This document outlines a federal construction contract opportunity for renovations and upgrades to the Perimeter East Building at the Social Security Administration campus in Woodlawn, Maryland. The General Services Administration will issue a Request for Proposal for approximately $30-50 million in construction work including renovating 90,000 square feet on the fourth floor, adding two exterior stair towers, upgrading the smoke control and building automation systems, renovating the cafeteria kitchen, and an option for mechanical infrastructure upgrades. The construction manager will be Hill International. Proposals are due by November 30, 2020 and award is planned for the week of February 8, 2021. A pre-proposal conference will be scheduled. Interested parties should monitor beta.sam.gov for the solicitation and any amendments. Inquiries should be directed to the specified email.

View the file

Other files

File Type Posted
Solicitation Amendment 47PD0121R0001_0008.pdf PDF
DOL General Decision Number MD20200030 Mod 10 dtd 12_11_2020.pdf PDF
Amendment 007 - Pre-Bid RFI responses.pdf PDF
Solicitation Amendment 47PD0121R0001_0007.pdf PDF
Solicitation Amendment 47PD0121R0001_0006.pdf PDF
Pre-Bid RFIs Responses - Amendment 006.pdf PDF
Bid Bond form - SF24.pdf PDF
Solicitation Amendment 47PD0121R0001_0005.pdf PDF
Amendment 0005 - Small Business Utilization Form.pdf PDF
Solicitation Amendment 47PD0121R0001_0004.pdf PDF
Pre-bid Photo Album No. 2 _11_12_2020.pdf PDF
Pre-bid Photo Album No. 3_11_12_2020.pdf PDF
Pre-Bid RFIs - Amendment 004.pdf PDF
Solicitation Amendment 47PD0121R0001_0003.pdf PDF
Pre-bid Photo Album No. 1.pdf PDF
Site Walk-Through Attendance List.pdf PDF
PEB Pre-Proposal Conference - Minutes 11.12.20.pdf PDF
Solicitation Amendment 47PD0121R0001_0002.pdf PDF
Amendment Number 0001 - pre-proposal information.pdf PDF
Amendment 0001 - SSA Complex 0001.pdf PDF
Amendment 0001 - PEB Parking Lots.pdf PDF
Solicitation Amendment 47PD0121R0001_0001.pdf PDF
Sol. 47PD0121R0001 C301 GC Rep and Cert.pdf PDF
Sol 47PD0121R0001 C101 Agreement.pdf PDF
47PD0121R0001 SF 1442.pdf PDF
DOL General Decision Number MD20200030 Mod 08 dated 10_09_2020.pdf PDF
Sol 47PD0121R0001 C201 GC Solicitation.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Initials: _________

SSA Perimeter East Building (PEB) 4th Floor & Infrastructure Upgrades & Cafeteria

Bid Sheet

OFFER SHEET – ADDENDUM TO SF 1442

1. The contractor shall provide all management, supervision, labor, materials and equipment in accordance with the scope of work and Government provided documents.

2. The contractor shall include all mark-ups, including overhead, profit and bonds, in their proposal.

3. This proposal is made in full compliance with all the terms and conditions of this Solicitation, the latest applicable Davis Bacon Wage Decision, and any amendments.

4. The breakdown below is necessary to account for numerous government funding accounts and to help evaluate the offers.

PEB 4th Floor Fit-Out

1. Base Bid

General Conditions $__________________

Demolition $__________________

Concrete $__________________

Masonry $__________________

Metals $__________________

Wood, Plastics, & Composites $__________________

Thermal & Moisture Protection $__________________

Openings / Doors & Windows $__________________

Finishes $__________________

Specialties $__________________

Equipment $__________________

Furnishings $__________________

Conveying Equipment $__________________

Fire Suppression $__________________

Plumbing $__________________

HVAC $__________________

Electrical $__________________

Communications $__________________

Electronic Safety & Security $__________________

Earthwork $__________________

Exterior Improvements $__________________

Utilities $__________________

Building Automation System $__________________

Overhead $__________________

Bonds $__________________

2. Grease Interceptor

Grease Interceptor (all work associated with removal and replacement) $__________________

Bond $__________________

3. Unit Prices

Fireproofing Type 1 Reapplication Assume 635 linear feet $__________________

Fireproofing Type 2 Reapplication Assume 216 linear feet $__________________

Fireproofing Type 3 Repair Fireproofing

Assume 95 repairs. Unit is per repair. $__________________

Fireproofing Type 4 Repair Fire Proofing at Existing Equipment Hangers Assume 95 repair. Unit is per repair. $__________________

Fireproofing Type 5 Repair Fireproofing at Existing Conduit Rerouting Assume 95 repair. Unit is per repair. $__________________

Fire Safing Type 1 Repair Fire Safing at Existing Penetrations Assume 62 penetrations . Unit is per penetration. $__________________

Fire Safing Type 2 Repair Fire Safing at Existing Ceiling/Floor Penetrations Assume 7 penetrations. Unit is per penetration. $__________________

ACM Floor Tile and Associated Mastic Assume 1,900 SF. Unit is per SF. $__________________

Core Drill ACM Floor Tile and Associated Mastics

Assume 16 ea. Unit is per location. $__________________

ACM Mastics and Sealants Associated with Fiberglass Duct Insulation on Ducts and Air Handling Units. Assume 9,421 SF. Unit is per SF. $__________________

ACM Mastics and Sealants Associated with Metal Fan Coil Units and Metal Exhaust Ducts. Assume 2,124 SF. Unit is per SF. $__________________

ACM Mastics on Fiberglass Pipe Insulation

Assume 8,905 LF. Unit is per LF. $__________________

Fire Door Abatement Assume 8 each. Unit is each. $__________________

Lead Based Paint (LBP) Assume 10 SF. Unit is per SF. $__________________

Mercury Containing Light Tubes

Assume 2865 ea. Unit is per tube. $__________________

PCB Light Ballast Assume 5 ea. Unit is per ballast. $__________________

Total Price for 4th Floor Fit-Out (Price includes item 1 + item 2 + item 3; listed above): $__________________

PEB Cafeteria Expansion

1. Base Bid

General Conditions $

Foundations $__________________

Exterior Enclosure $__________________

Interior Construction $__________________

Interior Finishes $__________________

Plumbing $__________________

HVAC $__________________

Fire Suppression $__________________

Electrical $__________________

Equipment $__________________

Demolition $__________________

Site Preparation $__________________

Site Improvement $__________________

Site Mechanical Utilities $__________________

Bonds $__________________

2. Unit Prices

ACM Mastics and Sealants Associated with Metal Ducts Assume 110 LF. Unit is per LF. $__________________

ACM Mastics and Sealants Associated with Metal Exhaust Ducts

Assume 425 LF . Unit is per LF. $__________________

Fire Doors

Assume 2 ea. Unit is per door. $__________________

Mercury Containing Light Tubes Assume 116 EA. Unit is per tube. $__________________

PCB Light Ballast

Assume 1 EA. Unit is per ballast. $__________________

Total Price for Cafeteria Expansion (Price includes item 1 + item 2; listed above): $__________________

PEB 4th Floor Alternate

See spec section 12300-2, 1.4A, Alt No. 001

Mechanical Systems Infrastructure $_________________

Bond $_________________

Overhead $_________________

Total Price for 4th Floor Alternate: $__________________

TOTAL EVALUATED PRICE includes: $_______________

Total Price for PEB 4th Floor Fit-Out Total Price for PEB Cafeteria Expansion Total Price for PEB 4th Floor Alternate

AUTHORIZED BY:

Signature:

Name:

Title:

Company: