This document is an Attachment I Submittal Items and Schedule for the Garrison Dam Spillway Modification (GDSM) Anchor Investigation Phase 2 project. The comprehensive submittal schedule details 31 different submittal requirements across three main phases: Pre-Field Work, In-Progress (Pre-Final) Documentation, and Final Submittals. Pre-Field Work submittals include critical documents such as the Quality Control Plan, Activity Hazard Analysis, Accident Prevention Plan, and various anchor-related plans like the Anchor Test Plan and Concrete Mix Design Plan, most of which must be submitted within 10-30 business days after contract award.

The In-Progress and Final Submittal sections outline detailed documentation requirements for anchor installation, testing, and reporting, including daily shift reports, field test data, bell and underream inspections, grout cube break strength tests, and anchor installation logs. Final submittals include a Draft and Final Anchor Field Installation and Testing Report, electronic anchor installation data, a user manual for on-site anchor instrumentation, and a Standard Operating Procedure for anchor instrumentation collection. Most final documentation must be submitted within 10-20 business days of anchor field testing completion, with specific requirements for government review and comment incorporation.

View the file

Other files for this federal contract opportunity

Other files attached to Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing, newest first.
File Type Posted
Updated 15 Apr 2025 - Price Schedule for GDSM_PH2 Anchor Program.xlsx XLSX spreadsheet
Updated Drawing - GR00108S-503.pdf PDF
Updated Drawing - GR00108S-101.pdf PDF
Updated Drawing - GR00108C-101.pdf PDF
Updated Drawing - GR00108C-102.pdf PDF
Amendment 0002 - W9128F25QA0100002.pdf PDF
4000 - 2025.04.15_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf PDF
Amendment 0001 - W9128F25QA010.pdf PDF
Site Visit Attendance - Garrison Spillway Anchor Testing - 3 Apr 2025.pdf PDF
4007 - Attachment VII - Anchors Phase 2 Geotechnical Data Report_Volume I_20250318.pdf PDF
1000 - Instructions to Offerors with Provision 52.212-2 and Site Visit Info.pdf PDF
2000 - Price Schedule for GDSM_PH2 Anchor Program.pdf PDF
4002 - Attachment II - Foundation Anchor Verification and Modified Extended Creep Test Steps.pdf PDF
4000 - 2025.03.17_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf PDF
4005 - Attachment V - GDSM Anchors Phase 2 DIPP_20250318.pdf PDF
4003 - Attachment III - Phase 2 Anchor Investiagion Drawings.pdf PDF
4004 - Attachment IV - Submittal Form 4025-R.pdf PDF
4006 - Attachment VI - GDSM Utilities Survey 2023.pdf PDF
W9128F25QA010_Solicitation for GDSM Anchor Testing Phase 2.pdf PDF
3000 - SCA 2015-5383 Rev 24 23 Dec 2024 - McLean County ND.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 3 GDSM Submittal Items & Schedule

GDSM ANCHOR INVESTIGATION PHASE 2

ATTACHMENT I – SUBMITTAL ITEMS AND SCHEDULE

# Submittal Type Submittal Name PWS Ref Para.

Schedule1

- Pre-Field Work Prior to Commencement of Field Services

1 Quality Control Plan (QCP) 1.4 Prior to mobilization, NLT 20 business days after award

2 Pre-Work Meeting Minutes (total of 3) 1.8 After award, within 5 business days from Pre-work Review Meeting

3 Activity Hazard Analysis (AHA) 1.10.1 Prior to mobilization

4 Accident Prevention Plan (APP) 1.10.2 Prior to mobilization

5 Site Safety and Health Officer 1.10.3 Prior to mobilization, NLT 20 business days after award

6 Draft Final Anchor Test Plan (ATP) 5.1 Prior to mobilization, NLT 20 business days after award

7 Final Anchor Test Plan 5.1 Prior to mobilization, NLT 30 business days after award

8 Concrete Mix Design Plan (separate or w/ATP) 5.1.a NLT 20 business days after award

9 Anchor Pad Construction Plan (separate or w/ATP)

5.1.a Prior to field mobilization, NLT 30 business days after award

10 Anchor Installation and Testing Schedule (separate or w/ATP)

5.1.a NLT 20 business days after award

11 Anchor Test Pad Details Plan (separate or w/ATP) 5.1.a Prior to field mobilization, NLT 30 business days after award

12 Anchor System Plan 5.1.d NLT 10 business days after award

13 Belling and Underreaming Tools Plan 5.1.e NLT 10 business days after award

In-Progress (Pre-Final) Interim Documentation of Completed Fieldwork

1 Per PWS Section 1.8, Unless otherwise noted, allow for 10-business days for Government review of submittals.

Page 2 of 3 GDSM Submittal Items & Schedule

Para.

Schedule1

14 Pre-anchor Installation: Borehole Inspection 5.3 Verbal confirmation of inspection to QA Lead prior to installation, formal documentation in field Daily Shift Report

15 Anchor Testing Results:

Bell and Underream Inspection

5.3/5.5/5.6 Provide draft of bell and underream inspection documentation in field Daily Shift Report and final documentation in Anchor Field Installation and Testing Report

16 Pre-anchor Installation: Water Tightness Tests 5.9.1 Verbal confirmation of water tightness test to QA Lead prior to installation, written notification in field Daily Shift Report and final documentation in the Anchor Field Installation and Testing Report

17 Anchor Testing Results: In-field Grout Cube Break Strength Test

5.10.1 Provide grout cube break strength results to QA Lead in accordance with the required reporting days after mixing and prior to installation, written notification in field Daily Shift Report and final documentation in the Anchor Field Installation and Testing Report

18 Anchor Pad Acceptance Testing 5.11.13 Within 2 business days of concrete anchor pad work or testing activity

19 Anchor Testing Results:

Anchor Installation Logs

5.14 Provide draft of anchor installation logs in field Daily Shift Report and final logs in Anchor Field Installation and Testing Report

20 Anchor Testing Results:

Verification and Modified Creep Test Results

1.1/4.0/5.2- 5.4/5.12

Pre-final documentation within 5 business days, final documentation in the Anchor Field Installation and Testing Report.

21 Anchor Testing Results:

Instrumentation and Monitoring Information.

1.1/4.0/5.1/ 5.5/5.6/5.15

Pre-final documentation within 2 business days, final documentation in the Anchor Field Installation and Testing Report.

22 Daily Shift Reports (Quality Control) 5.1 Daily (received same workday)

23 Field Test (raw) data 5.1 Within 2 business days

Page 3 of 3 GDSM Submittal Items & Schedule

Para.

Schedule1

24 Monthly Itemized Schedule Update 7.0 Monthly

25 Progress Report with Pay Estimates 10.0 Monthly

26 Monthly Itemized Schedule Update 7.0 Monthly

- Final Submittals Final Complete Documentation of Work

27 Anchor Field Installation and Testing Report (Draft Final)

5.1 Within 20 business days of anchor field testing

completion

28 Anchor Field Installation and Testing Report (Final)

5.1 Within 10 business days of receiving Government

comments on Draft Final Anchor Field Installation and Testing Report

29 Electronic anchor installation and field testing data

5.1 Within 10 business days of anchor field testing

completion

30 User Manual for On-Site Anchor Instrumentation 5.13 Within 20 business days of anchor field testing completion

31 Standard Operating Procedure (SOP) for Anchor Instrumentation Collection

5.13 Within 20 business days of anchor field testing

completion