4000 - 2025.03.17_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf

PDF 515 KB Posted

Attached to
Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing Federal contract opportunity
Solicitation number
W9128F25QA010
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This Performance Work Statement (PWS) details the Spillway Modification Anchor Investigation Phase 2 project for the Garrison Dam in North Dakota. The project involves installing and testing multiple foundation anchors (underream, bell, and Conventional Bond Zone types) in the Fort Union Formation to investigate anchor constructability, design loads, and geotechnical characteristics. Key objectives include drilling twelve foundation anchors with various diameters (57mm and 75mm), constructing twelve reinforced concrete test pads, performing water tightness testing, conducting anchor field testing, and completing comprehensive documentation.

The project requires specialized drilling and grouting techniques, with strict requirements for anchor fabrication, installation, and testing. Contractors must have experienced personnel with specific qualifications in anchor fabrication, installation, and drilling. The work will be completed within 360 calendar days, with all drilling and in-situ activities to be finished by October 31, 2025. The contract is performance-based, with anchors designed to test foundation resistance and anchor design loads, focusing on understanding the geotechnical properties of the clay-shale foundation at the Garrison Dam spillway site.

View the file

Other files for this federal contract opportunity

Other files attached to Garrison Dam Spillway Modification Project - Phase 2 Anchor Testing, newest first.
File Type Posted
Updated 15 Apr 2025 - Price Schedule for GDSM_PH2 Anchor Program.xlsx XLSX spreadsheet
Updated Drawing - GR00108C-102.pdf PDF
Amendment 0002 - W9128F25QA0100002.pdf PDF
Updated Drawing - GR00108S-503.pdf PDF
Updated Drawing - GR00108S-101.pdf PDF
Updated Drawing - GR00108C-101.pdf PDF
4000 - 2025.04.15_Performance Work Statement for GDSM Anchor Inv Phase 2 FRS.pdf PDF
Amendment 0001 - W9128F25QA010.pdf PDF
Site Visit Attendance - Garrison Spillway Anchor Testing - 3 Apr 2025.pdf PDF
4007 - Attachment VII - Anchors Phase 2 Geotechnical Data Report_Volume I_20250318.pdf PDF
4003 - Attachment III - Phase 2 Anchor Investiagion Drawings.pdf PDF
4004 - Attachment IV - Submittal Form 4025-R.pdf PDF
4006 - Attachment VI - GDSM Utilities Survey 2023.pdf PDF
1000 - Instructions to Offerors with Provision 52.212-2 and Site Visit Info.pdf PDF
2000 - Price Schedule for GDSM_PH2 Anchor Program.pdf PDF
4001 - Attachment I - Submittal Items and Schedule.pdf PDF
4002 - Attachment II - Foundation Anchor Verification and Modified Extended Creep Test Steps.pdf PDF
4005 - Attachment V - GDSM Anchors Phase 2 DIPP_20250318.pdf PDF
W9128F25QA010_Solicitation for GDSM Anchor Testing Phase 2.pdf PDF
3000 - SCA 2015-5383 Rev 24 23 Dec 2024 - McLean County ND.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS)

Spillway Modification Anchor Investigation Phase 2

Garrison Dam, ND

MAR 2025

1.0 General Information.

Background: The Garrison Dam – Lake Sakakawea Project was authorized by the Flood Control Act approved 22

December 1944, as part of the comprehensive plan for flood control and other purposes on the Missouri River

Basin. The authorized purposes include flood risk management, hydroelectric power, water supply, water quality control, irrigation, recreation, navigation, and fish and wildlife. The dam was constructed primarily between 1947 and 1954. Major project components include the earth-fill dam embankment, hydroelectric generating plant, and the concrete spillway.

The Garrison Dam Spillway Modification (GDSM) project, currently in design phase, involves installing additional foundation anchors in the spillway chute and stilling basin. A comprehensive anchor test program has been developed and implemented in phases. Phase 1 of the anchor test program was focused on three field anchor installations and tests to better understand foundation characteristics and early anchor production considerations.

Phase 2 of the anchor test program will include construction of concrete anchor pads and drilling, installing and testing of ASTM A722 anchor bar anchors in the Fort Union Formation to ensure the preliminary GDSM anchor design by the GDSM project is constructable, repeatable, and capable of resisting potential design loads. In addition, reducing geotechnical uncertainty with properties such as bearing capacity, undrained shear strength as well as geologic variability across site.

The primary foundation unit for anchor installation and testing is the Fort Union Group of the Tongue River

Formation. The dominant materials in the Fort Union are clay, silt, lignite, and sand, with prevalence in the order listed. The foundation has properties intermediate between soil and rock but are typically described using soil terms

(example: lean clay, CL). Geologic structure typically associated with rock (jointing, bedding planes, and discontinuities) exist within the Fort Union. The clay and silt beds are described as a “soil-like” clay-shale, stiff and highly compacted, but not cemented as rock would be described. The lignite layers are a low grade of coal, firm to hard in its un-weathered state and dark brown in color. The lignite beds are consistent across significant lateral distances and have site-specific designators (names 2U, 1U, 1L, etc. as shown in the attachments). A detailed description of the site stratigraphy will be further described in the Drilling and Invasive Activities Program Plan

(DIPP). The DIPP was prepared by the U.S. Army Corps of Engineering (USACE) and is provided as Attachment

V, GDSM DIPP, for Contractor use in preparation of the Anchor Field Installation and Testing Report.

1.1 Scope of Work: The major work activities for the GDSM Anchor Investigation Phase 2 includes pre-fieldwork submittals, mobilization of equipment to Garrison Dam, material procurement, construction of twelve (12) reinforced concrete test pads, construction of twelve (12) foundation anchors (underream, bell, and Conventional Bond Zone

(CBZ) type anchors), anchor field testing, demobilization, and all incidental activities required to fulfill the requirements of this PWS as stated herein. Activities include, but are not limited to, the following.

a. Pre-fieldwork submittals. The contractor shall prepare pre-fieldwork submittals for Government approval in advance of any planned field work.

b. Casing. Casing is required for this job. Based upon GDSM Anchor Investigation Phase 1, casing should not be sacrificial if proactive measures are taken. Should casing become unrecoverable, a modification for the material cost of the unrecoverable casing will be issued provided the

Contractor has taken reasonable measures to prevent casing from becoming seized in the ground.

c. Drilling. Various types of drill rigs are required to build the various types of anchors in this job.

Controls for measuring and inspecting foundation anchor tip profiles are required per this PWS.

d. Anchor Tendon (i.e., Bar). The anchor tendon shall be fully threaded Grade 150 steel bar meeting the requirements of ASTM A722. A variance is not permitted. Bar sizes and corrosion protection is required in accordance with this PWS.

e. Foundation Anchor Field Testing. Each foundation anchor shall be verification load tested.

Verification testing shall follow the load, duration, and cycles as shown in Attachment II, Foundation Anchor Verification and Modified Extended Creep Test Steps. These schedules are similar to FHWA NHI 05-039 and PTI DC35.1-14 testing requirements. The Contractor shall ensure that special safety considerations are defined in the APP and implemented when testing

CBZ anchors due to past failures at projects with similar weak foundations.

f. Foundation Anchor Instrumentation. The foundation anchor head and tip are to be instrumented in accordance with this PWS. The foundation anchor head shall have an automated long-term load monitoring system to measure changes in the lock-off load of each anchor. The field stress testing equipment and instruments shall be custom-built and manually operated. Each foundation anchor tip shall have two (2) strain gauges capable of measuring the force in the anchor bar at the anchor tip during testing. Two strain gauges are required for redundancy.

The Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government. This is a fixed priced, performance-based service contract where the

Government defines and measures desired outcomes, while Contractor methods are generally not constrained or directed. The Government will be onsite, and the Contractor shall provide the Government with safe access as needed to perform Quality Assurance (QA) for all anchor investigation activities as prescribed in this PWS.

The Contractor shall not take direction from any USACE employee or any other person other than the

Contracting Officer that changes the terms and conditions of this contract action, the scope, or any change that impacts the cost, price, or schedule. Coordination and communication of work activities with the COR and onsite Government QA lead is strongly encouraged but the Contracting Officer should be included in all official correspondence or Contractor progress updates. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action; the signed modification shall be received by the Contractor before the Contractor shall act upon the changes. The Contractor shall contact the

Contracting Officer of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contractor Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority shall be reported to the Contracting Officer. CORs are limited to the authorities stated in the COR appointment letters and the allowance of the use of discretionary tasks as defined in this document.

1.2 Period of Performance: The Contractor shall complete all work within 360 calendar days from issuance of the award. The Contractor shall efficiently plan, coordinate, and execute work so that materials can be acquired and all drilling and in situ activities completed before 31 October 2025. Other work activities shall be completed with mutually agreeable dates coordinated between the COR and the Contractor described in 5.0 Specific Tasks.

1.3 Contractor Personnel: The following are the qualifications required for the anchor fabricator, anchor hole drillers, and anchor installers. Qualifications shall be submitted in the QCP. Exemptions to the below cases shall be first requested by the Contractor and may be considered on a case-by-case basis by the COR with coordination of the

Contracting Officer.

a. Anchor Fabricator Qualifications. The anchors shall be fabricated by a manufacturer that has been in the practice of designing and fabricating bar anchors in accordance with industry standards similar in size and scope to this project for at least ten years. See Instructions to Offerors for details related to procurement of

ASTM A722 anchor bars and the Buy American Act.

b. Anchor Installer Qualifications. The anchors shall be assembled and installed by a firm which is regularly engaged in the installation of bar anchors and has at least five years of experience in the installation of similar anchors. The firm shall have a field superintendent and a field engineer onsite during all anchor installation and testing activities. The field superintendent shall have supervised the installation of anchors on at least three projects of similar scope and size and have 10 years of experience installing and testing bar anchors. The field engineer shall be an engineer with experience installing and testing vertical bar anchors of similar type and size. The field engineer shall have a Professional Engineer (P.E.) licensure or 5 years of experience installing and testing anchors similar to those in this award. Preferred that these workers have experience installing similar anchor systems on dam or other hydraulic structures. The firm shall have a Senior Engineer available for consultation with a minimum of 10 years of experience designing and constructing conventional anchors. Experience with drilled bell and underream anchors is preferred.

c. Anchor Hole Driller Qualifications. The anchor holes shall be drilled by a driller with at least three years of experience drilling anchor holes of similar requirements as this PWS. The driller shall have a minimum of 3 projects that demonstrate experience drilling conventional bond zone, belled, and underreamed type bored holes. All drilling activities are to be supervised by the field superintendent and field engineer referenced in

Section 1.3.1. Driller shall have experience drilling with the same type of drill rigs and tools as discussed in this PWS. Drill rig operators shall meet current requirements of ER-1110-1-1807 (June 2023).

1.3.2 The Contractor shall perform all work under this award using their own forces except as provided in

Paragraph 1.3.3 Subcontracting. Employees who perform this work shall be qualified persons on the

Contractor’s own payroll.

1.3.3 Subcontracting: The Contractor shall not subcontract any work without written approval of the

Contracting Officer. Subcontractor compliance with the provisions of this contract shall be the responsibility of the Contractor.

1.4 Quality Control:

1.4.1 The Contractor, not the Government, is responsible for quality control actions necessary to meet the quality standards set forth by the PWS. The Contractor shall demonstrate in the QCP that the USACE

3-Phase Inspection Model will be followed for the definable features of work. The Contractor shall maintain and update the QCP as necessary during the execution of this contract. Quality controls shall consist of plans, procedures, and organization necessary to produce a product that complies with the contract requirements. The quality controls shall include all on-site operations. Utilize established

Contractor or Manufacturer quality control procedures to assure full compliance with all off-site work.

The QCP shall include the following items at a minimum and shall not be modified without written approval from the COR.

a) Equipment data sheets indicating proposed equipment satisfies the equipment requirements specified in Section 4.0, Contractor furnished items.

b) Plan for performing drilling and anchor installation in accordance with the Contract.

c) Plan for independently validating data collection for accuracy and confirming instrumentation is functioning properly, including tolerances and potential sources of error in measurement.

d) Peer review of postprocessing of anchor test results.

e) Project schedule aligned with the PWS activities including completion of field tasks and transmittal of data.

f) Table of products, reviewers, and timeline when the product shall be reviewed as well as how

Contractor will document it has completed these reviews. (Who, What, When, How documented).

g) Field Supervision Personnel including the Field Superintendent and the Field Engineer: Name, organization, title, registrations, years of experience.

h) E-Verify and iWatch Security requirements for Contractor Personnel.

i) Anchor Hole Driller Qualifications: names, similar example projects, and years of experience.

j) Anchor Installer Qualifications.

k) Anchor Fabricator Qualifications.

l) Materials Testing Lab Qualifications including validation with Engineer Research and

Development Center (ERDC) as required by the paragraphs entitled “Accreditation Requirements” or “Construction Materials Testing Laboratory Requirements” for NAVFAC contracts. Contractor shall submit the USACE/ERDC approved third-party testing laboratory company to the COR for approval prior to mobilization.

m) Subcontractor technical support staff: Name, organization, title, registrations, years of experience

Once accepted, the QCP will be incorporated into the Quality Assurance Surveillance Plan (QASP). The

QASP will be utilized to monitor the Contractor’s efforts. The QASP is made part of the solicitation, but not a part of the resultant contract. The QASP is not a contractual instrument and may be changed at the COR’s discretion. The Contractor then uses the QASP to guide and document the implementation of the required management and quality control actions to achieve the specified results. The COR reserves the right under the Contract Terms and Conditions-Commercial Items (FAR 52.212-4) to inspect and test the services called for by the Contract, to the extent practicable at all times and places during the term of the task order. Non-conforming services will be rejected.

Responsible Individuals for Quality Control shall maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. In the QCP submittal, qualifications submitted for the responsible individuals shall demonstrate a minimum of 5 years of experience over the past 10 years performing

Contractor Quality Control (CQC) on projects of similar scope as this project and these individuals shall have Professional Engineer licensure. CQC staff will be subject to acceptance by the COR.

1.4.2 The Contractor shall designate, in writing, an employee who shall serve as the contact for matters involving quality and performance or nonperformance of the required work stated in this PWS. The

CQC person may have dual roles on the project as accepted by the COR. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the Contractor as necessary to ensure that the required work is performed in accordance with the standards contained herein. The quality control personnel shall be present full time both on-site and off-site. The names of the designated personnel should be included in the QCP that is submitted prior to start of work. The

Contractor shall furnish the above written designation to the Contracting Officer’s Representative

(COR) prior to mobilization. The Contractor shall include the name(s), address(s), and telephone number(s) of the responsible individual(s).

1.4.3 The Contracting Officer reserves the right to disapprove any individual whom he considers unqualified or unable to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the Contractor.

1.5 Quality Assurance: The COR will use a QASP to ensure that the Contractor is performing the services required by this PWS in an acceptable manner. The COR may use Quality Assurance Evaluators (QAE(s)) to assist with the quality assurance methods.

The COR has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The COR will perform inspections in a manner that will not delay the work unnecessarily. The COR will have a geologist or civil engineer (Geotech, structural, materials, or hydraulics) on-site during the anchor test program. The onsite geologist or civil engineer will represent the COR as the QA Lead. In addition, a construction quality assurance inspector from the Garrison Dam project office may be on-site. The

Contractor and any relevant sub-contractor shall interact and communicate field work status and findings with on-site USACE staff as well as the COR, Technical Points of Contact (TPOC), and Onsite USACE QA Lead. If USACE staff is not on site, the Contractor shall not delay the work and proceed in accordance with the contract. Presence of

USACE staff does not relieve the Contractor of its duty to perform or provide quality control.

1.5.1 If any of the services do not conform to contract requirements, the Government may require the

Contractor to perform the services in conformity with contract requirements and at no additional cost to the Government. If the contract requirements are not met after a second attempt the Government may

(1) require the Contractor to take necessary action to ensure that future performance conforms to contract requirements or (2) reduce the contract price to reflect the reduced value of the services performed.

1.5.1.1 Upon verification of a corrective action report, the COR will notify the Contractor that they are required to re-perform specific services.

1.5.2 The Government may take action, if the Contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The

Government may (1) by contract, or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that related to the performance of such service or (2) terminate the contract in whole or in part.

1.5.3 The Contractor shall replace/repair any damage to Government property due to negligence, at his or her own cost. The Government may take action, if the Contractor fails to replace/repair any damage to

Government property. The Government may (1) by contract, or otherwise, replace/repair damaged

Government property and charge to the Contractor any cost incurred by the Government to replace/repair any damage.

1.6 Hours of Operation: Work hours of operation should be planned during daylight hours from 0700 to 2000 local time (Central) but may be adjusted as needed upon approval of the Government. Requests for working outside of these hours shall be made in writing to the COR. Work should be planned for daylight hours; however, light plants

(if needed) may be used if approved in the APP and with approval of the COR.

1.7 Utility Clearance and Site Access. A previous utility survey completed in 2023 during Phase 1 drilling activities shall be utilized by the Contractor. In addition, the Contractor shall contact the North Dakota One Call service prior to commencement of drilling operations, to have public utilities marked in areas not previously surveyed (i.e., areas downstream of Phase 1 drilling activity). USACE engineering and operations staff are responsible for identifying and marking any project utilities that are not covered by the One Call service. Utility clearances and a field-check

(review with site USACE Staff) of all activity locations shall occur prior to field work.

Access to proposed anchor installation site shall be through a group of maintenance haul roads which can be reached from the main road along the embankment dam’s toe. These haul roads, depending on road condition and equipment size, may be restrictive to contractor mobilization. In addition, overhead lines will have to be assessed in anchor locations and may need to be de-energized when drilling at particular locations. Any damage done to roads, pads, or fields shall be remediated to equal as found condition prior to fully demobilizing from the site. See Attachment VI, 2023 Utility Survey, for more details about the Government provided utility survey.

1.8 Pre-Work Meetings: The Contractor shall participate in three pre-work meetings for different phases of the project following award of the requirement and prior to commencement of major work activities to coordinate with the COR and Technical Points of Contact. The Contractor is required to submit meeting minutes for each meeting.

a. Contract Kickoff Meeting. Prior to commencing any activities, the Contractor shall participate in a virtual

Kickoff Meeting. The COR will review contract requirements as part of the meeting. The Government will host the meeting and develop the agenda. The Contractor shall take and distribute meeting minutes for the kickoff.

This meeting will cover topics including work requirements, scheduling, submittal process, material procurement lead times, review of the Activity Hazard Analysis (AHA), and Abbreviated Accident Prevention

Plan (AAP). The Contract Kickoff meeting will be planned for four (4) hours.

b. Pre-Mobilization Meeting. This virtual meeting shall be conducted a week prior to mobilization to the site. This meeting ensures all necessary on-site coordination has been completed. The Pre-Mobilization meeting will be planned for two (2) hours.

c. On-Site Kickoff Meeting. Following mobilization and prior to the start of drilling, a formal on-site meeting will be held with Garrison Dam project staff and QA staff, the Contractor anchor driller and anchor installer, and QC staff. The Government and Contractor shall review the QCP and plan for ongoing communications. The

Contractor shall document and distribute meeting minutes. The On-Site Kickoff meeting will be planned for two (2) hours.

1.9 Submittals. Government quality assurance review and approval is required for all submittals. Unless otherwise noted, allow for 20 calendar days for Government review of submittals. Rejected submittals shall be resubmitted for approval.

The approval of submittals shall not be construed as a complete check and will not relieve the Contractor of the responsibility of quality control and providing satisfactory services in accordance with this PWS.

1.9.1 Submittal List and Schedule: See Attachment I, Submittal Items and Schedule, for more details about required submittals.

1.9.2 Submittal Form: The attached submittal form (ENG Form 4025-R) shall be used for transmitting the submittal. This form may be reproduced by the Contractor and shall be properly executed by filling out all the heading blank spaces and identifying each time submitted. Special care should be exercised to ensure proper listing of the specification paragraph or sheet number of the contract drawings pertinent to the date submitted for each item. The Contractor shall provide copies for each submittal to the locations stated below.

1.9.3 Means of Approvals: Action Codes will be as indicated on the back of ENG Form 4025-R. The

Contracting Officer’s Representative will mark an Action Code on each submitted ENG Form 4025 prior to returning a copy to the Contractor. The approval of a submittal by the Contracting Officer shall not be construed as a complete check but will indicate only that the general method of prosecution and detailing is satisfactory. Approval will not release the Contractor of the responsibility for any error that may exist, as the Contractor is responsible for satisfactory prosecution and detailing of all work.

1.9.4 When Not Approved: The Contractor shall make all corrections required by the COR and promptly furnish a corrected submittal in the form and number of copies as specified in the initial submittal.

1.9.5 Submittal Delivery Contacts: The Contractor shall provide an electronic copy of ENG Form 4025-R with each submitted item to the COR and the Primary and Alternate Technical Points of Contacts listed in Section 8.0, Coordination.

1.9.6 Submittal Delivery Means: Provide the submittals listed in the subparagraphs below to the

Government for review. Provide electronic deliverables for the submittal packages that are electronically bookmarked. Transmit deliverables to the Government using DoD SAFE

(https://safe.apps.mil/). Physical hard drives may be required for individual files larger than 8 gigabytes (GB). Electronic files shall be in a complete and useable format by the

Government. Provide the original electronic file types when requested by the Government and at the conclusion of this contract. All documents shall be fully compatible with software programs identified in the narrative below without any changes required of the Government.

a. Provide electronic files meeting the following requirements:

i. Meeting Minutes

• Size: Letter, 8.5-inches by 11-inches.

• File type: Microsoft Word.

• Deliverable type: Portable Document File (PDF).

ii. Reports

• Size: Letter, 8.5-inches by 11-inches.

• File type: Microsoft Word.

• Deliverable type: Portable Document File (PDF) and Microsoft Word.

iii. Drawings

• Plot Size: Half, 11-inches by 17-inches.

• Plotting Requirements: Flattened, optimized, and text searchable.

• File types: AutoCAD and Civil 3D.

https://safe.apps.mil/

• CADD Standard: USACE A/E/C CAD Standard, Release 6.2 (ERDC-ITL-TR-19-

7). https://cadbimcenter.erdc.dren.mil/

• Deliverable type: Portable Document File (PDF)

iv. Testing Data

• Size: Letter, 8.5-inches by 11-inches or 11-inches by 17-inches.

• File type: Microsoft Word or Excel.

• Deliverable type: Portable Document File (PDF).

1.10 Safety, Standards and Regulations: The Contractor shall perform to the Standards in the contract and comply with all local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations. In the event that one regulation is more restrictive than another, the more restrictive requirement will apply. Applicable regulations include, but are not limited to the following:

a. Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and Regulations Governing

Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316

(http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2-

316.pdf?ver=2013-08-22-104526-670);

b. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated March

2024.

c. Occupational Safety and Health Standard (29 CFR 1910) regulations related to the Management and

Control of Hazardous Wastes;

d. RCRA - Resources Conservation and Recovery Act (Primarily 40 CFR 268);

e. TSCA - Toxic Substances and Control Act (Primarily 40 CFR 761);

f. DOT - Department of Transportation Regulations for the Transportation of Toxic Wastes;

g. CERCLA-Comprehensive Environmental Response, Compensation, and Liability Act of 1980

(SUPERFUND);

h. CWA - Clean Water Act of 1972;

i. Safe Drinking Water Act of 1974;

j. All other applicable Federal, State, Country and City codes, laws, standards and regulations;

1.10.1 Activity Hazard Analysis (AHA): Before beginning each activity, task or Definable Feature of Work

(DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity shall prepare an AHA and review it with the work crew that will perform the work.

AHAs shall be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer

Representative. Submit the AHA with the APP.

1.10.2 Accident Prevention Plan (APP): The Contractor shall prepare and submit a full Site-Specific APP to the government for approval that covers plans regarding hazards for the work being performed. The

Contractor shall review the APP outline in the U.S. Army Corps of Engineers (USACE) safety and health manual EM 385-1-1 to determine the safety plans that are required for the scope of work and prepare their document for approval. The contractor shall use a qualified person to prepare the site-specific Accident Prevention Plan. For Contractor awareness, there are new requirements for Site Safety and Health oversight. The contractor shall prepare the APP in accordance with the format and requirements of EM 385-1- 1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.

1.10.3 Site Safety and Health Officer (SSHO): Provide an SSHO that meets the requirements of EM 385-

1-1 Section 1. The SSHO shall ensure that the requirements of 29 CFR 1926.16 are met for the project. Designate one person at the project site to function as the SSHO and not have any other duties. The SSHO or an equally qualified Alternate SSHO shall be at the work site at all times to implement and administer the Contractor's safety program and Government-accepted Accident

Prevention Plan. The SSHO and Alternate SSHO shall have the required training, experience, and qualifications in accordance with EM 385-1-1. If the SSHO is off-site for a period longer than 24 hours, an equally qualified alternate SSHO shall be provided and shall fulfill the same roles and https://cadbimcenter.erdc.dren.mil/ http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1165-2-responsibilities as the primary SSHO.

1.10.4 Environmental Protection Plan (EPP): The Contractor shall prepare and submit an

Environmental Protection Plan in accordance with EP 200-2-3 – Environmental Compliance

Guidance and Procedures. The EPP shall outline the Contractor’s plan to first avoid and then minimize negative environmental impacts to the worksite and adjacent environment. The Contractor shall provide work plan details in accordance with Federal, State, and local laws that include means to protect features plans, sediment and erosion control measures, environmental monitoring procedures, and hazardous material management plans; and all other aspects of environmental protection planned by the Contractor during this project. The Contractor shall use a qualified person approved by the COR to prepare and manage the EPP.

1.10.5 Hazardous Toxic and Radioactive Waste (HTRW): There is no known HTRW materials at this location. If HTRW is encountered, activity shall be terminated at that location and the TPOC and

COR contacted. The material will be investigated, and a modification put in place to change how the work will be further performed at that location and materials properly disposed of.

1.10.6 Endangered Species:

1.10.6.1 Piping Plover: The project area is located within the migration path of the Northern Great Plains

Piping Plover; however, 31 years of historical surveys, along with a habitat assessment, have provided negative findings. However, the following guidelines shall be followed:

a. If work is initiated within 0.5 miles of the project footprint prior to 15-Apr, no biological surveys to determine if Piping Plovers or suitable habitat is present are required prior to the commencement of work.

b. If work commences after Apr-15, and through Aug15, a survey via a US Fish & Wildlife

Service (FWS) permitted and trained USACE-Garrison Project Biologist is required within 48-hours of project initiation. The Contractor shall provide a 7-day advance notice of project initiation so biologists can accommodate the survey requirement in a timely manner and not cause project delays. If suitable nesting and foraging habitat is located within 0.5 miles of the project site, USACE biologists will conduct periodic surveys within a 0.5-mile radius if breaks in construction are greater than 72 hours.

If, at any point, piping plovers are observed within 0.5 miles of the project area, work shall immediately cease and the COR shall be contacted. The project shall be suspended indefinitely until

USFWS and USACE can collect the totality of circumstances and provide additional guidance.

Please contact USACE-Threatened & Endangered Species Lead, Scott Sterling at 701-301-0654, for initiating surveys, questions on regulations, or reporting a sighting and/or concern.

1.10.6.2 Bald and Golden Eagle: Due to the project footprint being located alongside the forested

Missouri River corridor, a Bald and Golden Eagle survey will be conducted by a trained USACE-

Garrison Project Biologist, Scott Sterling, if the project commences between February 1st – July

15th. If an active nest is located within 660ft of the project area, USFWS will be contacted for further guidance. All work within 660ft of the active nest shall cease until further notice.

The Contractor shall provide a seven (7) day advance notice of project initiation so biologists can accommodate the survey requirement in a timely manner and not cause project delays. Please contact USACE-Threatened & Endangered Species Lead, Scott Sterling at 701-301-0654, for initiating surveys, questions on regulations, or reporting a sighting and/or concern.

1.10.7 Certification of Real Estate/Utilities Clearances: USACE has cleared the Real Estate, which is

Government Property, for use by the contractor. The Contractor shall coordinate with utility locating companies and the project site to identify potential hazards.

1.11 Antiterrorism/Operation Security Requirements:

1.11.1 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer

Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the

Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition

(FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health

Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the

FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

1.11.2 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate

Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database

(commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.

1.11.3 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say

Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

1.11.4 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under

United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

1.12 Warranties: Contractor shall provide standard industry warranty for all equipment installed and for all repairs made.

This will cover at minimum one year of service, with the epoxy for attaching strain gauges being an exception. It will http://www.e-verify.gov/) http://www.e-verify.gov/) include all equipment, costs, and work associated with replacement of defective parts.

2.0 Definitions and Abbreviations: The following definitions and Abbreviations apply wherever used in this PWS:

2.1 Definitions:

Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot considered satisfactory on the average. The allowable leeway or variance from a standard before the Government will reject the specific service.

Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.

Foundation Anchor: Either a passive or prestressed anchor installed into the foundation at Garrison

Dam’s spillway. The foundation is an intermediary rock classification (i.e. over-consolidated clay-shale) with many soil parameters. Thus, the anchor is not strictly a rock or soil anchor.

Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.

Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.

Quality Assurance Surveillance Plan (QASP): An organized written document used by the Government for quality assurance surveillance. Document contains sampling/evaluation guides, checklists, and the performance requirements summary (PRS).

2.2 Abbreviations:

• AAP – Abbreviated Accident Prevention Plan

• AHA – Activity Hazard Analysis

• APP – Accident Prevention Plan

• AL – Alignment Load (used in anchor testing)

• ASTM – American Society for Testing and Materials

• CBZ – Conventional Bond Zone (in relation to anchor type)

• CERCLA – Comprehensive Environmental Response, Compensation, and Liability Act

• CFP – Code of Federal Regulations

• COR – Contracting Officer’s Representative

• CQC – Contractor Quality Control

• CWA – Clean Water Act

• DFOW – Definable Feature of Work

• DIPP - Drilling and Invasive Activities Program Plan

• DOT – Department of Transportation

• DL – Design Load (used in anchor testing)

• ERDC – Engineer Research and Development Center

• EM – Engineering Manual

• ER – Engineering Regulation

• FP&P Plan – Fall Protection and Prevention Plan

• GDSM - Garrison Dam Spillway Modification

• HEC – Hazardous Energy Control

• MTC – Materials Testing Center

• NAVD – North American Vertical Datum

• NAVFAC – Naval Facilities Engineering Systems Command

• NLT – No Later Than

• PED – Preconstruction Engineering and Design

• PDF – Portable Document File

• PRS – Performance Requirement Summary

• PTI – Post-Tensioning Institute

• PWS – Performance Work Statement

• QA – Quality Assurance

• QAE – Quality Assurance Evaluators

• QA Lead – Government assigned point of contract for field quality assurance.

• QASP – Quality Assurance Surveillance Plan

• QC – Quality Control

• QCP - Quality Control Plan

• RCRA – Resources Conservation and Recovery Act

• SSHO – Site Safety and Health Officer

• TPOC - Technical Points of Contact

• TSCA – Toxic Substances and Control Act

• USACE – United States Army Corps of Engineers

3.0 Government Furnished Items and Services:

3.1 Utilities:

a. Water Supply. A raw (non-potable) water fire hydrant is available at the Garrison project, outside maintenance shop located at the toe of the dam. Within the anchor testing area, water may be taken from the stilling basin and outlet channel if approved in the APP.

b. Cuttings Disposal Area. Cuttings shall be captured and properly disposed of so as not to reenter the environment. The Contractor shall coordinate with Garrison project staff for a disposal location on the west side of the spillway.

c. Electrical. There is no electrical hook-up in the location of the anchor testing area. The contractor shall supply all necessary power to the work area.

d. Bathrooms. Temporary bathroom facilities shall be provided by the Contractor during the duration of the field work, and shall be made available to Government Staff for use

4.0 Contractor Furnished Items and Responsibilities: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3.0 of this PWS.

a. Drilling Equipment. Drilling equipment and methods shall be suitable for advancing each hole to the required depth, diameter, and alignment at the correct location and with the appropriate degree of hole cleanliness. The drilling system shall be capable of drilling to a 2 degrees tolerance as measured against the specified anchor centerline.

Drilling equipment for the bell-out anchors shall be accomplished with Kelly drilling equipment (i.e., the pilot hole and bell shall be drilled and cuttings removed mechanically, without the aid of drilling fluids to remove cuttings). For other anchor types, the Contractor shall select the drilling means and methods provided they do not cause any damage to the structure or adversely affect the beneficial impact of any pre-grouting operation, or in any way inhibit bond development with the bar grout. See

Section 5.3 for restrictions and requirements for use of water and air drilling fluids for CBZ and underream anchors. During all drilling casing is required for hole stability. The casing shall be advanced with or ahead of the drilling.

b. Redrilling Equipment. Redrilling equipment and methods shall be suitable for redrilling each hole to the required diameter, depth, at the correct location and with the hole being clean of cuttings to at least the bottom of the bond zone, underream sump, or bell. Percussive drilling equipment is prohibited for redrilling. The drilling system shall be capable of following the original anchor bore hole without changing the alignment and shall not be detrimental to the pre-grout filling the voids outside the original borehole. The underream anchor drilling method shall use air as a drilling fluid; drilling fluid other than air is prohibited for underream construction. For CBZ anchors, the drilling system shall leave rough side walls in the bond zone and 5 feet above the bond zone.

c. Grouting Equipment. The grout mixer shall be a high-speed, high-shear, colloidal type grout mixer capable of continuous mechanical mixing that shall produce uniform and thoroughly mixed grout which is free of lumps and undispersed cement. The mixer shall be equipped with suitable water and admixture measuring devices calibrated to read in gallons and tenths and designed so that after each delivery the gauge can be conveniently set back to zero.

The grout pump shall be a progressive cavity type capable of pumping at rates at or below 20 gallons per minute. It shall be capable of pumping at a pressure of at least 50 psi at zero flow rate and capable of pumping at a rate fast enough to fill the hole in sufficient time to allow for a packer to be installed and the hole pressurized prior to the grout achieving initial set. The pump shall be capable of pumping both neat cement grout and sanded grout mixes. The pumping equipment shall have a digital pressure gauge capable of measuring pressures of at least 100 psi or twice the required grout pressure, whichever is greater, but shall be able to measure grouting pressure to the nearest 1 psi.

d. Watertightness Equipment. The type of single packer(s) used to isolate the stage to be watertightness tested or grouted and its means of inflation, sealing, and retrieval upon completion are the decisions and responsibilities of the Contractor. The packer shall have a minimum working pressure of 500 psi. The packer shall also be of a length sufficient to allow for proper sealing in a potentially rough sided borehole with extensive zones of permeable materials.

The watertightness pump shall be of the progressive cavity type, capable of pumping at least 50 gallons per minute, and shall be capable of being regulated for flows less than 1 gallon per minute.

e. Specialized Underream and Bell Equipment.

• Underreamed Anchors. A retractable cutter is required for underream anchors that can develop an underream diameter of 18 inches and up to 24 inches.

• Belled Anchors. A retractable tool for developing 34 inches in diameter belled drill holes is required. Bell tooling shall be top-hinged and have a spin dump at the bottom for collecting cuttings in a cleanout bucket. The cleanout bucket is required that can be attached to the bell tooling. A separate cleanout bucket is required to have onsite to clean the bell’s sump as required upon inspection. The Contractor may propose alternative heights of a cleanout bucket than shown on the drawings for COR approval.

f. Stressing/Testing Equipment. Stressing/testing equipment shall consist of a hydraulic jack with pump for applying the load, calibrated pressure gauges, and two gauges (one dial and one digital) to measure anchor movement.

The hydraulic pumps shall be pressure compensated variable displacement or have closed-loop control with a proportional relief valve and pressure transducer. Ideally, the hydraulic pump systems shall be capable of producing the anchor testing loads and autonomously holding the creep test load with an accuracy of 10 psi without manual intervention. If the Contractor is unable to meet this requirement a manual system for testing will be permitted if the operator does not manipulate the load resulting in inaccurate true creep data. The hydraulic pump system shall be capable of running automatically and manually, or if that is not possible, then manual is acceptable under the condition above. The hydraulic pump system shall be programmable with user-defined target pressure, ramp rates, and dwell times. The hydraulic pump system shall be capable of applying each load increment in less than 60 seconds. The hydraulic system shall have a digital display, showing at a minimum, test pressure (psi, reading to 1 psi and temperature compensation), ramp time (secs), and hold time (secs/minutes). The Contractor may add a dial pressure gauge to visually help hit target loads, but the digital gauge is the official load gauge.

Stressing (jacks) shall be hydraulically operated and have a capacity sufficient to stress the anchors to the specified required Test Loads within the rated capacity in one stroke. The ram travel of the stressing jack shall not be less than the theoretical elastic elongation of the total anchor length and the expected movement of the anchor pad and underream at the Maximum Test Load, but not less than 12 inches.

Stacking jacks or any multiple jack configurations for stressing an anchor are prohibited. Pumps shall be capable of applying each load increment in less than 60 seconds and shall be capable of maintaining the hydraulic pressure within 20 psi.