This federal opportunity notice describes a solicitation for the design-build renovation of Mental Health Ward 1L, 1H and 1K at the Minneapolis VA Medical Center. The contractor will furnish all labor, materials, tools and equipment required to complete general construction, demolition, structural, civil, mechanical, plumbing, electrical and low voltage work. Eligible offers are limited to Service-Disabled Veteran-Owned Small Businesses. The solicitation will be issued as a Request for Proposal on February 4, 2020 in accordance with FAR Parts 15, 19, and 36. The period of performance is approximately 790 calendar days from notice to proceed. The magnitude of construction is estimated between $10-20 million.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Log
| - | |||||||||
| Open | |||||||||
| PROJECT NAME : Renovate MH Ward 1L, 1H and 1K | Latest Response Date: | ||||||||
| RFI # | Division | Division | Description | Issue Date | Responsible Party | Response | Response Date | Status | |
| 1 | 04 | Soliciation & MH601 | The price/cost schedule on page 6 of the solicitation calls only line item 0001 (BASE BID) which includes the renovation of the entire work within the documents. Note 1 of the AHU schedule provided on MH601 asks to provide AHU installation price as a deductive alternate # 1. If later is correct, please provide an updated price/cost schedule. | ||||||
| 2 | 04 | Soliciation | Is this project tax-exempt? If yes, Please issue the Tax Exemption number for bidding purposes. If not, what is the percentage of tax? | ||||||
| Project is not tax exempt. | |||||||||
| 3 | 04 | General | Please show a pathway (for hauling off the demo debris) to the loading dock on the drawing from the construction area K, H, and L. | ||||||
| 4 | 04 | General | Are we allowed to use the courtyard entrance to bring in and takeout the construction materials to the construction area? | ||||||
| 5 | 04 | General | Please provide a site logistic plan showing the connection for temp water connection, temp power connection, location for site trailer, contractor parking, etc..for bidding purposes. | ||||||
| 6 | GI001 | Phasing notes & legends of GI001 reference and discusses the hazardous material abatement and direct us to obtain the ACM & lead-base paint report from the COR. Please provide the ACM & lead base paint report and provide ACM and lead abatement drawing, quantities of abatement, and specifications. | |||||||
| 7 | General | GI001 | Phase 2 & 3 reference and discusses that the VA medical center will continue to use the exterior therapy area plan south of zone 1L during phase 2 & 3. Are you referring to the courtyard as an exterior therapy area? Please identify the exterior therapy area on the drawing. | ||||||
| 8 | 04 | SG008 | Detail 5/SG008 titled sidewalk support at the new exterior door has shown on drawing SG008. We would not see any reference to this detail on any structural drawings. Please provide a reference on the drawing this detail applicable to. | ||||||
| 9 | 04 | SG008 | Detail 7 & 8/SG008 titled vertical skyfold partition support and vertical partition support respectively have shown on drawing SG008. We would not see any reference to this detail on any structural drawings. Are you referring to the accordian partition door and the won-door fire door as a skyfold partition? Please provide a reference to this detail on the respective structural drawing. | ||||||
| 10 | 04 | SG008 | Please provide a reference of an interstitial floor in the detail 7 & 8/SG008 to understand that C8x11.5 stays above or below the interstitial floor. | ||||||
| 11 | 04 | Architectural drawings | Are we to provide a temporary built-out for weather protection in construction area while removing the existing windows and installation of new windows/curtain walls? | ||||||
| 12 | AD100 | Some of the areas outside the construction in area K (C1-68A, C1-72A), area H (1J-101a, 1H-100, 1H-101, 1H-102, 1H-121) & area L (door by corridor C1-57 between column line 9 & 10) have only access from the construction area. Please confirm that these rooms will be closed and not in use for VA during the construction period as discussed during the site walk. | |||||||
| 13 | AD101 to AD104-P3 & A101 to A104-P3 | Keynote 24 of all demo drawings indicate "COMPLETE DEMOLITION OF AREA AS SHOWN. ONLY METAL STUDS WILL REMAIN ON EXTERIOR WALLS U.N.O. REMOVE INTERIOR WALLS IN THEIR ENTIRETY U.N.O.". But, Keynote 7 of all architectural drawings show "FURR/INSULATE EXTERIOR WALL W/ 35/8” LT. GA. METAL STUDS, R11 BATT INSULATION AND 5/8” GWB FROM FLOOR TO B.O. STRUCTURE ABOVE.". Please confirm that all the exterior walls are going to be entirely new with new studs as per architectural drawings. | |||||||
| 14 | 04 | AD101-P1 | KN-8 of AD101-P1 is annotated in rooms 1L-114, 1L-115, & 1-116 asking to remove the plumbing fixtures. There are no images of any plumbing fixtures on this demo plan neither on the plumbing demo drawing PD101-P1. Please provide an updated demo & plumbing demo drawing for phase 1 to understand the plumbing fixture demo scope. | ||||||
| 15 | 04 | AD101-P1 & A101-P1 | Phase 1 general notes provided on A101-P1 requires a demolition of FE cabinets, wall protection, patient beds, bathroom accessories, patient room flooring, interior glazing etc..However the demo drawing AD101-P1 do not show any of the above items to be removed. Please provide an updated AD101-P1 drawing. | ||||||
| 16 | 04 | A101-P1 | Phase 1 General note 2 shows "REMOVE MARKERBOARD, WALL HUNG HAND CLEANER DISPENSERS, HAND SANITIZERS, IDEA BOARD BULLETIN BOARDFROM WALLS AND OTHER ITEMS TO BE COORDINATED WITH OWNER FOR STORAGE AND/OR DISPOSAL." Please provide a list of items that need to be removed and stored for bidding purposes, so that all bidders can bid the same scope. | ||||||
| 17 | 04 | A101-P1 | Phase 1 General note 3 depicts "REMOVE ALL EXISTING UNLOCKED FIRE EXTINGUISHER CABINETS AND REPLACE WITH NEW FLUSH MOUNTED LOCKABLE FIRE EXTINGUISHER CABINETS." Please quantify the number of Fire Extinguisher cabinets that need to be removed and replaced for bidding purposes, so that all bidders can bid the same scope. | ||||||
| 18 | 04 | A101-P1 | Phase 1 General note 4 depicts "REPLACE ALL WALL PROTECTION ITEMS WITH ANTILIGATURE GRADE WALL PROTECTION AND CORNER GUARDS." Please provide the drawing showing temporary phase 1 wall protection and product information for bidding purposes, so that all bidders can bid the same scope. | ||||||
| 19 | A101-P1 | Phase 1 General note 5 depicts "CONTRACTOR SHALL RELOCATE PATIENT BEDS FROM EXISTING 1K AND SECURE INTO THE FLOOR OF PATIENT BEDROOMS ON THIS PLAN AT THE END OF PHASE 1 DURING THE ONE WEEK OWNER MOVE PERIOD." Please provide the existing patient bed's product manufacturer and detail to understand the disassemble and reinstallation of the same for bidding purposes, so that all bidders can bid the same scope. | |||||||
| 20 | A101-P1 | Phase 1 General note 6 depicts "ALL EXISTING PATIENT BATHROOMS IN PHASE 1 MUST HAVE ALL BATHROOM ACCESSORIES REPLACED WITH ANTILIGATURE GRADE ACCESSORIES." Please provide an anti-ligature bathroom accessories schedule and drawing for phase 1, so that all bidders can bid the same scope. | |||||||
| 21 | 04 | A101-P1 | Phase 1 General note 7 depicts "ALL PATIENT ROOM FLOORING IN PHASE 1 WILL BE REPLACED WITH RSV1. " Please provide a finish plan and finish schedule (incl product information) for area L phase 1, so that all bidders can bid the same scope. Do all patient rooms require a new wall base? if yes, please provide wall base product information. | ||||||
| 22 | 04 | A101-P1 | Phase 1 General note 8 depicts "REPLACE ALL INTERIOR GLAZING WITH AN APPROVED LAMINATE HIGH IMPACT GLAZING. " Please provide a list of doors and windows opening sizes and glazing sizes on phase 1 drawing which need to be replaced with the glazing. so that all bidders can bid the same scope. Also, provide a glazing type and thickness. | ||||||
| 23 | 04 | A101-P1 | Do we need to paint the entire area L phase 1? or just paint locally where patching has been done and new walls constructed. | ||||||
| 24 | A101-P1 | Keynote 6 of A101-P1 calls for providing of ADA compliant shower stall. Please provide a Basis of design of the shower stall. | |||||||
| 25 | 04 | A101-P1 to A104-P3 | Keynote 8 of all architectural drawings depict "EXISTING WALL MOUNTED STEAM CONVECTOR TO BE REMOVED (SEE MECH.). FINISH TO MATCH EXISTING CONDITION. SEE DETAILS ON SHEET AE500." This keynote refers to drawing AE500 for details that do not exist in drawing piles. Please clarify. | ||||||
| 26 | 04 | A104-P3 | A104-P3 shows accordian wall partition between OCC therapy 1L-114 and Group therapy 1L-116. The spec section1.1 of 10 22 26.13 indicates electric or manually operated accordian partition. Please clarify whether it requires an electric or manually operated accordian partition. Also, provide a basis of design for the accordian partition. | ||||||
| 27 | A104-P3 & 2/A406 | what is the window type on the southern wall of REC therapy room 1L-112? | |||||||
| 28 | A302 | Detail 3/A302 calls for L-angle MTL framing @ 16"O.C. to support pre-cast concrete bench. The detail is drawn as all light gauge framing, the detail references as L-angle MTL framing. This appears to be in conflict with what is drawn. Please provide cross section to show intent. | |||||||
| 29 | 04 | A302 | The top 2 feet portion of elevation 1/A302 (titled as feature wall) shows for decorative artificial plants and asking us to coordinate with VA. Who is responsible to furnish this item. If it is by the GC, please provide product information, basis of design, and specifications. | ||||||
| 30 | 04 | A302 | The middle 5' 6" portion of elevation 1/A302 (titled as feature wall) depicts for the Soundcor product asking us to coordinate with VA. It is also mentioned that the feature wall by the VA. The spec section 09 84 33 with a BOD as a soundcore product is provided in the spec book. Please clarify who is responsible to furnish this item the VA or GC. | ||||||
| 31 | 04 | A302 | The bottom 1' 6" portion of elevation 1/A302 (titled as feature wall) calls for stone (TBD by VA) and the color schedule of AF-001 also indicates stone TBD by VA. Please provide product information/BOD of the stone. | ||||||
| 32 | A405 | The equipment schedule for toilet 1L-101 and VAPD storage 1L-103 are missing on A405. Please provide the missing schedule. | |||||||
| 33 | A408 | The equipment schedule for toilet 1L-113A is missing on A405. Please provide the missing schedule. | |||||||
| 34 | 04 | A701 | The door type E and H are shown on A701. These door types are not used in any opening in the door schedule. Please clarify. | ||||||
| 35 | 04 | A701 & A702 | We do not see the aluminum frame type 2 and 6 in the door schedule nor in the floor plan. Please clarify where these frame types are used. | ||||||
| 36 | 04 | A502, A702 & AI101 | Detail 4/A502, 5/A702 & 14/AI101 show the hollow metal frame in the window section. But the window type W5 in nurse station 1H-110 & W13 in the High Acuity RN station 1L-120 are called out as an aluminum window per window type on A702. Please clarify which one is correct. | ||||||
| 37 | A701 & A702 | The door types provided on A701 call for LG-1 glazing and aluminum frame types and aluminum windows call for LG-1, IL-1A, and IL-1B glazing. Please provide specifics for each type of glazings. | |||||||
| 38 | AF-001 | Product types RSV-1 shows in (Corridor C1-61 & 1L-131 serving room) & RSV-2 (1K-127 HSKP room), rigid sheet vinyl inpro products have shown in the color schedule on AF-001 & AF002. Please specify the height of this products at this locations. | |||||||
| 39 | AF-001 | Sign schedules are provided on AF-001 for all 3 phases of signage requirement. Will a floor plan showing the location for each signage be available? | |||||||
| 40 | AF-001 | Product type SS-3 (Solid surface for walls by dining/nurses station front) has shown in the color schedule on AF-001. We do not see any wall in the dining room shows with SS-3 except the nurse's station front. Please clarify. | |||||||
| 41 | AF-001 | Product type MTL-1 stainless steel column wrap called out in theater room 1K-118. Please provide SS column wrap specification or basis of design. | |||||||
| 42 | AF-001 | HR-2 handrail shows in the color schedule on AF-001. We do not see this handrail type HR-2 on any of the interior elevations or plans. Please clarify. | |||||||
| 43 | AF-001 | Finish plan note 2 of AF-001 indicates "ALL PATIENT TOILET COVES SHALL BE EITHER PORCELAIN TILE MATCHING THE FLOOR TILE OR SOLID SURFACE MATCHING THE WALL SOLID SURFACE MATERIAL." Please specify whether to use porcelain tile or SS product for bidding purposes. | |||||||
| 44 | General | AF101-P1 | A variety of furniture have shown in the plan AF101-P1. Please confirm all those types of furniture are for reference only except for the patient beds. If those furniture are by the GC, please provide a furniture schedule and basis of design for bidding purposes. | ||||||
| 45 | 04 | AF101-P1 | A bunch of lockers has shown in the locker rooms 1L-124 & 1L-125 in area L phase 1. Who is responsible to provide those lockers? If it is by GC, please provide the size and quantities of lockers. | ||||||
| 46 | 04 | AF102, AF103 & AF104 | A variety of furniture have shown in the plan AF102, AF103 & AF104. Please confirm all those types of furniture are for reference except for the patient beds. If those furniture are by the GC, please provide a furniture schedule and basis of design for bidding purposes. | ||||||
| 47 | AI101 | Crash rail detail 12 CR1 is provided in AI101. We do not see this crash rail type CR-1 on any of the interior elevations or plans. Please clarify. | |||||||
| 48 | 04 | AI101 | Detail 11 of AI101 shows corner guard types CG-1 to CG-7. The floor plans AF102. AF103 and AF104 only call for CG-1. Please advise. | ||||||
| 49 | 04 | QH100 | The equipment schedule on QH100 indicates CT050, which is stainless steel countertop that needs to be provided and installed by the contractor. This stainless steel countertop does not show in any of the enlarged architectural plans or the equipment schedule of the enlarged architectural plans. Please clarify. | ||||||
| 50 | 04 | PP-501 & MH-501 | Detail 12/PP-501 & detail 2/MH-501 shows the interstitial deck repair detail. Which is not to scale detail. Please provide thickness, gypsum concrete specification, and as-built of the interstitial deck. | ||||||
| 51 | 04 | Plumbing | Please provide the existing slab on grade thickness that needs to be demoed for plumbing. | ||||||
| 52 | 04 | MH102-P2 & MH-301 | Keynote MH04 of MH102-P2 & MH301 ask for providing temporary heating and cooling to any spaces that are not within the limits of the construction while the new unit is being installed. Please provide the mechanical drawing showing the entire area outside the construction limit serving by 70 AHU 08 and temporary heating and cooling requirements. | ||||||
| 53 | MH104-P3 | MH12 of MH104-P3 calls for providing temporary cooling to areas that are to remain occupied during construction. Please provide the intent of the temporary cooling as there is only some modification to branch ductwork in area L. Also, provide the requirement of temporary cooling. | |||||||
| 54 | 04 | MH102-P2, MH104-P3 & MH-601 | MH102-P2 & MH104-P3 have shown some linear slot diffusers. There is no detail for linear slot diffusers in the mechanical schedule. Please provide linear slot diffusers schedule. | ||||||
| 55 | 04 | 04 01 00 | Specification 04 01 00 maintenance of masonry is provided within the specification booklet. We do not see any scope for the maintenance of masonry. Please identify the scope associated with 04 01 00. | ||||||
| 56 | 04 | 04 20 00 | Specification 04 20 00 unit masonry is provided within the specification booklet. We do not see any scope with CMU masonry for an exterior wall or interior partition. Please identify the scope. | ||||||
| 57 | 07 81 00 | Specification section 07 81 00 applied fireproofing is provided within the specification booklet. We do not see any fireproofing scope in this project. Please clarify. | |||||||
| 58 | 04 | 08 34 53 | Spec section 1.1 of 08 34 53 titled as Security doors and frames depicts "The extent of abuse-resistant security door assemblies required for the Project is indicated on Contract Drawings, and in Door/Frame/Hardware schedules, indicated as “Heavy Duty-Security Door” including construction, profiles, swing, sizes, hardware, accessories, devices, and locations." None of the doors and frames on the door schedule or the drawing identified as Heavy Duty-Security doors. Please clarify. | ||||||
| 59 | 04 | 08 41 13 | Spec section 2.3A & 2.9A of 08 41 13 indicates "Basis of Design, exterior systems: Specific material, finish, and color to match adjacent new aluminum curtain wall/door systems to be installed per separate, concurrent VA aluminum window/door system replacement project. Contractor to field verify, approved by Contracting Officers Representative.". Please confirm that this specification 08 41 13 applies to the curtain wall W1 and exterior aluminum frame type 1 of this project. Also, provide product detail & manufacturer, finish, color, and installer information of the VA aluminum window/door replacement project for the exterior system. | ||||||
| 60 | 04 | 08 41 13 | Spec section 2.3B & 2.9B of 08 41 13 indicates "Basis of Design, interior systems: Aluminum finish and color to match adjacent CRL Aluminum door/window and frame systems.". Please confirm that this specification 08 41 13 applies to the interior aluminum openings (frame type 3 & 4) and interior windows (W4 to W21) of this project. Also, provide finish, color, and installer information of the adjacent CRL Aluminum door/window and frame system. | ||||||
| 61 | 08 51 13 | Spec section 08 51 13 is provided as an aluminum window with integral blinds within the insulated glass units. Which window types does this spec section apply to? | |||||||
| 62 | 08 56 53 | Spec section 08 56 53 titled as blast resistant windows depicts "Prefabricated fixed aluminum, blast-resistant exterior window units |
to be included at all exterior window replacement and storefront locations indicated in this project.". Please confrm that this spec section 08 56 53 applies to window type W2 and W3.
| 63 | 10 11 13 | Specification 10 11 13 Chalkboard & Markerboards is provided within the specification booklet. We do not see any scope for the same. Please identify the scope associated with 10 11 13. | |
| 64 | The updated specifications provided in amendment 2 still have some of the Div 28 specification illegible, i.e. 28 05 00, 28 05 28.33, etc... Please reissue a legible copy of the specifications. | ||
| 65 | Are we allowed to work all the demo work, coring and drilling work within the construction zone during the regular normal working hours? | ||
| 66 | Please provide a contact information of the preferred/maintenance temperature control contractor. | ||
| 67 | Please provide a contact information of the preferred/maintenance fire alarm contractor. | ||
| 68 | 04 | Please provide a contact information of the preferred/maintenance nurse call system contractor. | |
| 69 | Please provide a contact information of the preferred/maintenance access control system contractor. | ||
| 70 | Please provide a contact information of the preferred/maintenance CCTV/SSTV system contractor. | ||
| 71 | Please provide a contact information of the preferred/maintenance public address system contractor. | ||
| 72 | 01 32 16.15 | 1.9A Contractor and their CPM consultant (if applicable) shall attend all monthly schedule update meetings. Could the meeting be conducted via Zoom or Webex call in lieu of in person meetings? | |
| 73 | 01 33 23 | 1.3C. The VA will provide the initial submittal register in electronic format. Thereafter, the Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the VA. Could the Government please provide the submittal register? | |
| 74 | 01 33 23 | 1.4D. All submittals are required to be approved prior to the start of the |
specified work activity. Has the submittal review and approval process, as well as the procurement been included in the aproximately 6 month period of performance for the Phase I portion or the entire period of performance?
| 75 | 01 33 23 | 1.10D D. VA review period is 15 working days for submittals. This is 21 Calendar days for VA review. Has the submittal process as well as the fabrication and procurements been included in the aproximately 6 months Phase I duration as well as the overall period of performance? |
| 76 | 01 33 24 | 1.6A A. Submittal Exchange, no substitute. Please verify if Viewpoint Team (meets all of the requirements) may be used in lieu of Submittal Exchange. |
| 77 | 01 35 26 | E. The SSHO or an equally-qualified Designated Representative/alternate will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor. |
CPs will maintain presence during their construction activities in accordance with above mentioned clause. A listing of the designated SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA as listed in Section 1.8 below. Can the SSHO also perform other roles onsite such as the superintendent?
| 78 | 02 41 00 | No Asbestos containing or lead containing materials have been identified in the specifications or the drawings. Is there hazardous materials within the work areas? |
| 79 | 08 51 13 | 3.5 C. Test Specimen: |
1. Include window assembly and construction. Affix test chamber to interior side of test specimen and the conduct testing using positive static air pressure (Test method A).
2. Test specimens to be selected by the Contracting Officer's Representative after windows have been installed according to the drawings and specification. Please identify the quantity and locations of these tests for bidding purposes.
| 80 | 09 30 13 | 3.19A. Test floors in accordance with ASTM C627 to show compliance with codes 1 through 10. This is destructive testing of the floor. Is this testing requirement to remain? | ||
| 81 | GI001 | Copies of the most current asbestos report and lead-base paint report are to be obtained from the COR. Please provide these reports for our review. | ||
| 82 | GI001 | Is there asbestos within the work areas? | ||
| In Area C, are there corner guards going on all corners? And are they all 8’? | ||||
| Has a design been chosen for WC11? We can get a budgetary number but not a firm number until a design is chosen. | - | |||
| What is the finish of the hallways in Area c? AF-001 shows the exterior walls of the hallway but not the inside hallway walls. | ||||
| Please provide HVAC insulation spec, spec section 230711 | ||||
| Please confirm CR-1, as detailed on 12/AI101, is not needed. CR-1 is not specified and no locations were identified. | refers to question 47 | |||
| Confirm CG-2, CG-3, CG-4, CG-5, CG-6, and CG-7 as detailed on 11/AI101 are not needed. No locations were identified. | ||||
| Confirm HR-2 as specified on Sheet AF-001 is not needed. No locations were identified. | refers to question 42 | |||
| Please provide installation height for RSV-1 & RSV-2. The installation height was not specified. | Same as question 38. | |||
| Drawing EP110 has “Wattstopper” as the basis of design for lighting controls; Lutron and Accuity are more commonly used in the facility and also meet the design with equal components, Spec section 26 09 23 does not specify a manufacturer. Are Accuity and Lutron acceptable? | ||||
| General Note #18 states that “circuits over 100’ require #10 conductors” (assuming that this is homerun portion of the circuit), the spec states all homeruns need to be #10. Should be assume that all homeruns are #10 (or larger if noted) regardless of length? (1H would still have to be #8 AWG for the homeruns as detailed on note #6 on EP103-P2) | ||||
| Spec section 27 12 00 paragraph 2.9. A.1 sates Riser rated cable for Cat6A but later in the sentence it says “listing for plenum and riser” we assume that “plenum” should be deleted since the space is applicable to riser rated cable? | ||||
| What is extent of CMU walls in project? Such as Room 1K-130 typical per area noticed to be CMU. | ||||
| What is extent of Gypsum Ceilings as opposed to ACT? Not all rooms were accessible. | ||||
| Will you please confirm all the areas that are employee spaces vs. private patient spaces? If the area is a private patient space do I need to meet behavioral health standards with anti-ligature (recessed) pulls and other hardware? | ||||
| I will price this project in the finishes as listed on the Color Schedule. Please note that the cost would be less if the end user were to choose standard finishes (instead of a special laminate). | ||||
| I’ve also gotten some feedback from our Engineering Department regarding the Nurse Station 1H-110. Along the guest side of this area the detail calls for a very large rounded front of the counter to be made of solid surface material. We can provide a typical 1 ½” thick solid surface top but it would not round over 20” tall on the front. Will it be acceptable for us to show our standard counter? Or, must the quote be compiled with this rounded front? | ||||
| The specifications include Section 10 11 13 Chalkboards and Markerboards. We have not been able to find in the drawings information relative to location(s), size(s) and quantities of the products. Please clarify where to find the information or provide if missing. | All marker boards and chalk boards are VV (VA procured and VA installed) This specification is not relevant to the project for the contractor. | |||
| The structural drawing 1338 - SB100 makes reference to the Detail 4 on Drawing 1338 -SG008. One of the notes in the detail 4 indicates “see arch. for additional information”. We could not find any additional information in the architectural drawings. Please provide this missing information of the work scope | ||||
| Spec section 23 07 11 HVAC Insulation appears to be missing from the spec. Could you please provide this section? | ||||
| Mechanical MH104-P3 notes a new range hood on the north side of room 1L-114. The mechanical plans note to make transition as necessary and make connection. Please confirm who provides the hood. If it’s by the construction team, please provide details on the hood – make, model, material construction, etc. | ||||
| Was this area tested for any Hazardous materials? Is there a report available? | ||||
| Please confirm only the column furrouts on exterior wall locations will get treated with the 3’11” Stone as shown on A503 Detail 11? Any interior locations? | ||||
| GI001, Phase 2 – Paragraph D, mentions about the un-scalable and to make those temp partitions to match current exterior walls, what is the height of those walls to match? Same material and finishes? | ||||
| Basis of design for the Auto-operator? | ||||
| Spec 10 16 01 – Solid Surface shower inserts mention both shampoo caddies and shower walls in patient rooms but elevations on A402.A is listing tile in the shower area, only Room 1L-136 on Page A101.P1 is calling for an ADA Shower stall. Please confirm if that Specification is only for the shower on the A101.P1? | ||||
| There were a couple of pages that seems to be misprint. A103-P2 – Elevator Lobby C1314, AF103 – 1H110A / B. | ||||
| RFI 14 on last amd says that AF101.P1 has the quantity of beds to be removed & relocated by Contractor. Im just not seeing the quantity. Is it all the beds in that page, 23 total? | ||||
| When the GC is securing those beds in the final locations, are we to mechanically anchor them? | ||||
| CR070 – tall cabinet Shown on A404 detail 8, A406 Detail 3.… is that VV or CC? | ||||
| Detail 3 on Page A405 showing 1H110B doesn’t seem to match with or may be mislabeled on AF103. Please confirm. | ||||
| Expansion Joints are not clear where they are needed… can you pinpoint where we can expect to replace them. | ||||
| The Patient beds on Spec 11 72 13, are those new, CC? or are those the ones to be relocated and secured as mentioned on page AF101.P1? | ||||
| Please confirm what to price out for the artificial plants on the feature wall? | ||||
| Can you clarify if there is to be an alternate in our bid? On page MH-601, Note 1 it calls out a deduct alternate. We could not locate anything in the specifications and the Price/Cost Schedule only has a line item for base bid. | CLIN 0001, Item I (Base Bid) contains all of the work for the project. All price and cost should be included in this line item. No bid alternate will be included for this procurement. | |||
| We are just looking for some clarification on hardware group HW-12C. Specifically the note that indicates C1-61 and C1-64 are to be on a remote release and a relay for interlock. Do those items fall under Division 28? | These doors are to have the ability to be unlocked by nurses at the nurse station for entrance to the sallyport one set of doors at a time. Guest would push an intercom button which will allow nurses at the desk to verify purpose of visit and then open the door | |||
| Per Tech Services at Tarkett the spec’d LVT-1 is part of the Event Collection which is made in China. The Contour Collection is made is the USA. Please advise | Change LVT-1 to Mannington, Harbour Pine (Arrow 7990), Style: Wood, Collection: Amtico Signature, Size: 7.25 x 48 | |||
| Please advise where Alum 2 on drawing sheet 1338-A702 Detail 1 is used. | This frame type not used | |||
| Drawing Sheet 1338-A103-P2 is missing wall information on the top left side of the sheet. Please provide a better quality drawing sheet | Walls within the gray area are not in scope. See finish plans and MEP for scope of work to be included. | |||
| Please provide details and specification of the drilled piers called out in amendment 6. | Spec 13 31 23 indicates all structural calculations to be completed by engineer specializing in TFS. Drilled pier backfil by structural engineer. | |||
| What is the basis of design for tensile fabric canopy? | See specification 13 31 23 | |||
| Please provide specifics of the existing landscaping and modifications to it. | See ammendment 6 details | |||
| Is that circular sidewalk in light grey shown on the sketch a new sidewalk or existing? | Areas of new work circled in red, area in yellow needs temporary sidewalk installed at Phase 1 and removed after Phase 2. All other areas existing | |||
| Provide us as-built of existing utilities in the exercising yard. | ||||
| Please provide multiple photos of the existing exercising yard to understand the existing conditions showing existing landscaping, existing catch basin, irrigation system, the existing surface at the locations of pole required for canopy, etc... |
Photos image1.jpeg image2.jpeg image3.jpeg image4.png image5.jpeg image6.jpeg image7.jpeg