Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing Federal contract opportunity
Solicitation number
W9128F25QA010
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

The document is an ENG Form 4025-R, a Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certificates of Compliance form used in federal construction contracts. This two-page form provides detailed instructions for contractors to submit technical documentation for review and approval by the U.S. Army Corps of Engineers. The form includes sections for listing submittal items, their type (such as shop drawings, product data, samples), specification references, and tracking the review and approval process.

Key instructions include numbering transmittals consecutively, using a specific format with specification section and sequential numbers, and identifying submittal types ranging from preconstruction documents to closeout materials. The form allows contractors to indicate variations from contract requirements and provides a comprehensive set of action codes for the government's review, such as "Approved as submitted" (A), "Disapproved" (E), or "Receipt acknowledged" (F). The form is specifically associated with the Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing solicitation (W9128F25QA010) managed by the Department of the Army Corps of Engineers Engineering District Omaha.

View the file

Other files for this federal contract opportunity

Other files attached to Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing, newest first.
File Type Posted
Updated 15 Apr 2025 - Price Schedule for GDSM_PH2 Anchor Program.xlsx XLSX spreadsheet
4000 - 2025.04.15_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf PDF
Updated Drawing - GR00108C-102.pdf PDF
Amendment 0002 - W9128F25QA0100002.pdf PDF
Updated Drawing - GR00108C-101.pdf PDF
Updated Drawing - GR00108S-503.pdf PDF
Updated Drawing - GR00108S-101.pdf PDF
Amendment 0001 - W9128F25QA010.pdf PDF
Site Visit Attendance - Garrison Spillway Anchor Testing - 3 Apr 2025.pdf PDF
4007 - Attachment VII - Anchors Phase 2 Geotechnical Data Report_Volume I_20250318.pdf PDF
W9128F25QA010_Solicitation for GDSM Anchor Testing Phase 2.pdf PDF
3000 - SCA 2015-5383 Rev 24 23 Dec 2024 - McLean County ND.pdf PDF
4003 - Attachment III - Phase 2 Anchor Investiagion Drawings.pdf PDF
4006 - Attachment VI - GDSM Utilities Survey 2023.pdf PDF
4000 - 2025.03.17_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf PDF
4005 - Attachment V - GDSM Anchors Phase 2 DIPP_20250318.pdf PDF
1000 - Instructions to Offerors with Provision 52.212-2 and Site Visit Info.pdf PDF
2000 - Price Schedule for GDSM_PH2 Anchor Program.pdf PDF
4001 - Attachment I - Submittal Items and Schedule.pdf PDF
4002 - Attachment II - Foundation Anchor Verification and Modified Extended Creep Test Steps.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

DATE TRANSMITTAL NO.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO:

PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal)

FROM: CONTRACT NO. CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

THIS IS A NEW TRANSMITTAL

THIS IS A RESUBMITTAL OF

TRANSMITTAL

FIO GA DA CR DA/CR DA/GA

ITEM

NO.

(See

Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation

(See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a. i.c. d. e. f. g. h.b.

CONTRACT DOCUMENT

REFERENCE

REMARKS

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

NAME OF CONTRACTOR SIGNATURE OF CONTRACTOR

NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATEENCLOSURES RETURNED (List by item No.)

REPLACES EDITION OF MAR 95, WHICH IS OBSOLETE.ENG FORM 4025-R, MAR 2012

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal

Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted.

B -- Approved, except as noted on drawings. Resubmission not required.

C -- Approved, except as noted on drawings. Refer to attached comments.

Resubmission required.

D -- Will be returned by separate correspondence.

E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify)

K -- Government concurs with intermediate design. (For D-B contracts)

R -- Design submittal is acceptable for release for construction. (For D-B contracts)

ENG FORM 4025-R, MAR 2012

Page of

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

ITEM

NO.

(See Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation (See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a.

i.

c.

d.

e.

f.

g.

h.

b.

CONTRACT DOCUMENT

REFERENCE

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

REPLACES EDITION OF MAR 95, WHICH IS OBSOLETE.

ENG FORM 4025-R, MAR 2012

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted. B -- Approved, except as noted on drawings. Resubmission not required. C -- Approved, except as noted on drawings. Refer to attached comments. Resubmission required. D -- Will be returned by separate correspondence. E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify) K -- Government concurs with intermediate design. (For D-B contracts) R -- Design submittal is acceptable for release for construction. (For D-B contracts)

ENG FORM 4025-R, MAR 2012

1.0 darwin.chen@usace.army.mil 2012-03-27 Forms Design Team Darwin Chen

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

2012-03-29

CurrentPage:
PageCount:
No1_DateTime:
No2_Transmittal:
No3_To:
No8_Pro_Title:
No7_Specification:
No4_From:
No5_Cont_No:
No6a_CheckBox: 0
No6b_CheckBox: 0
No6_Transmittal:
No9a_CheckBox: 0
No9b_CheckBox: 0
No9c_CheckBox: 0
No9d_CheckBox: 0
No9e_CheckBox: 0
No9f_CheckBox: 0
ITEM NO. (See Note 3):
DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.):

SUBMITTAL TYPE CODE (See Note 8):
NO. OF COPIES:
SPEC. PARA. NO.:
DRAWING SHEET NO. :
CONTRACTOR REVIEW CODE
VARIATION Enter "Y" if requesting a variation (See Note 6):
USACE ACTION CODE (Note 9) :
Remarks:
Contractor_Name:
Contractor_Signature:
Authority_Name:
Authority_Signature:
Authority_DateTime:
Enclosures: