Sol 47PD0121R0001 C201 GC Solicitation.pdf

PDF 286 KB Posted

Attached to
Perimeter East Building Renovation and Upgrades Construction Project at the SSA Complex in Woodlawn, MD
Solicitation number
47PD0121R0001
Issued by

About this file

This document provides information regarding a forthcoming solicitation for construction services. The General Services Administration intends to issue a Request for Proposal for renovations to the Perimeter East Building on the Social Security Administration campus in Woodlawn, Maryland. Renovations will include approximately 90,000 square feet on the fourth floor for tenant improvements, two new exterior stair towers, smoke control system upgrades in the lobby, and HVAC work on other floors. The project will also renovate the cafeteria kitchen and serving area. An option exists to fully upgrade the mechanical infrastructure, including four new rooftop air handling units. The estimated total construction cost is between $30-50 million. Competitive proposals are due by November 30, 2020 with award planned for the week of February 8, 2021. A pre-proposal conference will be held at the campus with registration required. The source selection will utilize the tradeoff process to select the best value proposal based on price and technical factors including project management, experience, past performance, small business subcontracting, and any project labor agreement.

View the file

Other files

File Type Posted
Solicitation Amendment 47PD0121R0001_0008.pdf PDF
DOL General Decision Number MD20200030 Mod 10 dtd 12_11_2020.pdf PDF
Amendment 007 - Pre-Bid RFI responses.pdf PDF
Solicitation Amendment 47PD0121R0001_0007.pdf PDF
Solicitation Amendment 47PD0121R0001_0006.pdf PDF
Pre-Bid RFIs Responses - Amendment 006.pdf PDF
Bid Bond form - SF24.pdf PDF
Solicitation Amendment 47PD0121R0001_0005.pdf PDF
Amendment 0005 - Small Business Utilization Form.pdf PDF
Solicitation Amendment 47PD0121R0001_0004.pdf PDF
Pre-bid Photo Album No. 2 _11_12_2020.pdf PDF
Pre-bid Photo Album No. 3_11_12_2020.pdf PDF
Pre-Bid RFIs - Amendment 004.pdf PDF
Solicitation Amendment 47PD0121R0001_0003.pdf PDF
Pre-bid Photo Album No. 1.pdf PDF
Site Walk-Through Attendance List.pdf PDF
PEB Pre-Proposal Conference - Minutes 11.12.20.pdf PDF
Solicitation Amendment 47PD0121R0001_0002.pdf PDF
Amendment Number 0001 - pre-proposal information.pdf PDF
Amendment 0001 - SSA Complex 0001.pdf PDF
Amendment 0001 - PEB Parking Lots.pdf PDF
Solicitation Amendment 47PD0121R0001_0001.pdf PDF
Sol. 47PD0121R0001 C301 GC Rep and Cert.pdf PDF
Sol 47PD0121R0001 C101 Agreement.pdf PDF
47PD0121R0001 SF 1442.pdf PDF
DOL General Decision Number MD20200030 Mod 08 dated 10_09_2020.pdf PDF
PEB 4th Floor and Infrastructure and Cafeteria Exp Bid Sheet 10-22-20.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Solicitation No.: 47PD0121R0001

Document: C201-GC/JULY 2020 (The Solicitation)

Construction Contract for: Perimeter East Building (PEB) Renovation and Upgrades Construction Project

The Solicitation

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers

II. Proposals

A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI)

Building Information

J. INFORM 2.0

IV. FAR/GSAR Solicitation Provisions A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR 101-29 B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of

Federal Specifications, Standards and Commercial Items Description C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal

Employment Opportunity for Construction F. FAR 52.225-10 Notice of Buy American Requirement-Construction Materials G. Buy American Exceptions H. FAR 52.233-2 Service of Protest I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference K. Small Business Subcontracting Plan L. Project Labor Agreement M. Additional Provisions

(i) GSAR 552.236-74, Evaluation of Options and or Alternate (Mar 2019)

(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options and or Alternate (Mar 2019)

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition B. Security Requirements

VI. Method Of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offers

V.I Additional Clauses

Notice of Equal Employment Opportunity (EEO) Compliance Plan

GSA has partnered with the Department of Labor to ensure compliance with equal employment opportunity requirements that apply to this project. An EEO Compliance Plan is required after the award.

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer.

No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award

(4) The Agreement and Attachments to the Agreement

(5) The PEB IFC and Cafeteria Construction Specification Packages, Drawings and Agreement attachments.

All documents listed above will be uploaded to the Contract Opportunities page on www.beta.SAM.gov under the Notice ID# 47PD0121R0001. These will be posted as restricted access. Offerors shall request access to GSA Contracting Officer, Anthony Teti, via email at Anthony.teti@gsa.gov.

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information (Primary Point of Contact)

Authorized Representative Information:

Name: Anthony Teti Address: 100 S. Independence Mall West, Philadelphia PA 19106 Telephone: (215) 765-5252 Email: Anthony.teti@gsa.gov

Contract Specialist Information (Secondary Point of Contact) Name: George Garcia Address: 100 S. Independence Mall West, Philadelphia PA 19106 Telephone: (215) 313-1692 Email: george.garcia@gsa.gov

I.D. Pre-Proposal Conference

Due to current GSA travel restrictions and various state restrictions on gatherings due to the ongoing COVID-19 pandemic, GSA may hold a pre-proposal conference virtually. All significant questions will be answered in an amendment to the RFP that will be posted on Beta.Sam.gov.

The Pre-proposal will be held as follows:

Date: To Be Determined Time: To Be Determined

I.E. Estimated Price Range In accordance with GSAR 536.204, the estimated price range for the Project is between $30,000,000 and $50,0000,000.

I.F. FAR 52.228-1 Bid Guarantee (Sep 96)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)

(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.

(2) Site Visits – Please see Section ‘I.D. Pre-Proposal Conference’ above.

I.H. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 1:00 pm EST on the following date and at the following address.

Date: December 07, 2020 Address: anthony.teti@gsa.gov and george.garcia@gsa.gov

The Technical and Price proposal must be submitted as separate PDF documents in an email. All proposals must be received by the specified closing date and time. Files shall not contain classified data. The Technical Proposal shall not contain any price information. The use of hyperlinks is prohibited.

(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.

(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

2. Technical Proposal

3. Representations and Certifications

4. Standard Form 24, Bid Bond

5. Subcontracting Plan

6. The Technical Proposal shall consist of the following factors:

1. Project Management and Staffing Plan

2. Prior Experience on Relevant Projects

3. Past Performance

4. Subcontracting Plan Methodology

5. Project Labor Agreements

7. Price Proposal – This proposal must be separate from the technical proposal, and must contain the following information:

1. Signed SF-1442, including acknowledgement of all amendments (if any)

2. Completed and Signed Bid Sheet

3. GSA Form 527-99a – Contractor’s Qualification and Financial Information

4. Bid Guarantee

5. Subcontracting Plan

8. Evidence of current VETS-4212 Registration (such as the registration confirmation email). Registrations can be accomplished at https://www.dol.gov/vets/vets4212.htm.

9. If applicable, Joint-Venture Agreement and any Mentor-Protégé Agreements

II.B. Proposal Format

All proposals and modifications to the proposals shall be submitted electronically via email to anthony.teti@gsa.gov and george.garcia@gsa.gov. The offeror shall submit their proposal in Portable Document Format (PDF) with a total file size of less than 10MB. It is recommended the offeror submit their proposal to the aforementioned emails with a read receipt request.

The Technical and Price proposal must be submitted as separate PDF attachments in an email.

All proposals must be received by the specified closing date and time. Files shall not contain classified data. The Technical Proposal shall not contain any price information. The use of hyperlinks is prohibited.

The submission shall be clearly indexed and logically assembled. Each proposal shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. A Table of Contents should be created using the Table of Content feature in MS Word. MS Word (doc) files shall use the following page setup parameters:

Margins – Top, Bottom, Left, Right – 1”

Gutter – 0”

From Edge – Header, Footer 0.5”

Page Size, Width – 8.5”

Page Size, Height – 11”

The proposal should clearly demonstrate that the Offeror has a thorough understanding of the project. Statements made by the Offeror that he/she understand, can or will meet the solicitation requirements or paraphrasing the solicitation or parts thereof will be considered inadequate.

Phrases such as “Standard procedures will be employed” or “well known techniques will be used” will also be considered inadequate. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked. Submissions of marketing brochures are not acceptable unless provided as supplementary information only.

Notwithstanding any other statement in the solicitation, the technical proposals must not exceed the following page limitations:

1) Technical Factor #1: Project Management and Staffing Plan (25 single-sided)

2) Technical Factor #2: Prior Experience (10 pages single-sided)

3) Technical Factor #3: Past Performance (10 pages single-sided)

4) Technical Factor #4: Subcontracting Plan Methodology (10 pages single-sided)

5) Technical Factor #5: Project Labor Agreement (10 pages single-sided)

NOTE: Proposals that exceed the required page limitations will not be evaluated. All pages (including table of contents, cover pages, etc.) will be counted towards the indicated page limitation unless it is otherwise stated in the solicitation.

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 with all the amendments , with prices and/or rates indicated for each price element shown on the pricing form included in form SF 1442.

Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

(3) Project Labor Agreement

Offerors may submit a price proposal subject to the Project Labor Agreement (PLA) requirements set forth in this solicitation (a PLA proposal), a price proposal not subject to the PLA requirements set forth in this solicitation, or both. Any price proposal submitted shall clearly identify whether it is a non-PLA proposal or PLA proposal.

FAR 52.222-34, Project Labor Agreement, states that a “Project Labor Agreement” means a pre-hire collective bargaining agreement with the labor organizations having jurisdiction over the trades involved in the construction of the project that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C.

158(f).

A proposal submitted subject to the PLA requirements set forth in this solicitation will receive additional consideration under this evaluation factor. A proposal submitted not subject to such PLA requirements will receive no consideration under this evaluation factor

II.D. Technical Proposal

The Technical Proposal shall include the information requested below for the non-price factors described in Section VI:

3. Past Performance on Relevant Projects

4. Subcontracting Plan Methodology

5. Project Labor Agreements

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).

(2) Qualifications of Offerors

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract. Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

II.F. Requirements of Joint Venture Offerors

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.

III.B. Requests for Clarification or Interpretation

All Requests for Clarification or Interpretation (RFI’s) must be received by no later than

2:00 pm EST on November 16, 2020.

The Government will attempt to answer all requests for clarifications or interpretations of the

Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 10 calendar days. Prospective Offerors should make such requests not less than 10 calendar days prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results

This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.

III.E. Affirmative Procurement Program

GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.

III.F. Notice Concerning Preparation of Proposals

Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.G. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.

III.H. Contractor Performance Information

(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process.

CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment

Completed CPARS evaluations are sent to the Past Performance Information Retrieval System (PPIRS) which may then be used by Federal acquisition community for use in making source selection decisions. PPIRS assists acquisition officials by serving as the single source for contractor past performance data.

(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS.

The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.

(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.

(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information

Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

III.J. INFORM 2.0

A. Overview of the IN-depth Feedback through Open Reporting Methods (INFORM 2.0)

Process

This solicitation is part of an initiative using the INFORM 2.0 process which is designed to enhance the quality and usefulness of post-award communications by providing greater transparency and openness into the procurement process. INFORM 2.0 seeks to increase GSA-industry communication by providing clearer and more complete information to explain the award decision.

Through the INFORM 2.0 process, GSA will seek to share additional information with offerors in writing and/or through an oral feedback meeting that is not required by statute or regulation. For purposes of this solicitation, and in addition to any information required by FAR 15.503 and 15.506, GSA is providing each offeror with the opportunity to participate in the INFORM 2.0 process as further discussed below.

B. Detailed Description of the INFORM 2.0 Process

B.1. Component 1 - Notification of Award

After award and in accordance with any post-award notification timeframes required by regulation (i.e., FAR Parts 15.503(b) and 16.505(b)(6)), the contracting officer will issue written notices to the successful and unsuccessful offerors (the Notification of Decision Statement (NODS)). The notices will contain:

● All information required by statute or regulation;

● An unredacted copy of the complete technical evaluation for that particular offeror that includes a full description of the unsuccessful offeror’s strengths, weaknesses, risks, and deficiencies;

● An overall technical evaluation summary for that particular offeror and the successful offeror that includes evaluated price; overall technical ranking, rating, or score.

B.2. Component 2 - Request for Oral Feedback Meeting or Written Questions

Within three business days after receipt of the NODS, an offeror may, but is not required to:

● submit a written request to the contracting officer for an oral feedback meeting;

● submit a list of written questions to the contracting officer; or

● take no further action.

If the offeror timely elects to request an oral feedback meeting or submit a list of written questions, GSA will consider any such request to constitute a required debriefing pursuant to FAR 15.506. If an offeror does not request an oral feedback meeting or submit a list of written questions within the three day time period, the receipt of the NODS concludes the INFORM 2.0 process and satisfies the FAR requirement for debriefs pursuant to FAR 15.506.

If the offeror submits a list of written questions in lieu of the oral feedback meeting, the contracting officer will attempt to respond within five business days of receipt of the written questions. Unless otherwise stated, the contracting officer’s response to the written questions will conclude the INFORM 2.0 process and any corresponding post-award debriefing as further set forth at FAR 15.506.

If the offeror requests an oral feedback meeting, the offeror should provide the following information:

● Primary point of contact;

● List of participants with titles (e.g., Senior Vice President);

● List of topics to assist GSA better prepare for the oral feedback meeting; and

● Preference for in-person, telephone, or web-based conferencing (if available).

B.3. Component 3 - Oral Feedback Meeting

During the oral feedback meeting, GSA’s objectives are to provide:

● Reasonable responses to written questions submitted by the offeror;

● Explanations for the evaluation conclusions and contract award decisions;

● Any additional information about the fairness and impartiality of the evaluation and why the award decision was rational;

● Reasonable responses to additional questions raised during the meeting;

● Additional transparency into the underlying competition process; and,

● A greater understanding of the evaluation and award process.

GSA will not provide any information that is prohibited by law or regulation.

B.4. Component 4 - Post Oral Feedback Meeting Questions

Within two business days after the conclusion of the oral feedback meeting, the offeror may submit a list of written questions to the contracting officer. The contracting officer will provide a written response within five business days and, unless otherwise noted by the contracting officer, the INFORM 2.0 process and any corresponding postaward debriefing as further set forth at FAR 15.506 will have concluded.

If the offeror elects not to submit a list of written questions within two days after the oral feedback meeting, the INFORM 2.0 process and any corresponding post-award debriefing as further set forth at FAR 15.506 is concluded.

IV. FAR/GSAR Solicitation Provisions

IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (AUG 98)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407

Telephone (202) 619-8925 Facsimile (202) 619-8978

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

IV.B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (JUN 1988)

(Applicable to solicitations that cite specifications not listed in the Index and are not furnished with the solicitation)

(a) The specifications cited in this solicitation may be obtained from: GSA Specifications Unit at (202) 755-0325. MIL Specifications may be obtained by calling (215) 697-2179.

(b) The request should identify the solicitation number and the specification required by date, title, and number as cited in the solicitation.

IV.C. FAR 52.216-1 Type of Contract (APR 84)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

IV.D. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work

(MAY 14)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

IV.E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

23% 6.9%

These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order

11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is:

State: Maryland City: Woodlawn County: Baltimore

IV.F. FAR 52.225-10 Notice of Buy American Requirement—Construction Materials.

(MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American—Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

IV.G. Buy American Exceptions

For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement

IV.H. FAR 52.233-2 Service of Protest (SEP 06)

(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

IV.I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 98)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:

Federal Acquisition Regulation

NUMBER TITLE DATE

52.214-34 Submission of Offers in the English

Language

APR 91

52.215-16 Facilities Capital Cost of Money JUN 03 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns

OCT 14

52.236-28 Preparation of Proposals - Construction OCT 97

IV.J. GSAR Clause 552.102 Incorporating Provisions and Clauses

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

IV.K. Small Business Subcontracting Plan

A Small Business Subcontracting Plan, as required under FAR 52.219-9, is required to be submitted with offers.

IV.L. Project Labor Agreement (PLA)

(1) This Project Labor Agreement section only applies to proposals submitted subject to the

PLA requirements of this solicitation.

(2) FAR 52.222-33 Notice of Requirement for Project Labor Agreement (May 2010) Alternate 1 (DEVIATION July 2011)

(a) Definitions. “Labor organization” and “project labor agreement,” as used in this provision, are defined in the clause of this solicitation entitled Project Labor Agreement.

(b) The apparent successful offeror shall negotiate a project labor agreement with all labor organizations having jurisdiction over the trades involved in the construction of the project.

The project labor agreement must be signed by all such labor organizations and cover the entirety of the construction work to be performed during the term of the resulting construction contract.

(c) Consistent with applicable law, the project labor agreement reached pursuant to this provision shall—

(1) Bind the offeror and all subcontractors engaged in construction on the construction project to comply with the project labor agreement;

(2) Allow the offeror and all subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;

(3) Contain guarantees against strikes, lockouts, and similar job disruptions;

(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;

(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and

(6) Fully conform to all statutes, regulations, Executive orders, and agency requirements.

(d) Any project labor agreement reached pursuant to this provision does not change the terms of this contract or provide for any price adjustment by the Government.

(e) The apparent successful offeror shall submit to the Contracting Officer a copy of the project labor agreement prior to contract award.

(3) The requirements of 52.222-33 Alt I are supplemented as follows:

(a) The project labor agreement reached pursuant to FAR 52.222-33 Alt I shall supersede the terms of any other collective bargaining agreement that conflict with the terms of such project labor agreement.

(b) Within 30 days following receipt of written notification to the apparent successful offeror by the Contracting Officer, the apparent successful offeror shall furnish the Contracting Officer with a copy of an executed project labor agreement that meets the requirements of this Section. If, for any reason, the apparent successful offeror fails to furnish such project labor agreement within the time stated above, the Government may, in its sole discretion, eliminate the proposal from consideration and select the next apparent successful offeror.

IV.M. Additional Provisions

(i) GSAR 552.236-74, Evaluation of Options and or Alternate (Mar 2019)

The Government will evaluate offers for award purposes by adding the total price for all options and or Alternates to the total price for the basic requirement. Evaluation of options and or alternates will not obligate the Government to exercise the option(s) and or alternate(s).

(End of provision)

(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options and or Alternate

(Mar 2019)

(a) The Government may exercise any option and or alternate in writing in accordance with the terms and conditions of the contract within sixty (60) days of NTP.

(b) If the Government exercises the option and or alternate, the contract shall be considered to include this option and or alternate clause.

V. Instructions and Clauses

V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (Jan 2017)

(a) Definitions. As used in this provision.

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.

“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals.

(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show.

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

(3) Submission, modification, revision, and withdrawal of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and.

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award.

Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225- 17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall.

(1) Mark the title page with the following legend:

This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed.in whole or in part.for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of.or in connection with.the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend:

Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(f) Contract award.

(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after…

This is the start of the file's text. The full file is on GovTribe.