A10 - 892CM3036 - Miramar NC - Bidders Questions.xlsx

XLSX spreadsheet 468 KB Posted

Attached to
Z1QA--892-036 - Miramar National Cemetery Expansion
Solicitation number
36C78620B0015
Issued by

About this file

This document contains questions and responses related to bid documents for a federal contract opportunity to expand columbarium and cremains facilities at the Miramar National Cemetery. The opportunity involves construction of additional columbarium niches, an in-ground cremains section, committal shelter, and related site work. Key details include questions regarding plan sheets and details not included in the bid set, specifications for construction materials and methods, utility locations, staging and access requirements, and confirmation of risk level 2 for stormwater permitting. The response provides clarifications, references revised plans, and notes requirements to coordinate construction activities with cemetery operations.

View the file

Other files

File Type Posted
Attachment 01 - Storm Drain Responses.pdf PDF
Attachment 02 - Water Responses.pdf PDF
S06 - A0004 - 36C78620B0015.docx DOCX document
Attachment 02 - NPDES Permit_NOI- WDID 937C356920.pdf PDF
Attachment 01 - 1999 const permit 99-08-DWQ.pdf PDF
S06 - A0003 - 36C78620B0015.docx DOCX document
ATTACHMENT 05 - Cost Estimate Worksheet - Miramar.xlsx XLSX spreadsheet
A04 - 892CM3036 - Bid Documents Plans - V-001.pdf PDF
A06 - CASQA Detail - SE-10.pdf PDF
S06 - A0002 - 36C78620B0015.docx DOCX document
A02 - 892CM3036 - Bid Documents Plans - A-101 - A-301.pdf PDF
A01 - 892CM2022 - Miramar Phase 1 Record Drawings - E-104.pdf PDF
A03 - 892CM3036 - Bid Documents Plans - C-201.pdf PDF
A11 - Digital Repeater - Equipment Specs.pdf PDF
A08 - CASQA Detail - WM-8.pdf PDF
A12 - Digital Repeater Picture 1.jpeg JPEG file
A07 - CASQA Detail - TC-1 and TC-3.pdf PDF
A05 - CASQA Detail - SE-1.pdf PDF
A13 - Digital Repeater Picture 2.jpeg JPEG file
A09 - 892CM3036 - BD - Geotech Report.pdf PDF
P09 - Scope of Work - FINAL.pdf PDF
S02 - 892CM3036 - Binder 9 of 9 Miramar.pdf PDF
S02 - 892CM3036 - Binder 6 of 9 Miramar.pdf PDF
S02 - 892CM3036 - Binder 5 of 9 Miramar.pdf PDF
S02 - 892CM3036 - Binder 1 of 9 Miramar.pdf PDF
S02 - 892CM3036 - Binder 7 of 9 Miramar.pdf PDF
S02 - 36C786-20-B-0015 - Solicitation.pdf PDF
S02 - 892CM3036 - Binder 2 of 9 Miramar.pdf PDF
S02 - 892CM3036 - Binder 4 of 9 Miramar.pdf PDF
S02 - Specifications.pdf PDF
S02 - 892CM3036 - Binder 8 of 9 Miramar.pdf PDF
P07 - WD - CA20200001 - 07.24.2020.pdf PDF
S02 - 892CM3036 - Binder 3 of 9 Miramar.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Project Title:Columbarium & Cremains Expansion -- Miramar N/CAwaiting response
Project Number:892CM3036Needs Clarification
Submission:RFI(s) Received for Bid Documents
Item No.Sheet No.RFIReviewerACCEPTREJECTFIRMA/E RESPONSE/COMMENT
1V-001Sheet V-001 "Overall Survey, Existing Conditions, Geotechnical and Demolition Plan" is listed on sheet index but not included in plan set. Please provide.EWLSheet V-001 was included in the planset (see page 7). An excerpt from the planset has been included as a attachment.
2A-102Sheet A-102 showns electrical requirements for the Committal Shelter. There are no electrical plans showing components or where power will be coming from or where to connect. Please clarify.EWLRefer to the revised architectural drawings provided in the supporting documentation.
3A-101There are cut section detail callouts that reference sheets that are not in the plan set. For example, on sheet A-101/B6 there are callouts for cut sections "B8/300" or "B2/200". There is no architectural sheets labeled with 200 or 300. Please clarify.EWLRefer to the revised architectural drawings provided in the supporting documentation.
4LK-401Legened calls for column number 1/LK501, row number 1/504. There are no details showing columns and rows. Also, columbaria section number detail 2/LK504 is a parking sign. Please clarify.RHAAThe correct detail numbers are as folows: Columbair column number - 3/L-501, Columbaria row number - 3/L-501, Columbaria section letter - 4/L-501
5C-104Calls for aggregate base access road. What is the thickness of the aggregate base course?TERMinimum thickness is 14-inches for Traffic Index of 5.0 to 5.5. Minimum thickness is 10-inches for Traffic Index of 4.5
6C-107SWPPP Notes and Legend, note 91 calls to see sheets C-508, C-509, and C-510. These sheets are not included in the set. Please clarify?EWLReference to the sheets are incorrect, please refer to SWPPP. Individual details referred to on C-107 are included as an attachment.
701 00 02 - 23Calls for new full size pickup to be used for duration of the project and to be leased for two years. Are we to lease it for two years or the duration of the project? Please clarify.VATo be determined at the discretion of the Contracting Officer / COR
8Bid Inv - A3 #1Call for GC to secure all permits including environmental permits required to meet compliance. Are all the construction permits to be paid by the Department of Veterans Affiars? If not, additional information will be required.VATo be determined at the discretion of the Contracting Officer / COR
9During the site visit, we encountered some large air vac cans in the area for alternate 4 and 5. These appurtenances are not shown on the plans or called out to be relocated. Please provide asbuilts for these facilities and where they will be relocated if the government chooses to exercise Alternate 4 and 5.EWLAir-vac cans are shown on the plans (see right). The utilities are owned by the City of San Diego. Please clarify on the plans where/which air vac cans this comment is referring to.
10How long can Alternate 3 Cortege Lane expansion be closed?EWLRefer to Specification 01 00 02, Section 1.6 Item O: Contractor shall submit a plan for phasing the cortege lane widening construction (Add Alt #3) which maintains ingress and egress for two lanes on the existing pavement, and shall coordinate with the cemetery director to schedule wrok to be done at times when committal services are not scheduled.
11During the construction phase for Alternate 3, will there be any restrictions for construction hours at this location?EWLRefer to response #10.
12Will construction fencing with green mesh be required during all phases of construction?EWLPer Specification 01 00 02 Section 1.6 Item I: The temporary fencing shall encompass the cosntruction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by RE/COR.
13During construction, will there be any restriction for construction hours at the two planting areas on the north side of the project?EWLPer Section A.3 of the Scope of Work, Item #2: Contractor shall coordinate with cemetery staff for all construction work to avoid or minimize any interruption of cemetery functions.
14Is there an alternate entrance that will be used during construction, or is the main entrance the only access?EWLContractors are not permitted to use Cemetery main entrance. Contractors are to use the alternate entrance located by the maintenance facility along the northern border of the cemetery as shown on the cover page G-001 of the planset.
15During construction, excess dirt will be stored to a stockpile location on the property. The haul route will pass in front of the assembly area. Is there a schedule or a particular time when construction will have to stop for ceremonies?EWLRefer to response #13.
16Can the government please provide the CAD files for the grading?VATo be released at the discretion of the Contracting Officer / COR
17Please provide Form S02 IFB Contractor Cost Estimation Worksheet to be included with bid package per Virtual Bid Instructions.VATo be released at the discretion of the Contracting Officer / COR
18E2/A-101 shows a "ceiling surface exposed to flourescent strip light", please provide a spec or product data sheet.EWLRefer to revised architectural drawings. The flourescent light fixture to be Lithonia #XP1 ceiling grid VA228UNVHI, or approved equal; surface mounted; (2) F28W T5; 56 Watts; 120 Volts; Provide drywall installation kit if required.
19Provide electrical drawings showing location/path of travel for conduit from power source to committal shelter for light fixture in committal shelter storage closet.EWLRefer to As-builts for Phase 1 for electrical stub at the Assembly Area. Refer to attached utility sheet for route to the new Committal Shelter.
20Provide specification for digital repeater system shown on F8/A-103EWLThe digital repeater system to match existing commital shelter at MNC. EWL has requested Cemetery for additional information on existing digital repeater systems currently installed at exising committal shelters.
21Provide electrical drawings for digital repeater systemsEWLRefer to the revised architectural drawings provided in the supporting documentation.
22Provide location of chain link fenceEWLPer Sepcification 01 00 02, Section 1.6 Subsection I, "(b)efore construction operations begin, the contractor shall provide a chain link construction fence, 2.1-meters (seven feet) minimum height, around the construction area indicated on drawings. Provide gate as required for access with necessary hardware, including hasps...". For silt fencing locations, refer to the erosion control plan and SWPPP included in the bid documents.
23Will the requirement to provide RE/COR a field office as stated in General Requirements 01 00 02 Paragraph 1.17 be enforced? The cemetery has an existing admin building and maintenance building on site that could possibly be used in lieu of the added cost to provide an office trailer for the RE/COR.VATo be determined at the discretion of the Contracting Officer / COR
24Will the requirement to provide RE/COR a new full sized pickup for 24 months per General Requirements 01 00 02 pp 1.17 be enforced?VATo be determined at the discretion of the Contracting Officer / COR
25If the contractor must provide a pickup truck, shouldn’t the period match the project duration? Project duration is 365 days and truck lease is supposed to be for 24 months.VATo be determined at the discretion of the Contracting Officer / COR
26Will the government provide the rosette mounting hardware for the niche covers?VATo be determined at the discretion of the Contracting Officer / COR
27Plans to not mention stockpile of BMP materials to be stored on site. Should contractor plan ~25% of what is shown?HZPlease clarify the RFI
28The "SWPPP Notes & Legend" provided mentions BMP details on sheets C-508, C-509 & C-510. Those sheets are not included in the combined bid set. Please provide.EWLRefer to response #6
29For the 2 locations that are to receive hydroseed or hydromulch there is no seed mix provided. Please provide.EWLRefer to Sheet LP601 - Planting Legend for the matrix of seed mixes (excerpt to the right)
30Based on the project's foorprint, it will be subject to SWPPP requirements. What is the project risk level?EWLPer page 1 of the provided SWPPP, the risk level of the MNC project was determined to be 2
31How many rain days should be assumed as part of base schedule before weather delays become an time extension?VATo be determined at the discretion of the Contracting Officer / COR
32Does Verduga wall installer need to be certified by Verduga?SRThe installer does not need to certified by Verduga. Additional design specification regarding the retaining wall has been included in the response for reference. Once the bid has been awarded, the GC is to coordinate with Soil Retention for additional information.