3B.C(2024.11.20)USBR_-_POR_24OCT11(FINAL)-3CA1541.pdf
PDF 291 KB Posted
- Attached to
- General Services Administration (GSA) seeks to lease office space in the Sacramento Metro Area
- Solicitation number
- 3CA1541
About this file
This document appears to be a set of general requirements from the U.S. Bureau of Reclamation, Central Valley Operations Office (CVO) for a new General Services Administration (GSA) leased space in the Sacramento, California area. The requirements cover site location, building specifications, HVAC, electrical, communications, security, and other facility needs to support CVO's 24/7 operations. Key details include a minimum of 32,046 usable square feet, 90 parking spaces, a communications tower and data structure, redundant telecommunications access, critical power systems and environmental controls, and compliance with federal security standards. The building must meet specific electrical, mechanical, and IT infrastructure requirements to support CVO's mission-critical operations. This document is being provided in relation to a potential pre-solicitation notice from GSA for leased office space in the Sacramento metro area to house the new Federal Operations Center for CVO and the National Oceanic and Atmospheric Administration.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Central Valley Operations Office New GSA Lease Building Program Requirements
U.S. Department of the Interior 10/11/2024
Contents
1. SUMMARY
2. SITE LOCATION REQUIREMENTS
3. BUILDING REQUIREMENTS
3.1. Office Requirements
3.2. Parking Requirements
3.3. Outside Storage
3.4. Design Requirements
4. PROGRAM REQUIREMENTS
4.1. Accessibility
4.2. HVAC Requirements
4.2.1. General HVAC Requirement
4.2.2. Control Center Room / Data Center Room
4.2.3. Building Control System
4.2.4. Duct Design
4.3. Electrical Requirements
4.3.1. Service Voltage
4.3.2. Lightning Protection Systems
4.3.3. Electrical Distribution System
4.3.4. Arc Flash Warnings
4.3.5. UPS System
4.3.6. Generator
4.3.7. Grounding System
4.3.8. Lighting Systems
4.3.9. Data Cabling and Electrical Power for Specialty Items
4.4. Communications
4.5. Telecommunications Tower and Communications Tower Data Structure
4.6. Fire Protection Criteria
4.7. Security and Safety Requirements
4.8. Exterior Glass - Blast and Anti-Glare Film
4.9. Lactation Room
1. SUMMARY
The United States Bureau of Reclamation, Central Valley Operations Office (CVO) is seeking to collocate with the National Oceanic and Atmospheric Administration (NOAA) into a new General Services Administration (GSA) leased space. This document includes general CVO requirements. Refer to NOAA documentation for NOAA requirements. Should a conflict between CVO and NOAA requirements exist, CVO and NOAA will determine the most suitable requirement to be adopted. The collective requirements from NOAA and CVO are being referred to as the new Federal Operations Center (FOC).
2. SITE LOCATION REQUIREMENTS
2.1. The proposed location must be coordinated with the current zoning and growth plans of the local jurisdiction. The current growth plans must not interfere with Government operations.
2.2. The property shall be at least 1 mile away from any railyard.
2.3. The property must be located outside of the 500-year Federal Emergency
Management Agency floodplain.
2.4. The Property must have an Architectural Barriers Act Accessibility Standard
(ABAAS) accessible route that provides a short and unobstructed path from the parking to the main entry point of the building.
2.5. The Government has 24/7 operations and does not want to disturb neighboring residential or other properties. The Government’s 24/7 operations must also not be adversely impacted by the operations of neighboring properties. In considering these requirements, the property shall have a dividing barrier (such as a two-way public road, canal, open space, tributary, etc.) acceptable to the LCO between the property and any residential areas, retail, or commercial properties having operations (such as deliveries, after hours activities, etc.) that would impact the Government’s operations. The property shall also not be located adjacent to high traffic or trucking areas and must support a 24/7 operation without significant noise or light interference.
2.6. The Property must reside within the described delineated area.
2.7. Provide ground space (20 feet by 35 feet) for a 60 feet to 70 feet high communications tower and an adjacent concrete or similar Communication Tower Data Structure (120 square feet). This area to have anti-climb security perimeter fencing.
2.8. The property must provide direct line of sight to 38.70787535117413, -
121.15724804201218 (top of Folsom Dam) to facilitate microwave communication needs. The line of sight should not be obstructed by anything on the property throughout the term of the Lease. The Government has the right to reject any properties that do not meet the Communications Tower radio frequency testing requirements prior to lease award if the proposed location is not acceptable to the LCO. The Lessor will not obstruct and will not keep any obstructions on the property for the term of the lease that causes any interference with the line of sight for the communications tower and path of radio frequency.
2.9. The property must meet Interagency Security Committee Risk Management Process Federal Security Level II for Federal facilities or can be reasonably modified to meet these standards.
2.10. The property shall have a turnaround for delivery trucks, touring buses, and large commercial vehicles (i.e., garbage or recycling vehicles, deliver vehicles, cranes, equipment trailers, etc.). Delivery trucks must have access to CVO’s designated Delivery Receipt Area. Circulation space acceptable to the LCO is required for tour buses that visit the facility. Buses need an ample amount of room to drive through the parking lot and make turns. The parking lot should not be tight and should allow for this type of traffic.
2.11. Provide ground space with security perimeter fence near the building to locate the emergency generator and fuel storage for ease of access, maintenance, and support for CVO operations.
2.12. Provide separate metering for all utilities to the CVO space.
2.13. Onsite parking for all federal employees, guests, collaborators, supporting operations partners must be located on the property with the Federal Operations Center. CVO requires a minimum of 90 parking spaces per the Paragraph 3.2.
2.14. A minimum 4,050 ABOA SF is required to be located on the ground floor. Other spaces need not be on the ground floor but must be located no higher than the next level above. Identified room adjacency requirements must be observed. Spaces on each floor must be contiguous.
2.15. The Government reserves the right to reject locations that the Government determines are subject to potential inundation or obstruction of access due to inundation resulting from the failure of a Dam, a portion of a Dam, or other water-related facilities.
2.16. Min 7,870 ABOA SF to be a minimum 250 lb/ft floor load. At least 2,500 ABOA SF out of Min 7,870 ABOA SF to be on the 1st floor.
3. BUILDING REQUIREMENTS
3.1. Office Requirements
To meet mission requirements, CVO is seeking approximately 32,046 usable square feet of space in the Sacramento, California area. See the attached Appendix A – CVO Room Matrix for room sizes and additional requirements information.
3.2. Parking Requirements
CVO requires the following Parking Spaces to meet operational needs:
• Secured/Fenced parking for Government Owned Vehicles: 30 spaces. 28 spaces shall be 18 feet by 8.5 feet per minimum and 2 spaces must be oversized (20 feet by 10 feet per minimum).
• Parking for Privately Owned Vehicles: 60 spaces (18 feet by 8.5 feet per minimum).
The secured/fenced parking area shall have a primary and a secondary ingress/egress point and shall be enclosed using anti-climb fencing. Access to the secured/fenced parking area shall be via motorized gates connected to the building’s physical access control system.
3.3. Outside Storage
CVO requires an exterior (minimum: 10 feet x 12 feet x 8 feet high) precast exterior concrete storage unit with a concrete foundation. This concrete storage unit will provide general storage, workspace, and storage for flammable and hazardous chemical materials. The unit must be able to accommodate a chemical container for ethylene glycol. A potable water hose bib and an eye station must be located within 1 foot of the storage unit’s foundation or attached directly to the storage unit. This unit should be securely fenced, have interior and exterior LED lighting, and minimally have a dedicated 20A duplex GFCI receptacle internal to the unit. Unit shall have standard double doors (6 feet x 6 feet-8 inch x 1-3/4 inch); minimum 18-gauge galvanized steel; insulated; tamper-proof hinges; deadbolt lock; adjustable mechanical door hold-open arm; door stop and holder; rain guard. Unit shall include two 12.5-gauge screened aluminum vents (minimum 7 inch x 18 inch). Unit requires 40 CFR Par
264.175 EPA compliant spill containment, corrosion resistant floor.
3.4. Design Requirements
The CVO has requirements for electrical, telecommunications, fire protection, lightning protection, mechanical and structural systems, security, and grounding. These requirements must be met; otherwise, mission-critical operations will be negatively affected. Therefore, CVO will pursue a design recommended to ensure these requirements are addressed and completed during the initial tenant build-out. The building shall be designed using resilient materials, either cast-in-place concrete, brick cladding, or equivalent material on all vertical surfaces. Roofing materials shall be resilient; standing seam metal roofing (or equivalent material). Regulatory requirements require rooms identified by CVO as Critical Security Rooms must be housed within the same collective area and have secured, common ingress and egress points to access the area housing these rooms. All common access points to this collective area must have an access control vestibule (i.e.., “sally port”) design with each door being secured by CVO’s physical access control system and video surveilled. The perimeter walls associated with this area as well as the individual walls associated with rooms located inside this area must all be true slab-to-slab construction.
Landscaping shall be neatly trimmed to minimize the opportunity for concealment of individuals, packages/containers, and parking areas. If Landscaping exists, the Lessor shall provide trees, hedges, berms, or any combination of these to create buffer zones to separate public areas and other functions. Landscaping shall not obstruct the views of security guards and Video Surveillance System (VSS) cameras or interfere with lighting or Intrusion Detection System (IDS) equipment. Landscaping on the property shall also not interfere with the utility of equipment or structures or obstruct communication tower or antenna line of sight requirements.
4. PROGRAM REQUIREMENTS
4.1. Accessibility
The CVO operates 24 hours a day 7 days a week 365 days a year; therefore, the CVO requires uninterrupted access to the facility and all spaces subject to its lease.
Furthermore, the facility design shall comply with the Architectural Barriers Act Accessibility Standard (ABAAS). To the extent the standard referenced in the preceding sentence conflicts with local accessibility requirements, the more stringent shall apply.
4.2. HVAC Requirements
4.2.1. General HVAC Requirement
The building supports a 24/7/365 operation; therefore, it requires 24/7/365 cooling and heating in certain rooms as identified in Appendix A.
4.2.2. Control Center Room / Data Center Room
The Data Center, UPS room, and the Industrial Control Systems Division’s (ICSD) Telecom room and Operations room require a sufficiently sized (estimate 3.5 to 4 tons per unit), independent, and redundant computer room air conditioning system (CRAC) separate from the base building HVAC system. The CRAC system is necessary to maintain temperature, air distribution, and humidity. Condensation floor drains for these systems shall be connected to the buildings plumbing drainage system. CRAC units shall be located outside of, but adjacent to, the rooms they serve to facilitate maintenance activities (i.e., outside of the secured spaces identified in Appendix A).
The Data Center, UPS room, and Telecom room shall be maintained between 65-degrees to 72- degrees Fahrenheit at all hours. The ICSD Operations Room shall be maintained between 70- degrees and 74-degrees Fahrenheit at all hours, and the relative humidity in each of these rooms shall be between the ranges of 45% to 55%. CRAC units are required to be connected to facility power and the emergency generator.
The Control Center room shall be maintained between 70-degrees to 78-degrees Fahrenheit at all hours and shall be adjustable by personnel.
Any HVAC unit(s) servicing the Control Center are required to be connected to facility power and the emergency generator.
The Data Center, Operations room, UPS room, and Telecom room house critical government information technology equipment, so the room must meet the Federal Information Security Modernization Act (FISMA) requirements. This act limits the plumbing, fire suppression, and HVAC piping lines only to those that are essential to the operation of the room.
4.2.3. Building Control System
HVAC systems shall be designed in accordance with the latest edition of the International Mechanical Code and the recommendations of American Society of Heating, Refrigerating and Air- Conditioning Engineers (ASHRAE).
4.2.4. Duct Design
Duct systems shall be metal ductwork designed and constructed in accordance with the recommendations of Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) except that insulated flexible duct connections to diffusers shall be allowed up to a maximum length of 7.5 feet provided that the flex duct is supported in accordance with SMACNA recommendations. All ductworks shall be located and coordinated in the interior space of the structure (above the finished floor ceiling height), and not exposed to outside elements.
4.3. Electrical Requirements
4.3.1. Service Voltage
Service voltage shall be sufficiently sized 277/480, three-phase, four wire. Provide K-13 rated or better transformers to serve 120/208 volt, three-phase, four wire distribution panel boards to serve general receptacles, lighting, and special equipment loads requiring 120-volt or 208-volt service.
4.3.2. Lightning Protection Systems
Provide a complete Underwriters Laboratories Master Label lightning protection system designed for compliance with National Fire Protection Association (NFPA)780.
4.3.3. Electrical Distribution System
Provide fully rated electrical distribution systems with each overcurrent device capable of independently safely interrupting the available fault current at its point in the system.
Incoming service and distribution systems shall be designed to provide capacity for all government-furnished equipment, all lighting loads, all HVAC equipment loads, and a minimum of 7 watts per square foot of general convenience receptacle load. The service and distribution systems shall include a minimum of 25% spare capacity. Provide a surge protector at the incoming main overcurrent device.
4.3.4. Arc Flash Warnings
Provide arc-flash warnings acceptable to the Government at all pieces of relevant electrical equipment.
4.3.5. UPS System
Uninterruptable power supply (UPS) system must have an external “make before break” bypass switch (K-13 or higher transformer at the external bypass and matched to UPS). CVO requires a sufficiently sized 3 phase, 480 to 208 V, using insulated-gate bipolar transistors (IGBT) UPS, with battery monitoring. CVO will approve UPS and battery monitoring system vendors. The dedicated grounds are isolated at each load, back to the panel (source).
Provide a modular UPS sized to carry the Critical Power Loads as defined by CVO, including certain loads from the Control Center, ICSD Telecom, ICSD Operations, and Data Center rooms. In the Data Center room, assume a minimum of 7.2kW of UPS load per requested server rack and an equivalent amount of facility power to each server rack.
The UPS shall include an external maintenance bypass and shall have battery storage capacity as required to carry the identified load for a time of not less than four hours. Lithium Iron Phosphate batteries, or better, is required. Furnish and install a remote annunciator panel, using a non- routable protocol (i.e., not Ethernet), in the Control Center on the display wall indicating UPS status.
Provide a Critical Power Panel with metering for loads served via the UPS.
Racks supporting batteries shall be properly grounded and bonded. Racks 6 feet or taller require seismic bracing.
4.3.6. Generator
The power distribution system shall be connected to an emergency generator. The estimated load is 200 kVA but should be confirmed. The electrical engineer of record shall verify the load.
The generator shall be sufficiently sized to handle the required load and be a minimum 200 kW, provide power at 277/480 volts, three-phase, four wire, and shall contain an output circuit breaker. The A/E will confirm the generator size and properties. Also, provide an open transition automatic transfer switch appropriately sized for the loads. The generator shall be fueled by natural gas, diesel, or propane. CVO will select the type of generator fuel based on site criteria.
Provide on-site fuel storage capacity of 2,500 gallons or equivalent. The ground space square feet associated with the generator and fuel storage are additional to areas noted in Appendix A.
The generator shall be located at ground level with a secured enclosure or shelter. All exterior located generators will be fully enclosed with sound attenuation or an exhaust muffler. (The engine shall have a block heater, circulating pump, battery charger, batteries, and a critical-grade muffler).
Fuel storage must be secured within the generator enclosure or securely fenced, using anti-climb fencing, immediately adjacent to the generator enclosure. Sufficient turnaround space for re- fueling trucks is required.
4.3.7. Grounding System
Each piece of electrical switchboard, panel board, or motor control center shall have a ground bus, and all circuits must include a grounding conductor. Where isolated equipment grounds are required, the isolated ground shall not be bonded to the electrical ground system at any point other than the point of service ground and in compliance with NFPA 780.
4.3.8. Lighting Systems
The lighting systems shall comply with the recommendations and the requirements of the International Energy Code. At a minimum, battery pack emergency ballasts shall be provided in the Control Center, Telecom, ICSD Operations, UPS room, and the Data Center rooms.
Battery packs will comply with IAW NFPA 101.0.
Provide dimmable lighting for conference rooms and other spaces defined by the CVO.
Incorporate LED assemblies in main use areas.
4.3.9. Data Cabling and Electrical Power for Specialty Items
All offices, cubicles, workspaces in the hoteling space, and the reception area will receive wall outlets that contain two cat6a minimum blue cables. All locations will be coordinated with the furniture designer. The Control Center will have a minimum of four blue and four yellow cat6a minimum color-coded cables at each workstation area. See additional detail in the CVO room specifications. All low-voltage and electrical outlet locations to be coordinated and approved by CVO. All data cables will be tied together by color code and placed in cables trays traversing the hallways/corridors or above raised ceilings that lead back into the Data Center room, Telecom room, or other CVO-approved location.
4.4. Communications
The building shall possess at least two separate access points into the building to facilitate the installation of multiple, redundant telecommunication circuits to the Telecom room.
4.5. Telecommunications Tower and Communications Tower Data Structure
Provide ground space (20 feet by 35 feet) for a 60 feet to 70 feet height communications tower and an adjacent concrete or similar Communication Tower Data Structure (120 square feet). This area shall be enclosed with anti-climb security fencing. The Communications Tower and its associated Communications Tower Data Structure shall be designed and installed following Office of the Chief Information Officer Directive 2010-008, Department of the Interior Radio communications Site Standards, and the latest version of Motorola R56 Standards.
Communications Tower and Communications Tower Data Structure (if applicable) must conform to FAA AC 70/7460-M Obstruction Marking and Lighting. The tower will require a concrete foundation with anchor bolts per the manufacturer. Also needed are a grounding system, two (2) each 3-inch data conduits with pull strings from the Communications Tower Date Structure tied back to the Data Center Room (coordinate with CVO for location), and one (1) 3-inch data conduit with pull string from the Communications Tower Data Structure to the Telecom room. Electrical power conduits tied back to the Electric Room (coordinate with CVO for location), 4- 120 electrical weatherproof outlets, exterior light, and a Lightning protection system.
The Communications Tower Data Structure is intended to house sensitive electronic and information technology equipment and shall have non-UPS and UPS power feeds, have LED interior lighting, have exterior LED lighting sufficient to illuminate the surrounding area, and have a dedicated, sufficiently sized HVAC system (estimate 2.5 tons, but should be confirmed).
The Communications Tower Data Structure shall be insulated and have standard double doors (6 feet x 6 feet-8 inch x 1-3/4 inch); 18-gauge galvanized steel; insulated; tamper-proof hinges;
deadbolt lock; adjustable mechanical door hold-open arm; door stop and holder; rain guard.
The Communications Tower shall be three or four-leg and self-supporting with an ultraviolet light and corrosion resistant (e.g., galvanized steel, stainless steel, glass fiber, reinforced nylon, etc.) cable-tray to the Communications Tower Data Structure.
The Government may also house ground mount antennas within this secured space or on the building’s roof during the life of the lease.
Sufficient space must be available near the tower for access and use by a boom truck to facilitate tower maintenance and antenna installation activities throughout the lease duration.
4.6. Fire Protection Criteria
Provide a complete fire alarm system designed in accordance with NFPA 72. Provide wet-pipe sprinkler systems designed in accordance with NFPA 13, NFPA 20, NFPA 24 and local Fire Codes or other suitable system approved by CVO. The entire fire protection system shall be monitored by a fire alarm system, including remote notification capability via telephone and data systems. Water mist or other accepted systems should be considered for the Data Center, UPS room, ICSD Telecom room, and ICSD Operations room areas. To the extent the standard referenced in the preceding sentences conflict with the GSA RLP and Lease, the more stringent shall apply.
4.7. Security and Safety Requirements
Lessor to provide a complete video surveillance system (CCTV) that provides unobstructed coverage of designated building ingress and egress points, the secured parking area, the generator and fuel storage enclosure, and the communication tower area, including the communications tower data room. CVO may install a separate video surveillance capability in select rooms or areas and will provide security feeds to a monitor array located in CVO-determined rooms.
CVO shall install a Homeland Security Presidential Directive-12 PIN-capable compliant
(Government Approved) physical access control system at all ingress and egress points to its spaces and other designated internal CVO spaces. Designated doors should have power, conduit, and back-boxes installed to facilitate installation of request-to-exist devices, sensors, and card readers.
Security and safety requirements shall minimally meet the Interagency Security Committee Standards (Federal Security Level II) and reference the following documents:
● Federal Security Assessment
● Physical Security Criteria for Federal Facilities
Guest call announcement 2-way communication (Push-to-Talk), including a minimum 10 inch video with sound, to communicate with the Administrative Assistant and in the Control Center Room (3- points).
4.8. Exterior Glass - Blast and Anti-Glare Film
The exterior glass windows and doors shall be coated with an anti-glare & blast proofing film. This includes glass within any entry doors and vestibules.
4.9. Lactation Room
The tenant buildout of space must incorporate the design requirement for a Lactation room.
This federal requirement is described in the passage of “The Patient Protection and Affordable Health Care Act” in 2010.
| 1. SUMMARY |
| 2. SITE LOCATION REQUIREMENTS |
| 3. BUILDING REQUIREMENTS |
| 3.1. Office Requirements |
| 3.2. Parking Requirements |
| 3.3. Outside Storage |
| 3.4. Design Requirements |
| 4. PROGRAM REQUIREMENTS |
| 4.1. Accessibility |
| 4.2. HVAC Requirements |
| 4.2.1. General HVAC Requirement |
| 4.2.2. Control Center Room / Data Center Room |
| 4.2.3. Building Control System |
| 4.2.4. Duct Design |
| 4.3. Electrical Requirements |
| 4.3.1. Service Voltage |
| 4.3.2. Lightning Protection Systems |
| 4.3.3. Electrical Distribution System |
| 4.3.4. Arc Flash Warnings |
| 4.3.5. UPS System |
| 4.3.6. Generator |
| 4.3.7. Grounding System |
| 4.3.8. Lighting Systems |
| 4.3.9. Data Cabling and Electrical Power for Specialty Items |
| 4.4. Communications |
| 4.5. Telecommunications Tower and Communications Tower Data Structure |
| 4.6. Fire Protection Criteria |
| 4.7. Security and Safety Requirements |
| 4.8. Exterior Glass - Blast and Anti-Glare Film |
| 4.9. Lactation Room |
File details come from the government source that posted it. Updated .