Sol 47PD0121R0001 C101 Agreement.pdf
PDF 545 KB Posted
- Attached to
- Perimeter East Building Renovation and Upgrades Construction Project at the SSA Complex in Woodlawn, MD
- Solicitation number
- 47PD0121R0001
About this file
This document provides details regarding a forthcoming federal construction contract solicitation for renovation and upgrade work at the Perimeter East Building on the Social Security Administration campus in Woodlawn, Maryland. The General Services Administration intends to issue a request for proposal for approximately $30-50 million in construction services including 90,000 square feet of renovations, installation of new HVAC equipment, building automation controls upgrades, hazardous material abatement, and cafeteria improvements. The scope also includes an option for mechanical infrastructure upgrades. Interested parties must register at beta.SAM.gov to access the solicitation, which is anticipated for release on or around October 26, 2020 with a possible proposal due date of November 30, 2020 and award date in early February 2021. A pre-proposal conference will be held at the campus with registration required. The award will be made using a tradeoff source selection process considering technical and price factors.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Solicitation Reference No.: 47PD0121R0001
Document: C101/AUGUST 2020 (The Agreement)
Construction Contract for: Perimeter East Building (PEB) Renovation and Upgrades Construction Project
The Agreement
Table of Contents
I. Project Information A. Project Summary B. The Contract C. Period Of Performance D. Work Conditions/Site Requirements E. Authorized Representatives F. Contract Liquidated Damages Rate G. Buy American Exceptions H. Statement of Work, Specifications, Drawings, Exhibits and Other Attachments
II. Prices
A. Basis of Pricing B. Contract Price Form
III. Terms and Conditions
A. Contractor Responsibilities B. Project Schedule C. Submittals D. Finality of Contract Modifications E. Liquidated Damages F. Insurance Requirements G. Order of Precedence H. Administrative Matters I. Non-Compliance with Contract Requirements J. Safeguarding Sensitive Data and Information Technology Resources K. Options and Allowances L. Equal Employment Opportunity Plan M. Additional Terms and Conditions
i. GSAR 552.236-74, Evaluation of Options and or Alternate (Mar 2019)
ii. GSAR 552.236-77, Government’s Right to Exercise Options and or Alternate (Mar 2019)
iii. FAR 52.211-18 Variation in Estimated Quantity (APR 1984)
iv. Additional Terms
IV. Contract Clauses
A. Clauses Incorporated in Full Text
1. FAR 52.222-99 Establishing a Minimum Wage for Contractor (JUL 2014)
(DEVIATION)
2. FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
3. FAR 52.223-9 Estimate of Percentage of Recovered Material Content for
EPA-Designated Items (May 08)
4. GSAR 552.204-9 Personal Identity Verification Requirements (OCT 2012)
5. GSAR 552.211-10 Commencement, Prosecution and Completion of Work
(Mar 2019)
6. GSAR 552.211-12 Liquidated Damages – Construction (Mar 2019)
7. GSAR 552.211-13 Time Extensions (Mar 2019)
8. GSAR 552.211-70 Substantial Completion (Mar 2019)
9. GSAR 552.232-5 Payments Under Fixed-Price Construction Contracts (Mar
2019)
10. GSAR 552.236-6 Superintendence by the Contractor (Mar 2019)
11. GSAR 552.236-11 Use and Possession Prior to Completion (Mar 2019)
12. GSAR 552.236-15 Schedules for Construction Contracts (Mar 2019)
13. GSAR 552.236-21 Specifications and Drawings for Construction (Mar 2019)
14. GSAR 552.236-71 Contractor Responsibilities (Mar 2019)
15. GSAR 552.236-72 Submittals (Mar 2019)
16. GSAR 552.252-6 Authorized Deviations in Clauses (Deviation FAR 52.252-6) (Sep 99)
17. FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2020)
18. Buy American Requirements
19. Additional Clauses
i. GSAR 552.236-70 Authorities and Limitations (Mar 2019)
ii. GSAR 552.236-73 Subcontracts (Mar 2019)
iii. GSAR 552.243-71 Equitable Adjustments (Mar 2019)
20. FAR 52.222-62, Paid Sick Leave under Executive Order 13706 (Jan 2017)
21. Project Labor Agreement
22. FAR 52.223-21, FOAMS (Jun 2016)
23. FAR 52.222-6, Construction Wage Rate Requirements
24. FAR 52.244-5, Competition in Subcontracting (DEC 1996)
B. Clauses Incorporated by Reference C. Subcontract Requirements
I. Project Information
I.A. Project Summary
The Perimeter East Building (PEB) was originally constructed to serve as the main data center for the Social Security Administration. The data center function has since moved out of the building and the program for the building seeks to convert the floors to modernized office space, using a space utilization rate of 150 usable square feet (USF) per seat.
The project scope consists of approximately 90,000 SF of renovations, tenant improvements on the 4th floor, two new exterior stair tower structures, smoke control system upgrades for the
PEB lobby, and new HVAC equipment on other floors as indicated in contract documents, building automation controls, upgrading existing BAS controls at the PEB and PEUB Building.
As part of the demolition, identified hazardous material removal is expected, including asbestos containing materials and lead based paint. In addition, the project will include a renovation to the
PEB cafeteria kitchen and serving area. There is also an alternate for a full mechanical infrastructure upgrade, which would include installing four new rooftop AHUs.
Other goals for the project include but are not limited to the following items:
• Creating an open and welcoming office environment;
• Increasing daylight and exterior views for the occupants of the open office areas and breakrooms;
• Creating more conference rooms and teaming areas;
• Creating work areas with good acoustics.
I.B. The Contract
(1) The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section
II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than five hundred and forty (540) calendar days from issuance of Notice to Proceed (NTP). If Alternate 1, Mechanical System
Infrastructure, is exercised the period of performance will remain the same.
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within sixty (60) calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
The PEB is a 5 floor, level IV security, government facility that is fully occupied with Social
Security Administration employees. The Perimeter East Utility Building (PEUB) is a separate, secured, government facility that houses the physical plant systems that provide mechanical and electrical services to the PEB. Throughout the construction, all Contractor work practices and plans must be coordinated and controlled to minimize impacts to occupant functions, building operations and security protocols.
The Perimeter East Utility Building (PEUB) where the Boiler, Chiller and other utility equipment are located will remain operational throughout the project. The utility systems and equipment located within and throughout the PEB Building shall remain operational, functional and secured throughout the project duration. Any contract work that ties into and/or requires cutting and capping of the operational building systems must be coordinated so that required systems remain fully functional for the duration of this project.
A Bid Guarantee will be required in accordance with FAR 28.101-2.
Performance and Payment Bonds will be required in accordance with FAR 28.102.
Construction Wage Requirements Statute Wage Determinations applies to this requirement in accordance with FAR Part 22.404.
Please refer to Division 1 specification section 01 10 00 “Summary” and Final approved
Construction drawing package for further information.
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the
Administrator of General Services (GSA), and the Contractor (the Parties). References in this
Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Authorized Representative Information:
Contracting Officer’s Information (Primary Point of Contact)
Name: Anthony Teti
Address: 100 S. Independence Mall West, Philadelphia PA 19106
Authorized Representative Information:
Telephone: (215) 756-5252
Email: Anthony.teti@gsa,gov
Contract Specialist Information (Secondary Point of Contact) Name: George Garcia
Address: 100 S. Independence Mall West, Philadelphia PA 19106
Telephone: (215) 313-1692
Email: george.garcia@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate
In accordance with GSAR 552.211-12, Liquidated Damages – Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $2,005 per calendar day.
I.G. Buy American Exceptions
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement, GSAR 552.236-70.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
(1) PEB Cafeteria IFC Specification_Volume 1, Dated October 29, 2020
(2) PEB Cafeteria IFC Specification_Volume 2, Dated October 29, 2020
(3) PEB Cafeteria IFC Appendices_Volume 3, Dated October 29, 2020
(4) PEB IFC Construction Drawings Package, Dated October 29, 2020
(5) PEB Cafeteria Construction Drawings Package, Dated October 29, 2020
(6) Wage Determination MD20200030 Modification 08, Dated October 09, 2020
All documents listed above will be uploaded to the Contract Opportunities page on www.beta.SAM.gov under the Notice ID# 47PD0121R0001. These will be posted as restricted access. Offerors shall request access to GSA Contracting Officer, Anthony Teti, via email at Anthony.teti@gsa.gov.
II. Prices
II.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work. The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.
(4) Options. If any portion of the Work is to be performed upon the timely exercise of an Option, the Option Price shall include all costs of coordinating and incorporating the Option-priced portion of the Work into the Base Contract Work. An adjustment to the Contract price for such additional work shall be computed solely on the basis of the Option price or prices set forth herein. Unless otherwise specified, all options may be exercised within 90 days of Contract award.
(5) Bid Rates. If this Contract includes Bid Rates to be used in determination of equitable adjustments (e.g., overhead, profit, daily rates for time-related costs), such rates shall be deemed to include all costs recoverable as components of an equitable adjustment consistent with the requirements, definitions, and exclusions applicable to equitable adjustments set forth in this Contract, and consistent with the Contractor's cost accounting practices. Unless otherwise specified, the bid rates shall be deemed to include only the Contractor's costs, and not the costs of any subcontractors.
II.B. Contract Price Form
See SF-1442 with attached Bid Sheet.
III. Terms and Conditions III.A. Contractor Responsibilities
GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:
(1) For the purposes of FAR 52.236-1, Performance of Work by the Contractor, the Contractor shall perform at not less than twelve percent of the Work.
(2) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution of the work to the Contracting Officer prior to commencement of any related work
(3) FAR 52.211-10, Commencement, Prosecution, and Completion of Work, and GSAR 552.211-10, Commencement, Prosecution and Completion of Work is supplemented as follows:
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in GSAR 552.211-70 Substantial Completion (Mar 2019) and the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
III.B. Project Schedule
GSAR 552.236-15, Schedules for Construction Contracts is supplemented as follows:
(1) Within 30 calendar days after NTP, the Contractor shall develop and provide a detailed schedule in widely used, commercially available software such as Microsoft Project and
Primavera P6 for completion of all Design Stage activities, tasks, and submissions required herein, leading up to and including the final design development submission(s).
III.C. Submittals
FAR 52.236-21, Specifications and Drawings for Construction, and GSAR 552.236-723, Submittals located in Section IV.A. of the Agreement are supplemented as follows:
(1) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, GSA Form 184 (associated 184A and 184B as necessary), and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract.
III.D. Finality of Contract Modifications
As set forth elsewhere in this Contract, the Contractor is entitled to additional consideration under certain conditions, including the issuance of change orders. It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing such consideration, adjustments to the Contract price or time agreed upon therein shall be deemed to provide all compensation to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to compensation on account of the change or other condition giving rise to the modification.
III.E. Liquidated Damages
The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work in accordance with FAR 52.211- 12, Liquidated Damages, GSAR 552.211-12, Liquidated Damages and within the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Section I (Project Information), paragraph entitled, “Liquidated Damages Rate,” for each calendar day following the required completion date that the Work is not Substantially Complete.
III.F. Insurance Requirements
(1) The Contractor shall obtain and maintain for the entire life of the Contract, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, and GSAR 552.228-5, Government as Additional Insured.
(a) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $2,000,000. If occupational diseases are not covered by workers' compensation insurance, Employers' liability coverage shall include occupational diseases.
(b) Broad form comprehensive commercial general liability insurance in the amount of at least $5,000,000 per occurrence. Such insurance shall include, but not be limited to, contractual liability, bodily injury and property damage.
(c) Comprehensive automobile liability covering the operation of all automobiles used in connection with performing the Contract in the amount of at least $1,000,000 per person and $2,500,000 per occurrence for bodily injury and $1,000,000 per occurrence for property damage.
(2) The Contractor shall require that the licensed design professionals it retains for the Project acquire and maintain professional liability insurance in the amount of $5,000,000 per claim and shall provide proof to the Contracting Officer.
(3) The Contractor shall promptly provide to the Contracting Officer proof that it has obtained insurance required by the Contract in the form of certificates of insurance. The Contractor shall submit to the Contracting Officer all renewal certificates issued during the life of this Contract immediately upon issuance.
III.G. Order of Precedence
Different requirements within this Contract shall be deemed inconsistent only if compliance with both cannot be achieved. In case of inconsistency between Contract Documents, the following order of precedence shall apply:
(1) Section IV of the Agreement
(2) Sections I, II, and III of the Agreement
(3) The Statement of Work
(4) The Specifications
(5) The Drawings
(6) Exhibits and Other Attachments
III.H. Administrative Matters
(1) Project Meetings. The Contractor shall attend a preconstruction conference and shall participate in regularly scheduled Project meetings.
(2) Payments. FAR clause 52.232-5, Payments under Fixed-Price Construction Contracts, is supplemented by GSAR 552.232-5 Payments under Fixed-Price Construction Contracts located in Section IV.A. of this Agreement. In accordance with the relevant FAR and GSAR clauses, GSA requires the following data be included with each invoice:
(a) Invoices shall be submitted in an original and two (2) copies to the designated billing office specified in this Contract or in individual delivery/work.
(b) Invoices must include the Account Document Number (ADN) assigned at award.
(c) Invoices must include the Account Document Number (ADN) assigned at award:
(i) GSA Form 184A and/or 184B - Construction Progress Report (Construction Phases Only), including the updated Schedule of Values upon which the payment request is based;
(ii) GSA Form 2419 - Certification of Progress Payments Under Fixed-Price Construction Contract;
(iii) The payment terms that apply for the particular services rendered;
(iv) Additional documentation:
[CO Instruction: Insert project-specific documentation required here. If none, add "NA."]
(3) Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:
(a) Progress Payments: 14 days
(b) Subsequent Subcontractor Payments: 7 days
(4) Payment Information. The General Services Administration (GSA) makes information on contract payments available electronically at http://www.finance.gsa.gov. The Contractor may register at the site and review its record of payments. This site provides information only on payments made by GSA, not by other agencies.
(5) Security Clearances. Contractor shall comply with the following requirements pertaining to security clearances.
(a) All personnel performing work under the Contract on the Project site must obtain an Enter on Duty (EOD) determination before they will be granted access to the site.
(b) To obtain an EOD determination, Contractor shall submit for all such personnel fingerprints on Form SF87 and a completed Contractor Information Worksheet (CIW). Detailed information is available at Detailed information is available at GSA Access Card . USAccess Credentialing Centers can be located at US Access Centers.
(c) In addition, all such personnel who will be on site 6 months or longer must apply for and receive clearance in accordance with Homeland Security Presidential Directive 12 (HSPD- 12). See Section IV, Contract Clauses, GSAR 552.204-9.
(6) Safeguarding and Dissemination of Sensitive But Unclassified (SBU) Building Information.
This clause applies to all recipients of SBU building information, including offerors, bidders, awardees, contractors, subcontractors, lessors, suppliers and manufacturers.
(a) Marking SBU. Contractor-generated documents that contain building information must be reviewed by GSA to identify any SBU content, before the original or any copies are disseminated to any other parties. If SBU content is identified, the Contracting Officer (CO) may direct the contractor, as specified elsewhere in this contract, to imprint or affix SBU document markings to the original documents and all copies, before any dissemination.
(b) Authorized recipients.
(i) Building information designated SBU must be protected with access strictly controlled and limited to those individuals having a legitimate business need to know such information.
Those with a need to know may include Federal, State and local government entities, and nongovernment entities engaged in the conduct of business on behalf of or with GSA.
Nongovernment entities may include architects, engineers, consultants, contractors, subcontractors, suppliers, utilities, and others submitting an offer or bid to GSA, or performing work under a GSA contract or subcontract. Recipient contractors must be registered as “active” in the System for Award Management (SAM) database at www.sam.gov and have a legitimate business need to know such information. If a subcontractor is not registered in the SAM and has a need to possess SBU building information, the subcontractor shall provide to the contractor its DUNS number or its tax ID number and a copy of its business license. The contractor shall keep this information related to the subcontractor for the duration of the contract and subcontract.
(ii) All GSA personnel and Contractors must be provided SBU building information when needed for the performance of official Federal, State, and local government functions, such as for code compliance reviews and for the issuance of building permits. Public safety entities such as fire and utility departments may require access to SBU building information on a need to know basis. This clause must not prevent or encumber the dissemination of SBU building information to public safety entities.
c. Dissemination of SBU building information:
(i) By electronic transmission. Electronic transmission of SBU information outside of the GSA network must use session encryption (or alternatively, file encryption). Encryption must be via an approved NIST algorithm with a valid certification, such as Advanced Encryption Standard (AES) or Triple Data Encryption Standard (3DES), in accordance with Federal Information Processing Standards Publication (FIPS PUB) 140-2, Security Requirements for Cryptographic Modules per GSA policy.
(ii) By nonelectronic form or on portable electronic data storage devices. Portable electronic data storage devices include, but are not limited to CDs, DVDs, and USB drives.
Nonelectronic forms of SBU building information include paper documents, among other formats.
1) By mail. Contractors must utilize only methods of shipping that provide services for monitoring receipt such as track and confirm, proof of delivery, signature confirmation, or return receipt.
2) In person. Contractors must provide SBU building information only to authorized recipients with a need to know such information. Further information on authorized recipients is found in Section 2 of this clause.
d. Record keeping. Contractors must maintain a list of all entities to which SBU is disseminated, in accordance with sections 2 and 3 of this clause. This list must include at a minimum: (1) the name of the State, Federal, or local government entity, utility, or firm to which SBU has been disseminated; (2) the name of the individual at the entity or firm who is responsible for protecting the SBU building information, with access strictly controlled and limited to those individuals having a legitimate business need to know such information; (3) contact information for the named individual; and (4) a description of the SBU building information provided. Once “as built” drawings are submitted, the contractor must collect all lists maintained in accordance with this clause, including those maintained by any subcontractors and/or suppliers, and submit them to the CO. For Federal buildings, final payment may be withheld until the lists are received.
e. Safeguarding SBU documents. SBU building information (both electronic and paper formats) must be protected, with access strictly controlled and limited to those individuals having a legitimate business need to know such information. GSA contractors and subcontractors must not take SBU building information outside of GSA or their own facilities or network, except as necessary for the performance of that contract. Access to the information must be limited to those with a legitimate business need to know.
f. Destroying SBU building information. When no longer needed, SBU building information must be destroyed so that marked information is rendered unreadable and incapable of being restored, in accordance with guidelines provided for media sanitization within GSA CIO IT Security 06-32, Media Sanitization Guide and Appendix A of NIST Special Publication 800-88, Guidelines for Media Sanitization. Alternatively, SBU building information may be returned to the CO.
g. Notice of disposal. The contractor must notify the CO that all SBU building information has been returned or destroyed by the contractor and its subcontractors or suppliers in accordance with paragraphs 4 and 6 of this clause, with the exception of the contractor's record copy. This notice must be submitted to the CO at the completion of the contract to receive final payment. For leases, this notice must be submitted to the CO at the completion of the lease term. The contractor may return the SBU documents to the CO rather than destroying them.
h. Incidents. All improper disclosures of SBU building information must be immediately reported to the CO at <insert address and contact information> . If the contract provides for progress payments, the CO may withhold approval of progress payments until the contractor provides a corrective action plan explaining how the contractor will prevent future improper disclosures of SBU building information. Progress payments may also be withheld for failure to comply with any provision in this clause until the contractor provides a corrective action plan explaining how the contractor will rectify any noncompliance and comply with the clause in the future.
i. Subcontracts. The contractor and subcontractors must insert the substance of this clause in all subcontracts.
III.I. Non-Compliance with Contract Requirements
In the event the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this Contract, fails to initiate promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the
Contracting Officer shall have the right to order the Contractor to stop any or all work under the Contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of Contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.
III.J. Safeguarding Sensitive Data and Information Technology Resources
In accordance with FAR 39.105, this section is included in the contract. This section applies to all users of sensitive data and information technology (IT) resources, including awardees, contractors, subcontractors, lessors, suppliers and manufacturers. The following GSA policies must be followed.
These policies can be found at Directives Library.
1. CIO P 2100.1K GSA Information Technology (IT) Security Policy
2. CIO P 2100.2B GSA Wireless Local Area Network (LAN) Security
3. CIO 2100.3C Mandatory Information Technology (IT) Security Training Requirement for
Agency and Contractor Employees with Significant Security Responsibilities
4. CIO 2104.1A CIO CHGE 1 GSA Information Technology IT General Rules of Behavior
5. CIO 2105.1 C CHGE 1 GSA Section 508: Managing Electronic and Information
Technology for Individuals with Disabilities
6. CIO 2106.1 GSA Social Media Policy
7. CIO 2107.1 Implementation of the Online Resource Reservation Software
8. CIO 2160.4A Provisioning of Information Technology (IT) Devices
9. CIO 2162.1 Digital Signatures
10. CIO P 2165.2 GSA Telecommunications Policy
11. CIO P 2180.1 GSA Rules of Behavior for Handling Personally Identifiable Information
(Pll)
12. CIO 2182.2 Mandatory Use of Personal Identity Verification (PIV) Credentials
13. CIO P 1878.2A Conducting Privacy Impact Assessments (PIAs) in GSA
14. CIO IL-13-01 Mobile Devices and Applications
15. CIO 2102 Information Technology (IT) Integration Policy
16. HCO 9297.1 GSA Data Release Policy
17. HCO 9297.2B GSA Information Breach Notification Policy
18. ADM P 9732.1 D Suitability and Personnel Security
The contractor and subcontractors must insert the substance of this section in all subcontracts.
III.K. Options and Allowances
This project consists of a base for the PEB 4th Floor and Cafeteria and one alternate as follows:
BASE – Perimeter East Building (PEB) 4th Floor Fit-Out
BASE – Perimeter East Building (PEB) Cafeteria Expansion
ALTERNATE #1 – PEB 4th Floor Mechanical Systems Infrastructure
Additionally, the SF-1442 Bid Sheet requires that offerors provide Unit Cost Pricing for several elements of the work associated with the 4th Floor Fit-Out and Cafeteria Expansion bases and alternate 1. These will be utilized in calculating the price of any equitable adjustments based on quantity changes as needed throughout the life of the contract.
III.L. Equal Employment Opportunity Plan
(1) Within 30 days following award, the Contractor shall furnish the Contracting Officer with an EEO Compliance Plan. The plan shall include the following:
(a) Name of contractor’s EEO Manager for the contract and point of contact information. The EEO Manager is responsible for:
(i) Monitor all employment-related activity to ensure that the Contractor’s equal employment policy is being carried out;
(ii) Submit reports as may be required by the Government; and
(iii) Keep records that shall at least include for each employee the name, address, telephone number, construction trade, union affiliation (if any), employee identification number, social security number, race, sex, status (e.g., mechanic, apprentice, trainee, helper, or laborer), dates of changes in status, hours worked per week in the indicated trade, rate of pay, and locations at which the work was performed. Records shall be maintained in an easily understandable and retrievable form; however, to the degree that existing records satisfy this requirement, separate records are not required to be maintained.
(b) Address how the contractor intends to include the EEO provisions of the contract in all subcontracts in excess of $10,000.
(c) Address what type of efforts will be used to ensure equal employment opportunity in accordance with FAR 52.222-27 Affirmative Action Compliance Requirements for Construction. Discuss organized meeting with subcontractors, labor organizations and/or other community stakeholders. Meetings should focus on increased employment opportunities, perceived problems and working to achieve the goals established. DOL representatives are available to participate in such meetings.
(2) During the performance of this contract, the Contractor shall submit to the Contracting Officer semi-annually an EEO Compliance Report containing the following:
(a) List of awarded subcontractors by trade, date of award and amount of subcontract. If subcontract is in excess of $10,000, date the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor was notified of award.
(b) Narrative of actions taken to comply with the affirmative action procedures in paragraphs (g)(1) through (g)(16) of FAR 52.222-27.
(c) List participation in any voluntary associations that may assist in fulfilling the contractor’s affirmative action obligations.
Semi-annual reports are due on the 30th calendar day (or next business day) following the March 31st and September 30th.
III.M. Additional Terms and Conditions
(i) GSAR 552.236-74, Evaluation of Options and or Alternates (MAR 2019) The Government will evaluate offers for award purposes by adding the total price for all options and or all alternates to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(ii) GSAR 552.236-77, Government’s Right to Exercise Options and or Alternates
(MAR 2019) [
(a) The Government may exercise any option and or Alternates in writing in accordance with the terms and conditions of the contract within ninety (90) days of contract award.
(b) If the Government exercises the option and or alternates, the contract shall be considered to include this option and or alternate clause.
(iii) FAR clause 52.211-18 Variation in Estimated Quantity (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
(End of clause)
(iv) Additional Terms
Security Requirements
This section is not inclusive; refer to Specification Section 00 80 00 “Supplemental
General Conditions” in PEB 4th Floor Cafeteria and IFC Construction Specification
Packages.
PART 1 – SECURITY REQUIREMENTS AND PERSONAL IDENTITY VERIFICATION
AND CREDENTIALING PROCEDURES FOR CONTRACTORS AND SPECIFIC
REQUIREMENTS
1.1 The General Services Administration (GSA) reserves the right to verify the identities of personnel with routine, unaccompanied access to GSA space, or Information
Technology (IT) systems. The term Contractor used throughout this section shall refer to General/Prime Contractor, Subcontractor(s) and all their personnel. The Contractor shall comply with the GSA personal identity verification procedures outlined below, that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of
Management and Budget (OMB) guidance M-05-24, and the Federal Information
Processing Standards Publication (FIPS PUB) Number 201, as amended. All Contractor personnel performing work on a GSA contract may be required to have a background investigation conducted and the results favorably adjudicated (HSPD-12 compliant suitability determinations) for all contract personnel requiring routine unescorted access to Federally-controlled facilities and/or IT systems for more than 6 months before identification cards may be issued.
1.2 Based on the building type (leased or owned) and the Facility Security Level (FSL) the GSA reserves the right to conduct background checks on Contractor personnel who support GSA contracts and require routine access to GSA facilities and IT systems. .
Contractors unable to obtain a favorable security determination or meet security requirements will be removed from the project and denied official access to federal facilities and IT systems.
A. The Government has full and complete control over granting, denying, withholding or terminating suitability determinations for Contractor personnel. The Government may authorize and grant temporary suitability to personnel of the Contractor. However, the granting of a preliminary suitability determination shall not be considered as a guarantee; that the employee will receive a favorable final suitability determination. The granting of either a preliminary or final suitability determination shall not prevent, preclude, or bar the withdrawal or termination of any such suitability determination by the Government.
B. Contract personnel working less than 6 months may be considered “temporary”. GSA may require low risk suitability determinations be completed for temporary contract employees, or have the option of granting unescorted access to temporary contractors based on the preliminary favorable results, a National Agency Check (NAC) consisting of NCIC and NLETS checks, an FBI fingerprint check, and a Citizenship and Immigration Services check. Short-term access based on the favorable results of a NAC for temporary access is only good for six months and cannot be extended or redone. Those requiring unescorted access greater than six months may have to undergo an HSPD-12 compliant suitability determination. Temporary contract personnel that are not required to receive a favorable suitability determination may be required to be escorted at all times while in non-public space.
1.3. The Contractor shall account for all GSA credentials issued to Contractor personnel in connection with the performance under this contract. The Contractor shall immediately return credentials issued by GSA under any of the following conditions:
A. When the employees is no longer required for contract performance.
B. Upon completion of the Contractor employee’s employment.
C. Upon contract completion or termination.
D. In the event a previously issued preliminary Enter on Duty (EOD) determination is revoked.
1.4. The Contracting Officer may delay final payment or execute an equitable adjustment under the contract, if the Contractor fails to comply with these requirements.
1.5. The General/Prime Contractor shall insert these requirements in all subcontracts. It shall be the responsibility of the General/Prime Contractor to return all credentials issued by the GSA and any other sources in association with this contract and in accordance with the terms set forth in paragraph 1.3, above.
PART 2 - FEDERAL DEBT REDUCTION AND OVERSIGHT OF FEDERAL FUNDS
2.1 The GSA has a fiduciary responsibility to provide oversight of federal funding. The
Contractor will work with the GSA to reduce expenditures, and assure oversight of federal tax dollars when requesting background checks. In order to reduce expenses and ensure prudent use of federal funds, the Contractor will make every effort to pre-screen, or interview prospective personnel to help ensure they are suitable for employment, and are able to pass a background check prior to submitting employee applications to GSA.
2.2 After the Contactor submits a request for background investigations to the GSA, the
Contractor must monitor the employee’s progress through completion of the process.
The Contractor must provide follow-up and monitoring, ensure the requested individual(s) responds to requested information, and completes all required forms within the prescribed times allowed. The Contractor must ensure the Contracting Officer or their Designated Representative has all of the requested documentation to ensure the completion of the application. The Contractor shall assign and dedicate a single Point of
Contact (POC) for the overall control, management, and oversight of all employee suitability investigation applications. This POC will be responsible for following up when requested to ensure timely and accurate document submissions for background investigations.
2.3 The Adjudicating Office reviewing the employees application may forward a written notification to contractor personnel for clarification information that pertains to the background investigation requesting additional information or supporting documentation. The POC shall ensure this inquiry is responded to in a timely manner.
PART 3 - ADJUDICATION AUTHORITY
3.1 GSA and its Authorized Agent, the Office of Personnel Management (OPM) or any other named designee, will be responsible for conducting the HSPD-12 background investigations, and credentialing of Contractor’s personnel. GSA has the overarching authority to process the HSPD-12 background investigations, as directed by the Office of
Personnel Management (OPM).
PART 4 -PROCESSING OF HSPD-12 INVESTIGATIONS AND CREDENTIIAL
PROCEDURES
4.1 Submission of Forms: All Contractor personnel requiring facility or IT system access, may be responsible to fill out and complete security HSPD-12 forms and fingerprint cards prior to being allowed access. GSA will provide detailed instructions on the HSPD-12 process, the forms to be submitted, and the handling of the forms after the contract has been awarded. Depending on the level of responsiveness and timeliness of individual Contractor personnel, a maximum of seven (7) days is expected for the completion and submission of all forms by the applicant for review through the
GSA. More importantly, however, the Contractor and the single Point of Contact (POC) managing all employees has the responsibility to submit applications in a timely fashion so as not to delay any project activities or the overall project schedule. Initiation of the suitability investigation forms are required to be provided for all applicants a minimum of thirty (30) days prior to access being required without the need for a HSPD-12 credential, or sixty (60) days prior to access being required when a HSPD-12 credential is required. Access requirements by Contractor personnel shall be based on the contract time performance requirements, and the planned activities on the approved project schedule. The Contracting Officer or their Designated Representative will notify the Contractor in writing if any Contractor personnel receive an unfavorable decision on their background investigation, and effective immediately; the individual will no longer be allowed to work on the project. The Contractor shall be responsible for planning and scheduling its work in such a manner as to account for the facility or IT access investigation requirement time frames. Difficulties encountered by the Contractor’s personnel in gaining access when required by not fulfilling application requirements in a timely manner shall not be an excuse for Contractor non performance under the contract, or the granting of any time extensions.
A. Throughout the life of the contract, the Contractor shall be responsible to follow these same procedures for any new Contractor personnel, who will require access to
GSA’s space or IT systems.
B. Also throughout the life of the contract, the Contractor shall maintain a listing of current/active personnel that have received a favorable suitability investigation and/or have a credential. The Contractor shall provide the Contracting Officer or their
Designated Representative, an updated listing of current/active personnel when requested. The Contractor is also responsible to show on that same list when personnel are no longer working on the project for whatever reason. The Contractor shall immediately return the credential of any individuals that are no longer requiring access.
4.2. Unsuitable Personnel: If the Contracting Officer receives an unsuitable report on any contract personnel after the processing their application, or if the GSA finds a prospective contract employee to be unsuitable or unfit for their assigned duties; the
Contractor shall be advised immediately by the Contracting Officer or their Designated
Representative that such personnel cannot continue to work or be assigned to work under the contract. The Contractor must then take action to remove the employee from the GSA contract.
4.3 Criteria for Eligibility: Refer to GSA Order 9732.1 or 5 CFR 731 which outlines the disqualifying and mitigating factors for personnel acceptance.
4.4 Prior Background Investigation: Contract personnel background investigations obtained through this process may be acceptable if the it can be validated equal to or higher level than required of the contract, and there is no break in service from which that favorable suitability was provided. The employee still needs to be vetted through the GSA HSPD-12 process to consider the applicant’s claim to possessing an active suitability, and being granted access under this GSA contract.
4.5 Identification Credential: When GSA initiates a National Agency Check with Written
Inquiries (NACI) suitability investigation and the applicant receive a favorable initial suitability Enter on Duty (EOD) determination, access to the facility or IT system is typically granted at that time. If there is a requirement that in addition, a credential is to also be issued, the Contract employee will need to enroll, and then activate that credential prior to being granted access to the facility or IT system. Credentialing requirements, when applicable, are describe later in this section.
A. Contractor personnel with credentials shall be required to comply with all applicable access security screening procedures applicable to Government or other personnel possessing similar credentials, or as determined by the building practices as defined by the Facility Security Committee.
B. All Contractor personnel possessing credentials (PIV or otherwise) shall visibly display their credentials at all times while in the building(s) where work is being performed.
C. The Contractor shall be responsible for ensuring that all identification credentials are returned to the GSA when Contactor personnel are no longer employed, providing service under the contract, the contract ends or the employee preliminary access is revoked.
D. The Contractor shall notify the GSA when credentials are lost. If the Contractor is determined to be negligent, the Contractor may be responsible for reimbursing the
Government for its cost in issuing a replacement credential.
4.6 Contractor personnel may be required to submit additional personnel information to other Government Agencies affected by the contract work and based on working within that Agency’s space.
PART 5 - GSA Fingerprinting Credential Card: Contractor’s travel costs
5.1. Contractor personnel who require routine access to GSA-controlled facilities and/or access to GSA IT systems must receive a preliminary favorable HSPD-12 security background investigation, before receiving a GSA credential card. Fingerprinting, however, is required for all applicants to receive an investigations. Therefore, all applicants will be required to visit a credentialing center as described below to enroll and be fingerprinted. Not all contractors, however, will receive a HSPD-12 credential and need to return for pick-up and activation of that credential.
5.2. Following a favorable HSPD-12 security background investigation, Contractor personnel may be required activate a GSA credential card at a designated location. The credential card is also a photo Identification card, which includes biometric information.
The following information is provided to assist the Contractor in estimating the costs that may be associated with this requirement. The Contractor will be expected to utilize the nearest credentialing site to their offices, closest the applicant’s residence or place of contract performance. The credentialing station may be a mobile station in the area, or as a fixed open station whose location(s) can be located through the following source:
http://www.fedidcard.gov/centerlocator.aspx. Credentialing centers that are listed as
“Open to all Agency personnel” are open to all customer agencies including GSA
Contractors. Credentialing centers that are listed as “For use by personnel from this
Agency only” mean that they are only open to personnel of that specific agency that is hosting that credentialing center. Currently a minimum of two visits to a credentialing center may be required to enroll and activate the GSA credential. The first visit is to enroll for the credential, and the second visit may be required to pick-up and activate the credential. Travel distance to a credentialing center will vary based on availability of enrollment and activation stations identified in the link above.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .