This is Amendment 0004 to solicitation 47PH5326R0017, issued by the General Services Administration (GSA) PBS Office of Acquisition Management on September 9, 2026. The amendment incorporates questions and answers regarding the submission requirements for offerors and is organized by Uniform Contract Format (UCF) section headings.
The amendment addresses two primary questions: (1) clarification of which blocks on the SF 33 form must be completed for the price proposal, and (2) confirmation of whether offerors must complete Page 2 of the SF 33. The Government confirmed that for the price proposal, offerors must complete Blocks 12, 13, 14, 15A, 15B, 15C, 16, 17, and 18 of the SF 33. For the GLS Max real estate brokerage firm fixed-price solicitation where pricing is expressed in commission rate percentages, offerors are not required to complete Page 2 of the SF 33; instead, all pricing must be submitted using the Updated RFP Attachment 1 - GLS Max Pricing Worksheet provided under AM0001. The amendment was not extended and all other terms and conditions remain unchanged. Contractor signature on this amendment is not required.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PQ1AD
Huy Le, Contracting Officer
The purpose of Amendment 0004 is to incorporate questions and answers via this SF 30.
1. Question 1: RFP - Section A - Solicitation/Contract Form; and L.5.2 Price Proposal - Price Proposal a. SF 33, Solicitation, Offer, and Award i.Blocks 12, 17, 23, 24, and 30 must be completed. Page 63. Instructions on what "Blocks" to complete were not updated when the SF 1449 was swapped out for...
[See Description of Modification Continuation Page]
PBS Office of Acquisition Management/PBS Centralized Acquisition Services Division Customer Contracting Branch B 1900 E Street NW W hi DC 2041 USA
EQ3PRN-25-0001
47PH5326R0017
1 3
9/9/2026
8/6/2026
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Description of Modification Continuation Page
... the SF 33. Will the Government please confirm which blocks the offeror needs to complete.
1a. Answer 1: RFP Page 63, L.5.4. Instructions For Proposals - Price Proposal (a)(i) is hereby corrected to read Blocks 12, 13, 14, 15A, 15B, 15C, 16, 17, and 18 must be completed.
2. Question 2: SF 33 and RFP - ITEM NO. (a) 0001 - The SF 33 contains UNIT PRICE (e) and AMOUNT (f) for supplies and services for the GLS Max real estate brokerage; firm fixed price solicitation. Page 2. Pricing for this solicitation is expressed in commission rate percentages. Will the Government please confirm the offerors are not to complete page 2?
2a. Answer 2: Confirmed. Offerors are not required to complete Page 2 of the SF 33. All pricing must be submitted using Updated RFP Attachment 1 - GLS Max Pricing Worksheet provided under AM0001.
All other terms and conditions remain unchanged.