This document includes a past performance reference questionnaire and details of a federal contract opportunity for construction services. The General Services Administration is seeking a general contractor for an 8(a) small business set-aside to provide construction services for a Customs and Border Protection Seized Cargo Facility project in Detroit, Michigan. The project scope involves renovations to existing office space, construction of a new precast concrete warehouse building addition, and associated site improvements. The contract value is estimated between $1-5 million. The contractor must have experience with precast concrete structures, construction logistics on constrained sites, selective demolition, office tenant improvements, security and IT infrastructure installation, and HVAC modifications. The pre-proposal conference will be held virtually on July 22, 2020, and proposals are due August 25, 2020. Award is targeted for January 2021. The past performance questionnaire is to be completed by references for the offerors and focuses on budget, schedule, staffing, administration, safety, project management, and overall performance.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Source Selection Plan RFP 47PF0020R0040
PAST PERFORMANCE REFERENCE QUESTIONNAIRE
CONTRACTOR:________________________________________
FIRM/KEY PERSONNEL:_________________________________
Reference Information:
Name:________________________________________________ Company:_____________________________________________ Telephone Number:_____________________________________ Title: _________________________________________________ Contract Number: ______________________________________ Location of Contract Performance: _________________________ Completion Date: ______________________________________ Length of time contractor employed: ________________________ Estimated price/cost for services: __________________________ Type of space/building: __________________________________ Type of Contract: ______________________________________ Actual Square Footage: _________________________________ New Construction: _____________________________________ Number of Stories of Bldg: _______________________________ Rehabilitation: __________________________________________
Questions: (Some questions may not apply to roles)
BUDGET
1. Did the contractor complete the project within the original contract budget? If not, what was the reason for the difference in actual costs for the project?
Poor Fair Good Very Good Excellent N/A Comments:
GSA, Region 5 Public Buildings Service Acquisition Management Division 47 May 12, 2020
SCHEDULE
2. Did the contractor cause any delays to the original project schedule? If so, what was the reason for delays?
STAFFING
3. Did the contractor staff the job adequately? Were key personnel adequately qualified for their positions?
ADMINISTRATION
4. How responsive and responsible was the contractor in administrative areas? (e.g.
submitting reports, documenting progress/problems, filing correspondence, tracking changes, responding to Requests for Information (RFI’s), processing payments, etc.)
SAFETY
5. Did the contractor address safety issues? (Developed a good safety plan, followed it, enforced it with subcontractors, posted OSHA information, etc.)
Acquisition Management Division 48 May 12, 2020
PROJECT MANAGEMENT
6. Did the prime contractor manage the subcontractors effectively? (Coordinate work, update them on changes, pay promptly, address work if performance was poor, etc.)
How well did the contractor demonstrate sensitivity to client/tenant concerns (coordination issues, debris, noise, fumes, inconveniences, disruptions within the occupied spaces, etc.)?
PERFORMANCE
7. Overall, how would you rate the contractor’s performance? How would you describe the quality of work? If you had a chance, would you hire the contractor again? Why or why not?
Would you like to make any additional comments, positive or negative, concerning the Offeror’s past performance on your contract(s)?
Acquisition Management Division 49 May 12, 2020
Instructions for Questionnaire
Dear Respondent, The United States General Services Administration would like to thank you for taking the time to assist us in the selection of a 8(a) General Contractor for our Project. Please complete the questionnaire to the best of your ability. We ask that you keep your responses to this questionnaire confidential. The information you provide on this questionnaire will not be shared with the Offeror.
When completed, please send a scanned or electronic copy of the questionnaire to the following e-mail addresses:
anna.vanko@gsa.gov daniel.ramirez@gsa.gov
We ask you to include the following information in the subject line of the e-mail:
Solicitation No. 47PF0020R0040
If you are unable to e-mail the questionnaire, please mail the completed questionnaire to:
U.S.General Services Administration Attention:
Daniel R. Ramirez and Anna Vanko 230 S. Dearborn St Suite 3500 Chicago, IL 60604
If mailed, the questionnaire shall be placed in a sealed envelope with an original signature of the Respondent to the questionnaire across the envelope seal. Include the following statement on the envelope:
Confidential - Information enclosed is for the sole use of the Government.
We ask the questionnaire be returned ON or BEFORE Close of Business August 25, 2020.
We appreciate your time and efforts in assisting us in serving the American public.
Acquisition Management Division 50 May 12, 2020 mailto:anna.vanko@gsa.gov mailto:daniel.ramirez@gsa.gov