This document outlines a federal construction contract opportunity for renovations and upgrades to the Perimeter East Building at the Social Security Administration campus in Woodlawn, Maryland. The General Services Administration will issue a Request for Proposal for approximately $30-50 million in construction work including renovating 90,000 square feet on the fourth floor, adding two exterior stair towers, upgrading the smoke control and building automation systems, renovating the cafeteria kitchen, and an option for mechanical infrastructure upgrades. The construction manager will be Hill International. Proposals are due by November 30, 2020 and award is planned for the week of February 8, 2021. A pre-proposal conference will be scheduled. Interested parties should monitor beta.sam.gov for the solicitation and any amendments. Inquiries should be directed to the specified email.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Initials: _________
SSA Perimeter East Building (PEB) 4th Floor & Infrastructure Upgrades & Cafeteria
Bid Sheet
OFFER SHEET – ADDENDUM TO SF 1442
1. The contractor shall provide all management, supervision, labor, materials and equipment in accordance with the scope of work and Government provided documents.
2. The contractor shall include all mark-ups, including overhead, profit and bonds, in their proposal.
3. This proposal is made in full compliance with all the terms and conditions of this Solicitation, the latest applicable Davis Bacon Wage Decision, and any amendments.
4. The breakdown below is necessary to account for numerous government funding accounts and to help evaluate the offers.
PEB 4th Floor Fit-Out
1. Base Bid
General Conditions $__________________
Demolition $__________________
Concrete $__________________
Masonry $__________________
Metals $__________________
Wood, Plastics, & Composites $__________________
Thermal & Moisture Protection $__________________
Openings / Doors & Windows $__________________
Finishes $__________________
Specialties $__________________
Equipment $__________________
Furnishings $__________________
Conveying Equipment $__________________
Fire Suppression $__________________
Plumbing $__________________
HVAC $__________________
Electrical $__________________
Communications $__________________
Electronic Safety & Security $__________________
Earthwork $__________________
Exterior Improvements $__________________
Utilities $__________________
Building Automation System $__________________
Overhead $__________________
Bonds $__________________
2. Grease Interceptor
Grease Interceptor (all work associated with removal and replacement) $__________________
Bond $__________________
3. Unit Prices
Fireproofing Type 1 Reapplication Assume 635 linear feet $__________________
Fireproofing Type 2 Reapplication Assume 216 linear feet $__________________
Fireproofing Type 3 Repair Fireproofing
Assume 95 repairs. Unit is per repair. $__________________
Fireproofing Type 4 Repair Fire Proofing at Existing Equipment Hangers Assume 95 repair. Unit is per repair. $__________________
Fireproofing Type 5 Repair Fireproofing at Existing Conduit Rerouting Assume 95 repair. Unit is per repair. $__________________
Fire Safing Type 1 Repair Fire Safing at Existing Penetrations Assume 62 penetrations . Unit is per penetration. $__________________
Fire Safing Type 2 Repair Fire Safing at Existing Ceiling/Floor Penetrations Assume 7 penetrations. Unit is per penetration. $__________________
ACM Floor Tile and Associated Mastic Assume 1,900 SF. Unit is per SF. $__________________
Core Drill ACM Floor Tile and Associated Mastics
Assume 16 ea. Unit is per location. $__________________
ACM Mastics and Sealants Associated with Fiberglass Duct Insulation on Ducts and Air Handling Units. Assume 9,421 SF. Unit is per SF. $__________________
ACM Mastics and Sealants Associated with Metal Fan Coil Units and Metal Exhaust Ducts. Assume 2,124 SF. Unit is per SF. $__________________
ACM Mastics on Fiberglass Pipe Insulation
Assume 8,905 LF. Unit is per LF. $__________________
Fire Door Abatement Assume 8 each. Unit is each. $__________________
Lead Based Paint (LBP) Assume 10 SF. Unit is per SF. $__________________
Mercury Containing Light Tubes
Assume 2865 ea. Unit is per tube. $__________________
PCB Light Ballast Assume 5 ea. Unit is per ballast. $__________________
Total Price for 4th Floor Fit-Out (Price includes item 1 + item 2 + item 3; listed above): $__________________
PEB Cafeteria Expansion
1. Base Bid
General Conditions $
Foundations $__________________
Exterior Enclosure $__________________
Interior Construction $__________________
Interior Finishes $__________________
Plumbing $__________________
HVAC $__________________
Fire Suppression $__________________
Electrical $__________________
Equipment $__________________
Demolition $__________________
Site Preparation $__________________
Site Improvement $__________________
Site Mechanical Utilities $__________________
Bonds $__________________
2. Unit Prices
ACM Mastics and Sealants Associated with Metal Ducts Assume 110 LF. Unit is per LF. $__________________
ACM Mastics and Sealants Associated with Metal Exhaust Ducts
Assume 425 LF . Unit is per LF. $__________________
Fire Doors
Assume 2 ea. Unit is per door. $__________________
Mercury Containing Light Tubes Assume 116 EA. Unit is per tube. $__________________
PCB Light Ballast
Assume 1 EA. Unit is per ballast. $__________________
Total Price for Cafeteria Expansion (Price includes item 1 + item 2; listed above): $__________________
PEB 4th Floor Alternate
See spec section 12300-2, 1.4A, Alt No. 001
Mechanical Systems Infrastructure $_________________
Bond $_________________
Overhead $_________________
Total Price for 4th Floor Alternate: $__________________
TOTAL EVALUATED PRICE includes: $_______________
Total Price for PEB 4th Floor Fit-Out Total Price for PEB Cafeteria Expansion Total Price for PEB 4th Floor Alternate