47PD0223R0043 RFQ CMS BOCp3_POR 11 9 2023.pdf
PDF 45 MB Posted
- Attached to
- CMS Back on Campus Phase III Federal contract opportunity
- Solicitation number
- 47PD0223R0043
About this file
This request for quotation (RFQ) solicits proposals for the CMS Back on Campus Phase III project. The General Services Administration Public Buildings Service Region 3 is seeking contractors to provide services to help transition federal employees back to in-person work on government campuses. Offerors must submit proposals by November 9, 2023 addressing their ability to provide workspace assessments, reconfiguration, signage and wayfinding, technology deployment, and training and communications services. Award is expected to be made by December 15, 2023 to a single vendor. Pricing shall be fixed for the base period of performance from January 1-December 31, 2024, with two optional one-year renewal periods. This is an unrestricted procurement open to small and large businesses.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTROLLED UNCLASSIFIED INFORMATION (CUI)
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy or return documents when no longer needed
Centers for Medicare & Medicaid Services
Program of Requirements CMS Headquarters Building
7500 Security Boulevard, Woodlawn, MD, 21244 Back to Campus Phase 3
North 3rd Floor
Final Submission October 20, 2023
GSA PROJECT NUMBER: 47PD0223F0014
NKB PROJECT NUMBER: 16320.160
7620 Old Georgetown Road, #728 Bethesda, Maryland, 20814
1020 7th North Street, Suite 130
Liverpool, New York, 13088
FOR OFFICIAL USE ONLY
Back to Campus Phase 3, North 3rd Floor Program of Requirements
FOR OFFICIAL USE ONLY
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY………………………………………………………………….………….
1.1. Introduction and Project Background
1.2. Program of Requirements Summary
1.3. Cost Estimate
1.4. Project Schedule
2. PROJECT OVERVIEW.……………………….………………….…………………………………..
2.1. Project Scope
2.2. Existing Building Information
3. DESIGN REQUIREMENTS…………………….…………………………………..….……………..
3.1. Applicable Codes, Federal Regulations and Guidelines
3.2. P-100 Exclusions
3.3. ABAAS Compliance
3.4. Energy Conservation and Sustainable Design
4. SPACE AND OCCUPANCY…………………….…………………………………..….……………
4.1. Program Methodology
4.2. Space Measurements
4.3. Space Program
4.4. Functional Relationships
5. ARCHITECTURE………………………….……………………………..……………………………
5.1. Applicable Codes and Standards
5.2. Existing Building
5.3. Interior Partitions
5.4. Doors
5.5. Finishes – General
5.6. Finishes – Wall
5.7. Finishes – Floor
5.8. Finishes – Ceiling
5.9. Casework
5.10. Accessories
5.11. Interior Signage
5.12. Furniture, Fixtures & Equipment (FF&E)
FOR OFFICIAL USE ONLY
6. STRUCTURAL………………………….………………………………..……………………………
6.1. General Structural Loading
7. HVAC……………………………………………………………………………………………………
7.1. Design Conditions
7.2. Codes and Standards
7.3. Load Calculations
7.4. Inside Design Conditions
7.5. System Description
7.6. Building Commissioning
8. PLUMBING………………………………………….…………………………….…..………………
8.1. Codes and Standards
8.2. Existing Domestic Water System
8.3. New Domestic Water System
9. ELECTRICAL……………….…………………………………………….……………………………
9.1. Codes and Standards
9.2. General Electrical
9.3. Power Distribution System
9.4. Variable Frequency Drives
9.5. Branch Wiring
9.6. Pathways
9.7. Interior Lighting
9.8. Elevator Modernization Support
9.9. Emergency Lighting and Power
9.10. Grounding
9.11. Equipment Labeling
9.12. Short Circuit, Selective Coordination, and Arc Flash Study
10. TELECOMMUNICATIONS AND SECURITY…………….………….………………….…………
10.1. Codes and Standards
10.2. General Telecommunications
10.3. Telecommunications Rooms
10.4. Horizontal Cabling
10.5. Outlets and Floor Boxes
10.6. Audio / Visual
10.7. Public Address and Sound Masking Systems
10.8. CATV
10.9. ACS
FOR OFFICIAL USE ONLY
10.10. DAS
10.11. BAS
10.12. Elevator Modernization Communications Support
10.13. Cable Testing
11. FIRE PROTECTION..…….………………………………….………….………………….…………
11.1. Codes and Standards
11.2. Fire Alarm
11.3. Fire Suppression
12. VERTICAL TRANSPORTATION……………………………….…….………………………..……
12.1. Codes and Standards
12.2. General
12.3. Existing Equipment
12.4. Vertical Transportation Equipment
12.5. Control Equipment
12.6. Hoistway Equipment
12.7. Car Frame, Platform and Enclosure
12.8. Door Operator and Opening Devices
12.9. Car, Hall, and Security Fixtures
12.10. Wiring, Conduit, and Traveling Cables
12.11. Fasteners
12.12. Identification Signage and Data Plates
13. APPENDICES
A. Space Program…………………………………………………….………………………..…….
B. Conceptual Plan / Code Drawing / Phasing Plan……………….…………………….……….
C. Space Data Sheets………………………………………………….…………………………….
D. Elevator Finish Drawing…………………………………………………………………………..
E. Responsibility Matrix ………………………………………………….………………………….
F. Deliverables Matrix……....………………….…..…………...……………………………..…….
G. Commissioning Plan……....………………….……………...……………………………..…….
FOR OFFICIAL USE ONLY
FOR OFFICIAL USE ONLY
1. EXECUTIVE SUMMARY
1.1. Introduction and Project Background
N.K. Bhandari, Architecture and Engineering, P.C. has been contracted by the General Services
Administration (GSA) to provide Design Build (D-B) procurement documents for the renovation of the 3rd Floor of the North Building of the Centers for Medicare and Medicaid Services (CMS)
Headquarters campus located on the campus at 7500 Security Boulevard in Woodlawn, Maryland.
This renovation is the third phase in the renovation and modernization of the CMS campus as envisioned in the May 2018 Master Plan. Previous renovations provide guidance to this Program of Requirements as to spatial layout, aesthetics, and materials of construction that will bring consistency to the design and construction of the third-floor renovation.
The North Building consists of a three-story rectangular shaped building which houses Class A office space, contains an approximate gross floor area of 222,350 square feet and was constructed in early 1995. The third floor is approximately 64,000 gross square feet and consists of a core area with elevators and mechanical space surrounded by open floor plate for office and support functions.
1.2. Program of Requirements Summary
The programmatic data included in this POR has been collected through an interactive process of interviews and work sessions with the tenant agency representatives. With the information gathered, the resulting POR is a design tool, serving as the basis for a future design team’s work in the production of Design Intent Drawings and ultimately Construction Documents. This document serves to assist in assuring the new facility will perform in a manner that satisfies the programmatic design requirements for CMS.
The following process and methodology to obtain, analyze and interpret the data contained in this report:
• Members of the project team held an initial orientation meeting to review project scope
FOR OFFICIAL USE ONLY
and purpose. The objective of this meeting was also to familiarize the CMS representatives with the facility programming process.
• CMS representatives were interviewed to develop an understanding of the space requirements regarding personnel and support space. GSA authorized representatives, CMS staff and the NKB team conducted a walkthrough of the existing facilities.
• Existing building construction drawings were reviewed as provided by the GSA and on-site observations of existing building systems were performed.
• CMS staff provided staff and spatial information for the CMS Departments that will occupy the third-floor post-renovation, and design direction for General Unassigned space.
Programming information is intended to capture projected needs based on the best available current information. As the project progresses into design, program requirements shall be confirmed and updated so that the evolving design remains current with CMS program needs.
Likewise, the project must be reviewed with users at the design development and construction document stages to confirm that all program requirements have been met.
The programmatic summary is as follows:
1.3. Cost Estimate
A Rough Order of Magnitude for the associated costs of construction is based on the content of this POR. The Design Builder shall produce a cost proposal as required by GSA procedures.
The Estimated Construction Cost (ECC) with assumptions and contingencies is thought to be between $25M - $35M.
FOR OFFICIAL USE ONLY
1.4. Project Schedule
A conceptual schedule has been generated in collaboration with GSA and represents phasing and durations based on the current information available at the time of this report. The schedule is subject to change, and the Design Builder shall prepare a project schedule per GSA procedures.
DB Contractor Notice to Proceed (NTP) Aug 2024
Peer Review Post Award & Integrated Design Review (IDR) Oct 2024
OPR Review, Validation, & Finalization Aug 2024
Post-award Design Phase Services Dec 2024
Construction Start Apr 2025
Construction Substantially Complete Apr 2026
Agency Occupancy May 2026
FOR OFFICIAL USE ONLY
2. PROJECT OVERVIEW
2.1. Project Scope
The renovation of the North Building 3rd Floor of the Centers for Medicare and Medicaid Services
(CMS) headquarters is the third phase of the implementation of a 2018 Master Plan which envisioned the housing and capital needs of the CMS Headquarters over 25 years.
The project is a Design Build effort to completely renovate approximately 63,400 gross square feet of office and support spaces on the Third Floor of the North Building and the upgrade and refurbishment of the North Building passenger elevators. Work to renovate the Third Floor and the elevators will require design and construction outside the confines of the third floor to support infrastructure or cosmetic improvements.
The work to demolish and reconstruct office and support spaces will require phasing and relocation in collaboration with GSA and CMS to accommodate staff currently housed in those spaces. It is currently envisioned that the work will occur in at least three phases, comprising of roughly half of the project scope area, such that certain staff will only require a single relocation.
The upgrades of elevators will require extensive collaboration with building managers to determine allowable outages and disruptions in service.
Collaboration with CMS vendors (e.g. furniture, audio / visual, security, etc.) is required of the
Design Builder to ensure a comprehensive design. CRI is the required vendor for all security scope. Artwork and sculptures within the area of work shall be removed and reinstalled by a professional, RFAO-approved fine arts handler during construction. Temporary storage will be in a GSA warehouse. The Design Builder shall use the Responsibility Matrix included in this
Program of Requirements, and verify requirements at the time of design, to identify third-party vendors.
The Design Builder shall incorporate the agency’s technical, functional, and spatial requirements in the conceptual design, detailed options, associated cost estimates, and in the final detailed architectural and engineering solution. The design shall adhere to appropriate codes, regulations, FOR OFFICIAL USE ONLY
GSA design guidelines, and be informed by the evolving technical and aesthetic standards being implemented by GSA and CMS in previous renovations at the facility.
2.2. Existing Building Information
Specific information regarding the existing building has been provided within the Basis of Design narratives of each discipline in this Program of Requirements. In addition to its own survey of existing conditions to verify and record information, the Design Builder shall request and secure existing building information from GSA at the outset of design. The following documents and information are available to the Design Builder:
• Building Engineering Report (Faithful + Gould, September 2017)
• CMS Master Plan (MGA Partners Architects, May 2018)
• CMS As-Built drawings (limited, does not include all systems)
• CMS CAD drawings (limited, does not include all systems)
• CMS Back to Campus Phase 1 Record Documents
• CMS Back to Campus Phase 2 Record Documents
FOR OFFICIAL USE ONLY
3. DESIGN REQUIREMENTS
3.1. Applicable Codes, Federal Regulations and Guidelines
The Design Builder is responsible for identifying and complying with all applicable codes and regulations. At a minimum, all design and construction work performed for this project shall comply with the most recent editions of the following building codes, federal regulations, and guidelines:
• International Building Code (IBC, 2021 with 2022 Addendum); or most current edition
• NFPA 101 Life Safety Code (National Fire Protection Association), 2021
• NFPA 13 and NFPA 72 (National Fire Protection Association) for fire sprinkler and fire alarm systems, 2022
• Architectural Barriers Act Accessibility Standard (ABAAS), 2010 or most current edition
• U.S General Services Administration’s (GSA) Facilities Standards for the Public Buildings
Service (PBS-P100, 2021 with 2022 addendum); or most current edition
Additional requirements can be found in the Basis of Design of each discipline in this Program of
Requirements.
3.2. P-100 Exclusions
All submissions must comply with the prescriptive and baseline performance requirements of the
PBS-P100, Facilities Standards for the Public Buildings Service. Project teams must establish minimum performance requirements in planning. They must also consider possible performance enhancements that benefit the mission, sustainability, and ownership cost of the specific facility or of GSA’s portfolio in general.
Any anticipated departures below the minimum requirements of the PBS-P100 must be submitted by the project team in a P100 waiver and approved by the chief architect and the assistant commissioner for project delivery. The process for submitting variances is outlined in GSA regulations.
FOR OFFICIAL USE ONLY
3.3. ABAAS Compliance
ABAAS compliance is mandatory for all GSA projects. The intent of this policy is to use standard building products set at prescribed heights and with prescribed maneuvering clearances to allow easy access by disabled employees and visitors. Building elements designated specifically for use by persons with disabilities should be kept to a minimum.
CMS, throughout its implementation of campus improvements, has striven to provide the highest standard of accessibility. The Design Builder shall seek opportunities to rise above minimum
ABAAS requirements and provide design and features that further this goal.
3.4. Energy Conservation and Sustainable Design
The Government does not intend to seek third-party sustainable building certification of the project.
In support of the Government’s lead in environmental stewardship, and CMS’ desire for a sustainable footprint, the project shall integrate sustainable strategies and features into the design to minimize the energy consumption of the facility; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health and comfort. The design and construction shall incorporate sustainable design strategies and features to the fullest extent possible, consistent with GSA P-100 requirements, however LEED certification is not required.
FOR OFFICIAL USE ONLY
4. SPACE AND OCCUPANCY SUMMARY
4.1. Program Methodology
The POR was developed from field investigations, review and subsequent discussion of the current situation and an assessment of planned future requirements.
• Field Investigation: The design team conducted a field investigation of the existing space and recently renovated floors to identify existing building conditions and the design logic of recent renovations.
• End User Interviews: Meetings were held with CMS Staff to review findings from the field investigation and to validate CMS provided information regarding space planning and program needs.
• Follow-Up Meetings: Additional meetings were held with CMS Staff to review preliminary space plans to better understand specific needs and to define the project program included in this document.
4.2. Space Measurements
The space calculations document basic Net Square Feet (NSF) defined as the space assigned to an individual function, such as an office or conference room. This number is measured from inside the walls of the space and does not include wall thickness or circulation.
The sum of all individual room/area NSF quantities for each occupant or space is supplemented by an internal circulation factor (approximately 1.6) to arrive at Usable Square Feet (USF). This circulation allowance accounts for access to and movement among interior room and areas as well as area(s) needed for internal subdividing partitions. The combination of the programmed net area and the circulation allowances results in the total Building Owners and Managers Association
(BOMA) USF for each occupant.
An additional factor is applied to the USF, to determine Gross Square Footage (GSF). GSF includes all floor area of a building that is totally enclosed within the building envelope including
Building or Floor Common Areas, such as:
• Public Elevators / Public Elevator Lobby
FOR OFFICIAL USE ONLY
• Exit Stairs
• Building Data and Communication Equipment Closets
• Electrical Equipment Closets
• Mechanical Equipment Closets
• Risers for Tenant Data and Communication Cables
• Public Telephone Alcove
• Public Men’s and Women’s Restrooms
• Custodial Storage w/Mop Sink and Recycling Storage
• Fire Closet
• Building Entry Lobby w/Security Screening Stations
• Building Circulation
Utilization Rate (UR) is used to compute the square footage allowed for space. It is a target or benchmark for the average usable square feet per person for office (including enclosed and open offices), office support space, meeting spaces, and circulation associated with those spaces. CMS has established a goal UR of 135 USF.
The UR does not apply to storage spaces or building ‘special’ spaces that unique functions that are constructed, maintained, or operated significantly differently than standard office space.
4.3. Space Program
Refer to the Appendix for the Space Program for the CMS North Building Third Floor renovation.
4.4. Functional Relationships
Refer to the Appendix for the Conceptual Plan for the CMS North Building Third Floor renovation.
The designer of record shall determine the final arrangement of space through collaboration with
GSA and CMS. The following, by department, are criteria expressed during the development of this Program of Requirements.
General Design Guidance:
• Departments shall be located in a single cohesive arrangement, with all
FOR OFFICIAL USE ONLY
functions co-located.
• Create a wide area with collaboration spaces at each entry.
• Enlarge all corridors beyond minimum widths to increase navigation ease for all.
• Locate Trash / Recycle and Print / Copy areas in each department space so that they are not immediately visible upon entering a suite.
• Locate Private Offices away from exterior windows as much as possible to allow daylight to penetrate each suite.
• Provide multiple environments for collaboration within each suite.
OACT:
• Department shall be located in a single cohesive arrangement, with all functions co-located.
• Private Offices do not open to workstations to provide additional privacy.
• May be located near OEOCR.
OEOCR:
• Department shall be located in a single cohesive arrangement, with all functions co-located.
• Due to the sensitive nature of the department’s function, OEOCR shall be partitioned from the main building corridor with openings protected by card-access secure doors.
• Department-only Pantry provided, as staff does not use main pantry.
• Reception space designed in a way to provide visual privacy and minimize direct line of sight through the entire suite.
• To be located furthest from the “link” bridge to the Center Building and in close proximity to an elevator lobby and stair to provide a sense of privacy for visitors coming and going from the suite.
• May be located near OACT.
FOR OFFICIAL USE ONLY
Unassigned General:
• The Conceptual Plan in this Program of Requirements was developed to house the above departments as a priority, with the remainder of third floor space being reserved for yet-unknown departments.
• The design of the Unassigned General follows the design logic and language set forth in the Master Plan. The final layout and logic must follow the needs of any department that is identified at the time of final design.
FOR OFFICIAL USE ONLY
5. ARCHITECTURE
5.1. Applicable Codes and Standards
The design of alterations shall adhere to the following codes and standards:
• GSA PBS P-100, Facilities Standards for the Public Building Service (PBS-P100)
• NFPA 101 Life Safety Code (National Fire Protection Association), 2021
• 2021 International Existing Building Code (IEBC)
• 2021 International Building Code (IBC)
• Architectural Barriers Act Standards (ABA)
5.2. Existing Building
The interior of the existing building shall be prepared for a complete interior renovation with the total demolition of interior partitions (consisting of metal stud with gypsum wallboard partitions), finishes, and non-structural building features as necessary. The existing structural system
(columns, beams, and slabs) shall remain with no significant modifications. The building exterior envelope including framing, insulation, glazing, and facade shall not be disturbed other than the internal face of gypsum wallboard as necessary.
Existing office furniture shall be removed and disposed of by Design Builder.
Due to the age of the building, hazardous materials are not thought to be present within the existing building.
Existing building firestopping and fireproofing shall be amended or replaced as necessary to provide all required ratings and protections.
5.3. Interior Partitions
Interior partitions shall generally be constructed of metal stud and gypsum wallboard in type and construction suitable to required acoustical performance, fire rating, and structural stability.
Additional framing and GWB shall be provided to accommodate higher ceilings, where existing interior or perimeter walls are only constructed to existing ceiling heights. Partition construction
FOR OFFICIAL USE ONLY
shall include water-resistant sheathing at spaces receiving ceramic tile. Fire-retardant blocking shall be included at partitions where necessary for the support of D-B and Government provided items. The minimum STC rating shall be 50 for all interior gypsum wallboard partitions. Partitions shall be constructed from the top of Raised Access Floor to underside of deck above. In the condition where existing partitions are removed that were constructed from the floor slab through the raised access flooring, or if new partitions are constructed through the raised access floor, the raised access floor must be reconstructed to create a complete and sound system.
Office and Support spaces shall receive Demountable Partitions as indicated in the Space Data
Sheets, with a minimum STC rating of 39. Demountable Partitions shall be single glazed, ½” laminated glass, and include integral door and frame from same manufacturer as part of a complete system. All glass partitions shall receive patterned film from 2’-0” to 7’-0”, with partial glass partitions from bottom of glazing to 7’-0”.
5.4. Doors, Frames, and Hardware
Interior doors shall be solid core wood doors with a laminate face or veneer and have an opaque finish. Hollow metal doors shall be provided in service areas. Door frames must be welded heavy duty hollow metal. Hardware must be heavy‐duty commercial grade. See Space Data Sheets for individual space passage or lockset type. Provide card access and security features at designated spaces or suites. Doors shall be coordinated with the performance requirements of the spaces they serve to provide suitable visibility/light levels, fire ratings, and acoustic performance.
5.5. Finishes - General
CMS desires to standardize the aesthetic and design language of its interior spaces to maintain cohesive experience for occupants and visitors to its Campus. With that goal in mind, the Design
Builder shall reference the previously completed project known as “CMS Back to Campus Phase
2” and familiarize itself with the materials and application of finishes. In subsequent narrative, this shall be referred to as “CMS Aesthetic Guidelines”.
Elevator finishes can be found in this Program of Requirements in the Elevator Section and attached Appendix drawing.
FOR OFFICIAL USE ONLY
5.6. Finishes - Wall
Office and Support space wall finish shall be generally eggshell finish white paint, with accent eggshell finish paints applied in a similar color and pattern to the CMS Aesthetic Guidelines. Walls shall include a 4” rubber base generally, and ceramic base where ceramic floors are scheduled.
Corridor walls shall employ a 5-1/2” high x 1” deep maple wood chair rail with (3) 1/8” stainless steel strips by length of rail.
12mm acoustic semi-ridged wall panels made from materials with a Flame-Spread Rating of less than 25 and a Smoke-Developed rating of less than 450 shall be placed in Conference Rooms, Huddle Rooms, Training/Classrooms, other collaboration spaces, Elevator Lobby, and in entry vestibules to mitigate sound reverberation.
Full-height corner guards, formed of 16ga. stainless steel with 2” legs, shall be located at all outside corners of new and existing gypsum wallboard partitions.
Restroom spaces shall be 2” x 8” porcelain wall tile, biscuit type, with similar base material and pigmented grout.
5.7. Finishes - Floor
Office and Support space floor finish shall be generally carpet tile fitted to the existing raised access floor system. A maximum of (2) colors of carpet tiles shall be included in (2) installation methods to achieve a similar aesthetic to the CMS Aesthetic Guidelines.
Elevator lobby floors shall be patched as necessary with two tones of epoxy terrazzo to match adjacent surfaces.
Restroom spaces shall be 32” x 32” porcelain floor tile and pigmented grout. The porcelain tile is to be rated PEI Class 3 or higher. Existing restroom floors will need to be modified through appropriate means to match required floor height.
FOR OFFICIAL USE ONLY
5.8. Finishes - Ceiling
Office and Support space ceiling finish shall be generally 2’ x 2’ fiberglass acoustic ceiling panel with sound absorption qualities (NRC 0.90 - 1.00), in a suspended 9/16” metal grid. Design shall include accent ceilings, consisting of GWB soffits and linear simulated wood, fiberglass panel systems, and/or gypsum wallboard ceiling surfaces, in the type, manner, and construction as indicated in the CMS Aesthetic Guidelines. Acoustic ceiling panel systems throughout the project shall be generally 9’-0” in Corridors and 9’-6” in Office Spaces.
The accent linear wood ceilings located at the entrance of each suite, social spaces, and in the main corridor, are to be at 9’-6” with the adjacent gypsum wallboard ceilings at 9’-0”.
The Link corridor ceiling finish basis-of-design shall be the Accent Torsion Spring Series full panel at 9’-0”. Design shall be consistent with previous projects at CMS Headquarters.
5.9. Casework
Casework shall be plastic laminate faced architectural millwork of the size and location as depicted in the Space Data Sheets. Countertops shall be solid surface.
5.10. Accessories
Toilet accessories shall be stainless steel commercial grade items, selected in accordance with
CMS building management standards. Toilet enclosures shall be ceiling hung solid phenolic, and urinal screens wall-hung, complying with ABAAS guidelines and inclusive of necessary hardware.
Glass mirrors shall be custom sized to toilet rooms and accessibility requirements.
For ceiling hung phenolic systems, provide manufacturer's standard corrosion-resistant anchoring assemblies with leveling adjustment nuts at pilasters for connection to structural support above finished ceiling. Provide assemblies that support pilasters from structure without transmitting load to finished ceiling. Provide sleeves (caps) at tops of pilasters to conceal anchorage.
All exterior windows shall be provided with motor-operated custom single roller shades with 3% openness factor. Shades shall be recessed in a pocket, similar to recent projects in CMS
FOR OFFICIAL USE ONLY
Headquarters. Rollers shall be constructed of corrosion-resistant steel or extruded-aluminum tubes of diameters and wall thicknesses required to accommodate operating mechanisms and weights and widths of shadebands indicated without deflection. Rollers shall have permanently lubricated drive-end assemblies and idle-end assemblies designed to facilitate removal of shadebands for service. Motor control shall operate the roller shades from an individual switch control station and be capable of accepting connection to the building automation control system.
Black-out shades are required in conference and training spaces.
5.11. Interior Signage
The primary goal of signage is to provide information to the users and visitors of a building to facilitate wayfinding through the building. By identifying the traffic flow of an area, the positioning and quantity of signage may be determined. The signage system is directly related to the spatial structure of a location. The signage should always be located at decision points, and on long paths, the information should be reinforced to assure people they are heading in the correct direction to their destination. Identification signs should then be located at the destinations to which people have been directed, to confirm their arrival at the destination they have been seeking.
Signage Placement Guidelines:
• Signage to be placed at circulation nodes where people congregate naturally and circulate.
• Locations will be identified to make the most effective use of the least amount of signs.
• Signs will be mounted to the wall (permanent fixture), either flat or perpendicular (in blade mount).
• When there are many signs to be grouped together, these will be mounted to create an information node (they should not be touching each other).
Signage Product Guidelines:
• Provide signage per code requirements and as noted here. If there is a conflict between these requirements and code requirements, code requirements supersede.
FOR OFFICIAL USE ONLY
• Sign sizes vary depending on the type of sign that is required. The use of standard sized modules will make the signage more comprehensive since the users will look for the same format to get the information they need. Signs describing the same action should have the same size.
• Permanent rooms numbers and permanent room types are to be indicated on room signs as both tactile and raised Braille characters. Indented characters shall not be used. Braille characters may be located within an incised area on the face of a sign.
• Where International Symbol of Accessibility is required, specify raised pictogram.
Symbols, tactile and raised Braille characters are to all follow ABAAS standards.
Accessibility:
The interior signage at Centers for Medicare & Medicaid Services aims to be accessible to all. By standardizing the signage family, the facility allows an ease of recognition and prevents users from having to adapt to several signage types. Below are some of the aspects of signage that are implemented to encourage accessibility:
• Cubicle signage shall have tactile and raised braille characters
• Uniform approach to all signage in each location.
• Logical positioning of signage with respect to its function.
• Color contrast (foreground/background): 70% minimum
• Short, easy to understand message.
• Matte finish sign surface
• Installation of wall sign: median horizontal line of lettering at 62” from the floor
• Identification of a locale: on the wall adjacent to the door, at approximately two inches from the frame, on the door handle side.
• Identification of service areas made clear with the incorporation of appropriate pictograms.
Technical Requirements:
• Text Font: Avenir Black & Avenir Roman
• ADA Tactile Numbers & Grade II Braille
FOR OFFICIAL USE ONLY
• 2 Ply Multi-Layered Fire-Retardant Thermo-Foil Sheet w/ Class A Decorative & Surface
VOC Free Digitally Printed Copy where applicable
• Removeable Aluminum Accent
• 3 Ply Non-Glare Acrylic Construction Subsurface VOC Free Digital Printed Copy &
Graphics and Laminate Header where Applicable
• Non-Glare Removeable Lens, Acetate Insert & Removeable ACM Background Panel w/
Surface Digitally Printed Background Color
• 75% Recycled Aluminum Anodized Holder; Mechanically Fastens to the Wall
(Limits Future Wall Damage)
• Component Based System w/ Spring Clips Loading for Interchangeable Variable Depth
Media
• 2 Ply 3/16” Frosted Acrylic Beveled Panel w/ Subsurface Color/Graphic & Surface
Printed Copy Adhered to 1/16” Clear Acrylic Backer & Subsurface Background
• Individual Sign Finishes:
o Satin Aluminum o GOW o Anigre
Type A – Directionals Primary and Secondary
• Wall Mount
• Primary Overall Size: 26.75”H x 17”W
• Secondary Overall Size: 14.75”H x 17”W
• Header o GOW text color o Floor Number Text Font: Avenir Black o Floor Name Text Font: Avenir Roman o Central Building indicated by Blue Circle color & graphic on header.
o North Building indicated by Green Lines color & graphic on Header.
o South Building indicated by Yellow Triangles color & graphic on header.
o Anigre Accent
• Satin Aluminum frame finish
FOR OFFICIAL USE ONLY
• GOW Center Panel finish
Type B – Overheads
• Overall Size: 6”H x 44”W
• Background color is to be GOW with text color to match individual building zone color:
o Central Building indicated by Blue Circle color & graphic.
o North Building indicated by Green Lines color & graphic.
o South Building indicated by Yellow Triangles color & graphic.
o When sign is located above a directory the background color is to be GOW with text color to match individual building zone color.
Type C - Elevator Branding
• Panel – Large Image and Floor Number o Overall Size: 48”H x 72”W o Mounted on ¾” Round Satin Silver Standoffs, ¾” Barrel Dept o Text color to be GOW.
o Background color to match building zone color:
Central Building indicated by Blue Circle color & graphic.
North Building indicated by Green Lines color & graphic.
South Building indicated by Yellow Triangles color & graphic.
• Floor ID:
o Overall Size: 20”H x 15”W o Wall Mount o Header
GOW text color
Floor Name Text Font: Avenir Roman
Central Building indicated by Blue Circle color & graphic on header.
North Building indicated by Green Lines color & graphic on Header.
South Building indicated by Yellow Triangles color & graphic on header.
o Floor Number
FOR OFFICIAL USE ONLY
Size: 8” x ¼” Aluminum Cut-Out
Silver Finish
Text Font: Avenir Black o Floor Name
Size: 2” x ¼” Aluminum Cut-Out
Silver Finish
Text Font: Avenir Roman
• Directory:
o Wall Mount o Overall Size: 20”H x 11”W o Large Vertical Pocket with Header o Header
Anigre Finish
Black Text
Type D - Building Threshold ID
• Overall Size: 12”H x 80”W
• Sign to match building zone color when located by itself (see below):
o Central Building indicated by Blue Circle color & graphic.
o North Building indicated by Green Lines color & graphic.
o South Building indicated by Yellow Triangles color & graphic.
Type E - Projecting Signage
• Blade Mount
• Overall Size: 9”H x 9”W
• Satin Aluminum mounting plate
• Background Color: GOW
• Text Color: Black
Type F - Cubicle / Department ID Panel Sign with pocket inserts
FOR OFFICIAL USE ONLY
• Wall Mount Panel with center panels mounted on ¾” Round Satin Silver Standoffs, ¾”
Barrel Dept.
• Cubicle signage shall have tactile and raised braille characters.
• Overall Size: 36”H x 20”W o Background color to match building zone color:
Central Building indicated by Blue Circle color & graphic.
North Building indicated by Green Lines color & graphic.
South Building indicated by Yellow Triangles color & graphic.
o Text Color: GOW o Center panels to have satin aluminum frame with acrylic pocket for 8 ½” x 11” client provided insert.
Type G – Trash and Recycling Receptacle
• Adhesive backed decal to be stuck on backsplash of trash and recycling station for each trash and recycling collection bin.
• Overall size, graphics and background color to match existing trash and recycling signage for continuity of message and design.
Coordinate all signage info, font type, size and with Centers for Medicare & Medicaid Services.
5.12. Furniture, Fixtures & Equipment (FF&E)
Refer to Responsibility Matrix for Design Builder and Government provided FF&E. Design Builder to coordinate all FF&E.
FOR OFFICIAL USE ONLY
6. STRUCTURAL
6.1. General Structural Loading
Compliance with the IBC occupancy/use minimum concentrated live loads is required. Local administrative and building system equipment loads must be accommodated. Where encountered, specialized and/or concentrated loads from new building system equipment or fixtures must be accommodated.
Various loading capacities exist within the facility, and the Design Builder should review the existing building documents and existing conditions for analysis of new work.
High-volume storage solutions, if requested by the facility, require structural analysis and design for floor loading and bracing.
FOR OFFICIAL USE ONLY
7. HVAC
7.1. Design Conditions
Outdoor Design Conditions (2021 ASHRAE Fundamentals):
• Location o City Name: Baltimore Downtown o Location: Maryland o Latitude: 39.281 degrees o Longitude: 76.611 degrees o Elevation: 20 feet
• Summer Design o Dry Bulb Temperature: 95.5 °F (ASHRAE 0.4%) o Mean Coincident Wet Bulb Temperature: 75.6 °F (ASHRAE 0.4%)
• Dehumidification o Dry Bulb Temperature: 83.2 °F (ASHRAE 0.4%) o Dew Point Temperature: 74.9 °F (ASHRAE 0.4%)
• Winter Design o Dry Bulb Temperature: 16.8 °F (ASHRAE 99.6%)
• Humidification o Mean Coincident Dry Bulb Temperature: 19.4 °F (ASHRAE 99.6%) o Dew Point: -4.3 °F (ASHRAE 99.6%)
7.2. Codes and Standards
The following codes and standards apply to this project:
• 2021 International Mechanical Code
• American Society of Heating, Refrigerating & Air Conditioning Engineers (ASHRAE) o 90.1-2019 - Energy Standard for Buildings Except Low-Rise Residential Buildings o 62.1-2019 – Ventilation for Acceptable Indoor Air Quality o 55-2020 – Thermal Environmental Conditions for Human Occupancy
FOR OFFICIAL USE ONLY
o 135-2020 – BACnet A Data Communication Protocol for Building Automation and
Control Networks
• ASHRAE Handbooks o 2019 HVAC Applications o 2020 HVAC Systems and Equipment o 2021 Fundamentals o 2022 Refrigeration
• ASHRAE Sound and Vibration Control
• Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) standards
• P100 Facilities Standards for the public building service, October 2021 with 2022
Addendum
• 10 Code of Federal Regulation (CFR), Part 434
7.3. Load Calculations
Heat dissipation for building occupants and equipment shall be based on Chapter 18 of the 2021
ASHRAE Fundamentals handbook. Heating and cooling load calculations must be performed with a computer-based program using the latest ASHRAE Handbook of Fundamentals Heat
Balance (HB) Method, Radiant Time Series (RTS) Method, or Transfer Function Method (TFM), developed for the hourly analysis of heating and cooling loads in commercial buildings.
The program must be capable of calculating each zone’s peak heating and cooling loads as well as the whole-building simultaneous peak load. The program must, at a minimum, calculate solar gains through fenestration; internal gains from occupants, including latent heat for cooling purposes; internal gains from lighting and equipment; outside air loads (sensible and latent) from ventilation and infiltration; and heat and moisture gains or losses through fenestration, walls, floors, and roofs. The heating load calculations must be done without credit for occupants and internal gains. The HVAC load calculations must not include additional safety factors unless specifically asked for in the applicable tenant design guides.
FOR OFFICIAL USE ONLY
7.4. Inside Design Conditions
Existing AHU humidification system is no longer in service, provide psychrometric calculations to determine relative humidity based on existing Air Handling Unit (AHU) performance. The inside temperature and humidity conditions must comply Section 5.1 Mechanical Performance Table within P100-2021v2. The following design conditions must be met in the different space classifications within the building:
Space Summer Winter
Temperature* Humidity* Temperature* Humidity*
Conference 75° F db 50% RH 72° F db 30% RH
Office 75° F db 50% RH 72° F db 30% RH
Corridor 75° F db 50% RH 72° F db 30% RH
Storage 85° F db 50% RH 65° F db 30% RH
Break Room 75° F db 50% RH 72° F db 30% RH
Elevator Machine Room 78° F db 60° F dp 55° F db UC
Telecom Room 68°-72° F 50% RH 68°-72° F 30% RH
Electrical Room 78° F UC 55° F db UC
Mechanical Room** N/A N/A N/A N/A
Restrooms*** N/A N/A N/A N/A
UC: Uncontrolled N/A: Not Applicable *P100-2021 w/ 2022 Addendum, Humidifier is not available in existing AHU.
**Mechanical room is used as an air mixing plenum for the AHU.
***Exhaust ventilation only.
7.4.1. Equipment and Lighting Loads
The following equipment and lighting loads shall be used to calculate the cooling loads for the building (Note: These typical loads were utilized to develop the report. More detailed equipment and lighting loads must be provided during the design to include elevator and elevator machine room):
FOR OFFICIAL USE ONLY
Space Equipment Load Lighting Load*
Watts/ft2
Offices 100 Watts/Work Station 0.64
Conference 2 Watts/ft2 0.64
Break Room 5 Watts/ft2 0.64
Storage N/A 0.64
Telecom 15 Watts/ft2 0.64
Corridors N/A 0.64
Restroom N/A 0.64
*Per ASHRAE 90.1-2019, Building Area Method
7.4.2. Occupancy Loads and Ventilation Requirements
8. Ventilation rate must be calculated per ASHRAE 62.1-2019 Ventilation Rate Procedure method only. Ventilation schedule is required for all spaces and included room number, room name and use, floor area, number of occupants, outside air, supply air, return air, and exhaust air. The following occupant densities and ventilation or exhaust rates shall be used in establishing ventilation requirements for specific areas:
Space Occupant Density
Persons/ft2 Minimum Ventilation
Requirements*
Offices 1 Person / 200 ft2 5 CFM/Person + 0.06 CFM/ft2
Conferences 1 Person / 150 ft2 10 CFM/Person + 0.18 CFM/ft2
Break Rooms 1 Person / 150 ft2 10 CFM/Person + 0.18 CFM/ft2
Corridors N/A 0.06 CFM/ft2
Telecom N/A N/A
Janitor’s Closets N/A 1 CFM / ft2 (Exhaust)
Restrooms N/A 50 CFM / WC, Urinal (Exhaust)
9. *Per ASHRAE 62.1-2019
10. WC = Water Closet
FOR OFFICIAL USE ONLY
7.4.3 HVAC Noise Control
Per P100-2021.v2, the noise criteria must follow the table below:
Space Descriptor
Mechanical
Noise Range
(RC/NC)*
Training rooms Deskbound, interactive 30 min – 35 max
Meeting rooms Frequent tele/video conferencing Infrequent tele/video conferencing
Less than 6 person capacity
20 min – 30 max 30 min – 35 max 30 min – 35 max
Private offices High speech privacy
Normal speech privacy, deskbound, concentrative Normal speech privacy, internally mobile, interactive
35 max 35 max
35 min – 40 max
Quiet rooms Individual or small group, interactive
Individual or small group, concentrative 35 min – 40 max
35 max Misc. enclosed spaces Short occupancy, no speech privacy 35 max
Open plan offices High density occupancy, internally mobile or interactive Low density occupancy, deskbound, concentrative
40 max
35 min – 40 max *Per P100-2021.v2
7.5 System Description
7.5.1 Existing Chilled Water System
An existing central chiller plant serves the campus with two types of chilled water systems: general chilled water and ADP chilled water. The general chilled water is available all year long and is controlled with a temperature setback during unoccupied hours. The ADP chilled water is available all year long. There are two existing chilled water risers located in the North Building 3rd floor mechanical rooms. The 3rd floor is divided into two segments, segment 5 and 6. Each mechanical room has 2-1/2” ADP chilled water supply and return (ACHS/R) and 3” general chilled water supply and return (GCHS/R) risers, shown in Figure 1. The general chilled water currently serves two (2) AHUs. The existing fan coil unit that serves the telecom rooms is supplied with
ACHS/R, shown in Figure 2.
FOR OFFICIAL USE ONLY
Figure 1. Chilled Water Pipe Risers in 3rd Floor Mechanical Room N3-09-00.
Figure 2. FCU in 3rd floor telecom room.
FOR OFFICIAL USE ONLY
7.5.2 Existing Heating Water System
An existing central boiler plant serves the campus with heating hot water. 2-1/2” heating hot water risers are in segment 5 mechanical room that serves the North Building 3rd floor. The heating hot water serves two (2) glycol heat exchangers and the fan powered box reheat coils. The glycol heating hot water system in shown in Figure 3. The glycol heating hot water system will remain to serve the existing heating and ventilation unit.
7.5.3 Demolition Heating Water System
The existing heating hot water piping will require demolition from the Fan Powered Box (FPB) reheat coils up to the main heating hot water pipe distribution loop on the 3rd floor. Demolition of the 3rd floor heating hot water system will include, but not limited to, pipes, coils, supports, valves, controls, and other associated appurtenances.
7.5.4 New Heating Hot Water System
Provide heating hot water system for the 3rd floor to serve the new FPB with reheat coils. The new heating hot water system will include, but not limited to, pipes, coils, supports, valves, controls, and other associated appurtenances. The heating hot water system will serve the fan powered box reheat coils on the 3rd floor.
Figure 3. Glycol Heating Hot Water System for Heating and Ventilation Unit.
FOR OFFICIAL USE ONLY
7.5.5 Existing Air Distribution System
Two (2) air handling units (AHU) currently serve the North Building 3rd floor. One AHU serves the east half of the floor and the other serves the west half. Each AHU is sized to serve the entire floor. The ductwork for both systems are interconnected for redundancy. The AHU utilizes campus general chilled water for cooling. The AHU is equipped with MERV 10 pre-filter and MERV 10 final filter for filtration. There was an abandoned steam humidifier in the AHU that was recently replaced with a UV light system. The facility maintenance personnel noted that the steam humidifier was disconnected because the steam was condensing on the cooling coil instead of humidifying the supply air. The AHU supply fan is equipped with VFD, the fan typically operates at low speeds since building is rarely at peak capacity. The supply fan, installed in 1994, is original, but some parts have been replaced over the years. While the supply fan is currently operational, it has surpassed its intended lifespan of 25 years per 2019 ASHRAE Handbook HVAC
Applications. The mechanical room is under negative pressure since the room is used as a mixing plenum for return and outside air. The return air is pulled from the ceiling plenum so all items in the ceiling plenum must be plenum rated. The outside air damper control is tied to the CO2 sensor that is mounted at the return air plenum opening.
The outside air is delivered to each mechanical room from a roof mounted Heating and Ventilation
(H&V) system, shown in Figure 5. The H&V system is equipped with MERV 10 filter. The H&V system heats the outside air with a glycol heating system located in the 3rd floor mechanical rooms.
FOR OFFICIAL USE ONLY
Figure 4. 3rd Floor AHU in Mechanical Room
Figure 5. Heating and Ventilation Unit With Glycol Heating Hot Water on Roof.
FOR OFFICIAL USE ONLY
7.5.6 Demolition Air Distribution System
Contractor will be responsible for adequately confirming system operation and configuration prior to commencing demolition work.
All branch ducts up to the main duct air distribution will require demolition. All equipment and accessories such as, but not limited to, fan powered boxes, grilles/diffusers, controls, supports, and associated appurtenances must be demolished to create space for new air distribution system.
7.5.7 New Air Distribution System
A UV coil disinfection project was recently completed, and therefore the existing UV light system will remain. Record documents can be obtained through CMS facilities group. The final filter in each AHU must be upgraded to MERV 13.
Provide FPB with reheat coils to serve the new architectural layout. Each zone must be served by a series fan powered box terminal unit with hot water reheat coils. Each FPB must be equipped with MERV 13 filters. FPBs in each zone must provide Variable Air Volume (VAV) for conditioning and maintaining the offices at a positive pressure relative to surrounding spaces and the outdoor environment. Each FPB must be provided with a local thermostat capable of local control by +/-
3 °F of room temperature setpoint. The humidity in each zone must not exceed 55 °F dewpoint temperature when occupied and 60 °F dewpoint temperature when unoccupied.
The HVAC thermal zoning must comply with Section 5.1 Mechanical Performance Table within
P100-2021v2.
Occupied office and administrative areas shall be designed with ventilation and occupancy rate shown in Section 1.1.6. All supply air ductwork shall be externally insulated. Internal duct liners shall not be used in supply or return ductwork.
The 3rd floor pressurization must comply with Section 5.1 Mechanical Performance Table within
P100-2021v2. The exterior zones shall be maintained at a positive pressure with respect to the outside to mitigate outside air infiltration and moisture migration through the building envelope.
FOR OFFICIAL USE ONLY
7.5.8 General Building Exhaust
The restroom and janitor spaces are served with the general exhaust system. General exhaust fans are scheduled from the BAS scheduler. Existing exhaust fans will remain in service to serve
3rd floor restroom and janitor spaces.
7.5.9 Telecom Rooms
The telecom rooms must be served by a dedicated fan coil unit (FCU) that utilizes the ADP chilled water (ACHS/R) for cooling source. Each FCU must have a dedicated thermostat and be integrated into existing Building Automation System (BAS).
7.5.10 Mechanical Rooms
The mechanical rooms serve as an air mixing plenum, which does not adhere to the current code specified in P100-2021.v2 section 5.3.3.2 regarding outdoor air intake locations. However, since this building is already existing and designed in this manner, the replacement of AHUs and updating controls are not within the scope of this project.
7.5.11 Electrical Rooms
The electrical rooms are equipped with a constant exhaust ventilation system that draws makeup air from the return air ceiling plenum. The exhaust fans are constant air volume and operates 24/7 all day. The existing exhaust fan will continue to operate and serve the electrical rooms on the
3rd floor.
7.5.12 Elevator Machine Room
Provide mechanical upgrades in the elevator machine rooms to meet current International
Building Code and ASME A17.1 requirements. The elevator machine rooms are conditioned with existing ADP chilled water fan coil units with exhaust ventilation. The existing FCUs are at end of useful life. Demolish existing FCUs and provide new chilled water FCU.
This is the start of the file's text. The full file is on GovTribe.