This document is a past performance questionnaire for a design/build contractor supporting the CMS Back on Campus Phase III Project. The General Services Administration is soliciting feedback on a contractor's previous work through completion of the attached questionnaire by January 8, 2024. The questionnaire requests ratings and comments on management, construction, close-out/warranty, and overall performance for the identified project. It will be used to evaluate contractors for solicitation 47PD0223R0043 for the CMS Back on Campus Phase III project by the General Services Administration Public Buildings Service Region 3. Responses should be emailed to the lead contracting officer with a copy to the contract specialist by the due date.

View the file

Other files for this federal contract opportunity

Other files attached to CMS Back on Campus Phase III, newest first.
File Type Posted
47PD0223R0004 CMS Back on Campus PH1 Amendment 0002 12 10 2023.zip ZIP file
47PD0223R0043 CMS Back on Campus Phase III Amendment 0002 12 10 2023.pdf PDF
7PD0223R0043 CMS Back on Campus Pictures Zip File Amendment 0002 12 10 2023.zip ZIP file
47PD0223R0043 CMS Back on Campus Phase III Kickoff Meeting Site Visit Sign In Sheet 11 28 2023.pdf PDF
47PD0223R0043 CMS Back on Campus Phase III Revised Solicitation 12 7 2023.pdf PDF
47PD0223R0043 CMS Back On Campus Phase III Amendment 0001 12 7 2023.pdf PDF
47PD0223R0043 CMS Back on Campus Phase IIII RFI Log Response 12 7 2023.pdf PDF
47PD0223R0043 CMS Back on Campus Phase III Pre-Proposal Agenda 11 28 2023.pdf PDF
47PD0223R0043 RFQ CMS BOCp3_POR 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS BOCp3_Ahearn Torres Art Move SOW 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS BOCp3_Design Deliverable Summary 11 9 2023 .pdf PDF
47PD0223R0043 RFQ CMS BOCp3_Attic Stock Minimums 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS BOCp3_DB SOW 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS Site Visit Form 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS Back on Campus Phase III PP Questionaire Lead Design Firm 11 9 2023.docx DOCX document
47PD0223R0043 RFQ FY23 CEW-Version Nov 2022 11 9 2023.xls XLS spreadsheet
47PD0223R0043 RFQ CMS Security Vendor Requirements 11 9 2023.pdf PDF
47PD0223R0043 RFQ DB_Solicitation CMS BOC Phase III 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS Back on Campus Phase III DB_Agreement 11 9 2023.pdf PDF
47PD0223R0043 RFQ CMS Back on Campus Phase III DB GC Reps and Certs 11 9 2023.docx DOCX document
47PD0223R0043 RFQ Design Change Log 11 9 2023.xlsx XLSX spreadsheet
47PD0223R0043 RFQ CMS BOCp3_Division 01 Specifications 11 9 2023.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The General Services Administration is evaluating past performance in selecting a design/build contractor for the CMS Back on Campus Phase III Project in Woodlawn, Maryland. You have been identified as someone who could attest to the quality of the offeror’s performance on the project listed below. Your completion of the attached questionnaire would be of great benefit in selecting the most qualified firm to perform this project.

Completed questionnaires will be considered procurement sensitive information and will not be seen or reviewed by the offeror in question or any other party not having a need to know.

References will be contacted by the General Services Administration requesting they email the completed Past Performance Questionnaire, which is due on Monday, 8 January 2024 by 2 PM EST. The Past Performance Questionnaire is to be submitted electronically to Mr. Raymond J Porter, Lead Contracting Officer, at email raymondj.porter@gsa.gov with a courtesy copy to the GSA Contract Specialist Shane O'Brien at email shane.obrien@gsa.gov.

OFFEROR BEING EVALUATED:

PROJECT BEING EVALUATED:

NAME OF EVALUATOR:

EVALUATOR’S AGENCY/COMPANY:

EVALUATOR’S ROLE IN PROJECT:

EVALUATOR’S EMAIL ADDRESS:

EVALUATOR’S TELEPHONE NUMBER:

PAST PERFORMANCE QUESTIONNAIRE – PRIME CONTRACTOR

CMS Back on Campus Phase III Project

SECTION 1 – NUMERICAL RATINGS

Please indicate your level of satisfaction with the contractor’s performance on the project in question by placing an “X” in the appropriate block using the rating scale provided to the right of each question. This scale is defined as follows:

RATING PERFORMANCE LEVEL

5 EXCELLENT – The contractor’s performance met all contractual requirements and exceeded many to the Government’s or customer’s benefit. The few corrective actions that may have been necessary were provided expeditiously and were highly effective.

4 GOOD - The contractor’s performance met contractual requirements and exceeded some to the Government’s benefit. Performance was provided with some minor problems, but corrective action was prompt and effective.

3 ACCEPTABLE – The contractor’s performance met contractual requirements. There were minor problems but the corrective actions taken were generally satisfactory.

2 MARGINAL – The contractor’s performance did not meet some contractual requirements. There were significant problems with the contractor’s performance and the corrective action provided was only marginally effective or was not fully implemented.

1 UNACCEPTABLE – The contractor’s performance did not meet most contractual requirements and corrective action was untimely, ineffective or both.

NNOT APPLICABLE – Unable to provide a rating
MANAGEMENT
5
4
3
2
1
N

Exhibits professional conduct

Cooperation/responsiveness is timely, provides/solicits feedback, suggests alternatives

Offeror is easy to work with, friendly, courteous

Provides effective oversight of project managers/superintendents

Quickly and professionally resolves issues/disputes

Reviews and addresses subcontractor issues

Provides a clear and effective line of supervision on the worksite

Follows and maintains the established project budget

Follows the negotiated subcontracting plan

CONSTRUCTION
5
4
3
2
1
N

Complies with laws and regulations

Coordinates and controls subcontractors, adheres to work schedule

Maintains good construction pace and work environment

Site management – materials are properly stored and staged, job-site is clean

Adheres to an adequate initial project schedule, schedule revisions are timely submitted

Resolves delays in a timely manner

Completes punch list items in a timely manner

Uses specified materials

Identifies and corrects deficient work timely and effectively

Implements and follows a satisfactory safety plan

Provides high quality workmanship

QC testing is adequate and fully implemented

CLOSE-OUT/WARRANTY
5
4
3
2
1
N

Requirement documents are fully submitted

Documents are submitted in a timely manger

As-built drawings – redline drawings are accurately maintained on site per specs

Close-out documents follow the required format

Responses to warranty issues are timely and effective

Noted deficiencies are adequately corrected

OVERALL PERFORMANCE
5
4
3
2
1
N

Overall performance – Likelihood of contracting with this firm on future projects

SECTION 2 – NARRATIVE COMMENTS

Please provide in the spaces below any additional comments you have regarding the offeror’s performance on the project in question:

1. Strengths of Performance:

2. Weaknesses of Performance:

3. Describe the contractor’s level of attention to safety and describe any incidents that occurred on the project:

4. Additional Comments: