Renovate Mental Health Inpatient Ward Project Addendum 1.docx
DOCX document 504 KB Posted
- Solicitation number
- 36E77620R0050
About this file
This document contains an addendum and related federal contract opportunity. The addendum provides revisions to architectural, civil, mechanical, electrical, low voltage, and specification elements of the Renovate Mental Health Inpatient Ward Project at the Minneapolis VAMC. Revisions include adding drawings and scope of work, phasing revisions, retrofitting doors, revising wall ratings and door hardware, and adding anti-ligature covers to wireless access points.
The related federal contract opportunity is a solicitation for the Design-Bid-Build renovation of Mental Health Wards 1L, 1H and 1K at the Minneapolis VAMC. The solicitation will be issued as a Request for Proposal to SDVOSB concerns only and awarded as a single, firm-fixed price contract. The period of performance is approximately 790 calendar days with a magnitude of construction between $10-20 million. The solicitation is scheduled for issue on February 4, 2020.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
List of Addendum Items for Project 618-17-127 Renovate Mental Health Inpatient Ward
Civil Revision Items
1. Add VA drawings and scope of work to 1K exercise yard to contract documents.
Phasing Revision
1. Delete installation of door C1-57F and associated temp wall during phase 1 and 2, install during phase 3. Omit Card Reader shown on LV sheets.
2. Install construction barrier as noted below during phase 2 work. Complete the remainder of the finishes update in corridor C1-76 and C1-65 in multiple short phases to ensure access to area L through these corridors during phase 2. Limited complete corridor shutdown during off hours(8PM to 5AM) are acceptable to replace corridor flooring and ceilings and demolish cross corridor walls, etc.
3. Retrofit phase 1 sally port door with auto operator. Door should match inner sally port door in function and capability.
Architectural Revision Items:
Sheet G101 Revise wall rating at MSA room 1H-110B:
Sheet A701
1. Door 1K-118 to have frame type 6.
2. Door C1-61D Hardware Group to change to HW-12C
3. Door 1L-108 Hardware Group to change to 12H.1. Add 45 Minute Rating.
4. Door 1H-110E Hardware Group to change to HW-1Y. Add 45 Minute Rating.
5. Door C1-64 add 45 Minute Rating
6. Door 1L-106 add 45 Minute Rating
7. Door 1L-140 add 45 Minute Rating
8. Door C1-57C add 45 Minute Rating
9. Door 1K-120 add 45 Minute Rating
10. Door C1-67 add 45 Minute Rating Sheet A702
1. Change glass type for windows W4, W7 and W21 to rated glass. More info to come in future addendum.
Sheet AF002
1. Add note in rooms C1-313 and 314 that existing paint and tile needs to be matched at wall infills.
Low Voltage Revision Items General Note
1. Add general note that all existing and new wireless access points of all types, need to be outfitted with Anti-ligature covers in all areas.
Sheet LV101
1. Add note- Phase 3 nurse call, camera and staff assist systems to be temporarily installed during phase 1 for use during phase 2. Systems to be salvaged for reinstallation during phase 3. Confirm layout of each temp system with COR.
Sheet LV 102
1. Add CR Symbol on Corridor side of MD Office Door 1H-111 Sheet LV 103
1. Add WB symbol at rooms 1K-104, 1K-105 and 1K-106
2. Delete CR symbol at room 1K-119
3. Add interior and exterior CR symbol at door 1K-118 Sheet LV 104
1. Add interior CR symbol at doors 1L-110 and 1L-112
2. Add CR symbol on corridor C1-57 side of doors C1-60B and C1-59B
3. Add CR symbol on C1-60 side of door C1-60A
4. Add CR symbol on C1-59 side of C1-59A. Add DA symbol for door C1-59A.
5. Add note for remote release button RI at High Acuity Nurse Station for door C1-59A.
6. Add CR Symbol for door C1-57C on corridor C1-57 side.
7. Add DH Symbol in room 1L-140 Mechanical Items
1. Add general note H requiring all Duct mains to remain will be cleaned.
2. Room 1H-110B is to be fed from AHU 70.AHU.07.
Electrical
1. Copy note 16 from sheet EP106-P3 on power for Pneumatic Tube Station and add to sheet EP104-P2 Work Room 1H-110A
2. “Greyed” outlets at the new nurses station desk on sheet EP102-P1 are new and to be provided and installed with new desk.
3. Note that new VFD and Motor are to be install/connected for return air fan, reuse existing circuits. Missing note missing from sheet EP103-P2
4. Room 1H-110B on sheet FA100 is to be included with area L not area K.
Specifications
87100
Hardware Group HW-12C
1. Delete the following as noted:
Add the following:
HW-12C
| Each Pair Integrated Double Egress Doors to Have: |
| RATED |
| 1 Steel Frame |
| - |
1 Integrated Pair Doors w/Elec Exit Exit Devices Q2331 x TYPE 8 (E04) ELECTRIC EXIT DEVICES (F01)
| 2 Continuous Hinges |
| A51031B |
| Electric Power Transfer |
| EPT 10 |
| 1 Overlapping Astragal with SelfAdhesive Seal |
| R5Y634 x R0E154 x THRUBOLTS |
| 1 Set SelfAdhesive Seals |
| R0E154 |
2 Key Switch
Power, wiring, conduit, and fire alarm connection by Division 26.
Power transfer shared by electric panic and reactivation sensor wiring (reactivation sensors provided by Section 08 71 13).
Auto door operator and controls by Section 08 71 13, AUTOMATIC DOOR OPERATORS.
Key switch to allow 1 door to open at a time with key.
Hardware Group HW-12H.1
1. Provide hold open closers for doors C1-59A and C1-60A.
2. No Card Readers required for door 1L-108
088000
Fire Rated glazing is required for doors in rated walls and windows. Add rated glass type for windows W4, W7 and W21 and for glass in all rated doors. More info to come in future addendum.
149200
Pneumatic Tube Stations are to be removed and reinstalled. New stations are not needed as the existing stations were recently upgraded.