shown in drawing) o IF5 220ft
Note: Pipe (swing) driveway entrance gates for each site shall remain in place.
IF7
Radar Contractor shall disassemble, remove, and recycle/destroy the C-band radar components. The dome is in sections sealed with silicone and may be difficult to separate. Because the components are to be recycled/destroyed, the contractor may remove in the most economical way possible.
Contractor shall remove the 8’ x 8’ x 20’ shipping container and shipped/transported to the SGP main site.
Note: Removal of all wiring and computer systems associated with the radars shall be done by
SGP personnel prior to removal of any structures.
Remediation – Remains in Place No Site remediation at IF7.
IF8 and IF10
Radar Radars have previously been removed from IF8 and IF10
Remediation Contractor shall perform the following:
APPENDIX B – SOW for ARM SGP IF Site Remediation Page 7 of 7
Structures
• Remove and dispose of an 8’x 8’x12’ structures at IF8 and IF10
• Remove and dispose of a communication tower at each site o IF8 40’ o IF10 60’
Underground Electrical
• Remove wire inside of underground conduit from the service disconnect to the radar building and cut off the conduit 24” below the surface and abandon remaining conduit in place.
• Remove and dispose of all buried grounding circuits and communication lines within the sites.
Civil Remove and dispose of the following foundations:
• Communications tower pads, 72”x72”x48” deep
• Electronics Enclosure pads, 168”x132”x24” deep
• Radar pad, 168”x168”x24” deep
• All site gravel within the fence line
• Remove 4 in-ground anchors around the radar pad
• Removal of a 1.5” diameter rain gauge pole set in concrete approximately 36”
Fill and compact all holes appropriately.
Fencing Remove and dispose of all 6’ Chain Link fences, gates, and poles for each site, 32’x48’.
Note: There are no pip entrance gates at IF4&5
Earth Work At the IF8 site, the Contractor is obligated to perform earth-moving activities to facilitate agricultural operations by the Landowner. The grading must be executed in a manner that permits the use of a mower, bushhog, or other farming equipment necessary for the regular maintenance of rotating crops. Pictures of the
IF8 site are provided with this scope, and all prospective bidders shall be afforded the opportunity to conduct an on-site inspection. Following the site visit, a Request for Information (RFI) period will be available prior to the submission of bids.
Appendix A: Pictures and Drawings
IF4 and IF5 IF4&5 Radar pedestal
IF4&5 Radar lower half
IF4&5 Radar Base
IF4&5 Radar Dish
IF4&5 Radar Upper Half
IF4&5 Site Layout
IF4&5 Site Sketch
IF4&5 Radar Foundation Detail
IF7
IF7 Site Layout
IF7 Site Sketch
IF8 and IF10 IF8&10 Site Sketch
Please note that the tower at IF8 is 40' and IF10 is 60'.
IF8&10 Electronics Enclosure
IF8&10 Communications Tower foundation
IF8&10 RWP Foundation
Please note that the RFP has been previously removed from the foundation pad.
| SGP_Remediation_SOW_IF4,5,7,8,10 |
| Appendix A - Pic_Drawings |
| IF4 and IF5 |
| IF4&5 Radar pedestal |
| IF4&5 Radar lower half |
| IF4&5 Radar Base |
| IF4&5 Radar Dish |
| IF4&5 Radar Upper Half |
| IF4&5 Site Layout |
| IF4&5 Site Sketch |
| IF7 |
| IF8 and IF10 |