S06 - 0004 - Att1 - Technical Responses.xlsx
XLSX spreadsheet 125 KB Posted
- Attached to
- Construct EHRM Infrastructure Upgrades - Philadelphia, PA Federal contract opportunity
- Solicitation number
- 36C77626R0063_1
About this file
This file is a Technical Responses Q&A document for the EHRM Infrastructure Upgrades construction project at a VA medical facility in Philadelphia, covering Buildings 1, 2, 3, 21, and 30. The document addresses 100 technical questions and clarifications submitted by contractors regarding design specifications, materials, equipment, and construction requirements outlined in the 100% bid design documents.
Key technical requirements include: security systems featuring Avigilon H6a series dome cameras, Lenel LNL-M2220 and LNL-1320-S3B access control panels with LifeSafety power supplies, and an Avigilon NVR6-PRM-FIPS-FORM-D-160TB-NA video server; telecommunications infrastructure with Category 6A cabling, 48-strand OM4 and 24-strand OS-2 fiber optic backbone cables, and specific WAP reinstallation requirements; electrical systems including L21-20R receptacles for single-rack telecom room configurations with A/B power redundancy, split system HVAC units using A2L refrigerant, and fire protection systems classified as Ordinary Hazard 1 for telecom rooms per NFPA 13; architectural work including fire-retardant plywood (4'W x 8'H) mounted 16" above finished floor, vision lite doors (6" x 27"), and specific keyed note revisions and clarifications on finish schedules; and IT infrastructure modifications to the Building 2 Data Center involving new MDA cabinets in Row N connected to existing ED cabinets in Rows T, J, and G. Critical project constraints include construction restricted to 5pm-5am ET weekdays only due to occupied facility operations, with all materials removed and work areas cleaned by 5am daily, requiring five phasing zones and a 365-day period of performance under VA Infrastructure Standard for Telecommunications Spaces (ISTS) V4.0, June 1, 2023.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Responses 5-28-26
| Discipline | # | Question | Answer |
| Security | 1 | Access Control, Video and IDS equipment: Need Name brand of the Equipment installed on site today. | The current equipment is irrelevant, as we are using Pelco analog cameras that were discontinued decades ago. |
To align with the Avigilon camera project, EHRM rooms should be fitted with Avigilon H6a series dome cameras.
| Security | 2 | Existing security network rooms: If current security equipment lines/equipment are damaged/removed during construction, would that be considered part of this project to replace? | Yes, if contractor damages existing equipment during the installaition. |
| Security | 3 | Existing security network rooms: Can the exact Reader Model number from the manufacture be supplied to match the system on-site? | HID Signo Keypad Reader 40KHNKS-03-0004XR |
| Security | 4 | Existing security network rooms: Would the department owner of the security systems be available to go over system availability and connections prior to project starting? | Yes. We will also ensure that our onsite maintenance vendors Star Communication / Tri-M are on location to assist with technical details. |
| Security | 5 | Existing security network rooms: Can you supply information on existing panel capacity for Access, IDS and Video systems? | All panels, readers, power supplies are beyond service life and should be replaced with new equipment. Any new Access Controlled Door will require a combination of a Lenel LNL-M2220, LNL-1320-S3B and LifeSafety Power Supplies. |
| Security | 6 | Existing security network rooms: If any security system capacity has been reached or would be reached in some areas, would mitigation be considered part of this project? | Yes, if expasion or storage would be required to support the new equipment that would be included. |
| Security | 7 | Existing security network rooms: Based on initial design will changes in pathways be considered if it is found to be more advantageous to the security systems layout and possible be more cost effective? | Yes, but any deviations from the design would need to be approved by the design team |
| Multi-discipline | 8 | LAN Network: Can you provide a network map that indicates where that network is established? | TECH: The local network core is located in the Main Computer Room. |
| Multi-discipline | 9 | LAN Network: Is all security equipment on a stand-alone LAN network? If so, can you list the components of that network and available expansion. | TECH: Security equipment is not within the scope of EHRM. |
| Multi-discipline | 10 | LAN Network: Will any new switches need to be provided for this Bid? If so can you list the exact model and manufacture of switch needed. | TECH: Network switches will be provided by the Governement. |
| Security | 11 | Video server: Would a new video server be needed to support the additional cameras for this project? | An Avigilon NVR6-PRM-FIPS-FORM-D-160TB-NA will be required to handle the additional EHRM room video streams. |
| Security | 12 | Video server: Would any additional video License be needed for the new cameras? | Yes, all new cameras will require a license. |
| Security | 13 | Video server: If new licenses are needed, please provide what level of license they have existing (Enterprise, Standard) | An Avigilon NVR6-PRM-FIPS-FORM-D-160TB-NA will be required to handle the additional EHRM room video streams. |
| Security | 14 | Access Control Equipment: Will any additional license be needed to add new readers to the existing access control platform? | Lenel PRO-64RUP Door Licenses will be required for the total number of doors added. |
| Security | 15 | Access Control Equipment:If new licenses are needed, please provide what level of license they have existing (Enterprise, Standard) | Enterprise. Lenel Onguard PRO |
| Multi-discipline | 16 | Network switches: Will any new network switches be required for any of the new security products? | TECH: Network switches will be provided by the Governement. |
| Multi-discipline | 17 | Network switches: If they are required, can you supply the exact model number of the switches needed? | TECH: Refer to the answer to Line 16. |
| Multi-discipline | 18 | Network switches: If they are required, can you supply the exact Location of the new switch/switches? | TECH: Refer to the answer to Line 16. |
| Security | 19 | Motion detectors: Where do the motions in each room terminate into. No IDS panel is listed on the prints and no Keypads to disarm upon opening the room? | Provide an arm/disarm panel in protected spaces. All IDS must meet UL 639 Intrusion Detection Standard. Terminate all IDS sensors on the PACS data gathering panel. |
| Security | 20 | Panel equipment: What IDS panel is needed if not installed? | All IDS must meet UL 639 Intrusion Detection Standard. Terminate all IDS sensors on the PACS data gathering panel. |
| Architecture | 21 | Could you please confirm whether the project includes a glazing scope of work, specifically related to glass and aluminum doors and entranceways, windows, interior glass office partitions, glass guards/handrails, and specialty glass? | Glazing limited to vision lites on doors. |
| 22 | Confirm that concrete encased ductbank is only required under roadways. | TECH: There is no underground construction under roadways. | |
| VA Response | 23 | Please confirm that it is acceptable for the following TRs to have a dimension less than 10ft: A601, B3A151A, 1B198, 8B101, A107, A216, A318, A422, 1B134, 1C122, and 2B133. | Correct, an EHRM Project Standards Compliance Exception Memo had been submitted and approved acknowledging that these TRs do not meet the 10'x10' ISTS size requirements and are acceptable at dimensions indicated in the drawings. |
| Architecture | 24 | Demo note D4 plase clarify what it means to maintain fur down at below existing ceiling | Disregard KN D4. there is an existing fur-down in corridor to remain which should not be affected by new construction. Occurs on sheets 21-A200 and 21-A220. When existing doors or windows removed presume header will remain place. |
| Architecture | 25 | Demo note D 61- Existing sealed concrete floor. Is anything to be done with this floor or should it just be protected? | Contractor to prep to receive scheduled flooring at TR's per sheets 2-A210 and 2-A212. |
| Architecture | 26 | Demo note D 85- Is the existing raised flooring to be removed- should it be salvaged or be disposed of? | Dispose system. |
| Architecture | 27 | Confirm that plywood is required on all walls not 3 walls. | Provide on all walls per Technology drawings. |
| Technology | 28 | Confirm the patch panel requirements for POTS lines as the detail on TN-503 specifies 24 ports but the rack elevations only specify 48 ports. | Sheet TN-503 has two details that depict 24 and 48 POTS lines. The table on sheet TN-503 indicates the number of POTS lines, 24 or 48, for each TR. |
| Technology | 29 | Confirm the number of horizontal cables required per WAP and what a WAP symbol with a G label represents. | 1. Refer to sheet TN-500, detail 5. |
2. The WAP with the G label represents the Guest Network.
| Technology | 30 | Confirm what the © symbol represents on the telecom plans and the horizontal cabling requirements for said symbol. | © is a security camera. Security cameras shall be cabled with Category 6A cable. |
| Technology | 31 | Confirm that the number of copper patch cables that will be required within each telecom room will be the same as the number of horizontal cables terminating within each telecom room. | The Contractor shall provide two Category 6A patch cables for every installed Category 6A cable according to Specifications Section 271619. The patch cables shall be the same color as the modular jacks and be 7 ft. and 10 ft. in length. |
| Mechanical | 32 | Confirm that whether or not the split units must use A2L refigerant or if split units with other refrigerant is acceptable. | Yes, Contractor shall Bid this project using A2L Refrigerant for Split System Units for Telecommunication Rooms as shown in Design Documents. |
VA Leadership shall confirm that other Refrigerants shall Not be used for any of these new Split Systems.
| Electrical | 33 | Please confirm it is acceptable to reconnect existing feeders in the Building 2 Data Center to the new rows of racks and not provide redundant A-Side/B-Side power bus bars serving overhead rack receptacles. | Yes, See Keyed Note 4 on 2-E-201. UPS's are being replaced but we are reusing feeders under raised floor as possible. Need to check and verify feeder sizes; Some new feeders may be required, but for the most part existing feeders can be reused. We are not using New Overhead Bus-way for power distribution to racks. This is the one VA EHRM Project that is Only getting new data lines, but not all new Data Center Racks, etc. |
| Electrical | 34 | Please confirm if two (2) 120V electrical circuits are supposed to be provided above the door to TR AB3 in Building 21 per the symbols shown. Please confirm what the symbol represents if the sheet note already calls for the circuit to be fed by critical power. | No, the "E" Symbol is NOT a receptacle but represents Electrical Power Drop, one is for Magnetic Door Lock - See Keyed Note 2. The other power drop should have been for AC Power shown rough, not at specific location bc Condenser is outside and Evaporator is on the wall. See Equipment Data Schedule and Panelboard Schedules for Clarity. |
| Electrical | 35 | The Added Loads table for Building 30 on sheet 30-E-700 states that there is one (1) rack per telecom room, however, each TR is being provided with two (2) L21-30R receptacles, which is typical for a two (2) rack configuration. Please confirm if L21-30R receptacles should be provided or if two L21-20R receptacles should be provided. | The intent of the design is to support a single equipment rack per Telecom Room (TR). The two receptacles shown were intended to provide A/B power redundancy to the single rack, not to indicate a two-rack configuration. |
Accordingly, provide two (2) L21-20R receptacles per TR in lieu of L21-30R receptacles. The 20A configuration is sufficient for the anticipated single-rack telecom load while still maintaining the required redundant power arrangement.
The Added Loads table on Sheet 30-E-700 shall govern regarding the quantity of racks.
| Fire Protection | 36 | Confirm that telecom rooms are required to be Ordinary Hazard 1. | TELECOM ROOMS ARE TO BE CLASSIFIED AS OH1 BASED ON NFPA 13 4.3.3.1 AND A 4.3.3.1. |
| Fire Protection | 37 | Confirm the double-slash hatch pattern for occupancy classification indicates Ordinary Hazard 2. Pattern is not currently represented on the legend for Building 1. | THE HAZARD CLASSIFICATION LEGEND FOR BUILDING 1 DID NOT INCLUDE THE DOUBLE SLASH HATCHING. BUILDING 1 DOES INCLUDE SOME SPACES THAT REQUIRES OH2 SO THE LEGEND WILL BE MODIFIED TO REFLECT WHAT IS SHOWN ON THE DRAWINGS. |
| Fire Protection | 38 | Confirm storage spaces to be classified as OH2. | STORAGE SPACE CLASSIFICATION TO BE REVIEWD AND REVISED AS REQUIRED FOR THE CONFORMANCE SET SUBMITTAL. |
| Fire Protection | 39 | Confirm storage spaces are to be enclosed within a 1 hr fire rated barrier where applicable in accordance with VA Fire Protection Design Manual Section 3.1. | BASED ON THE VA FIRE PROTECTION DESIGN MANUAL SECTION 3.1.B, THE ONE HOUR FIRE BARRIER REQUIREMENT IS ONLY FOR STORAGE ROOMS CONTAINING MEDICAL RECORDS STORAGE OR MOVEABLE-AISLE/MOBILE SHELVING. I WAS INFORMED BY RAY MARTINEZ THAT THESE HAZARDS WILL NOT BE PRESENT IN THE STORAGE ROOMS WITHIN OUR SCOPE OF WORK. |
| Fire Protection | 40 | Confirm all spaces are marked with the correct hazard classification on the overall sheets. | A THOROUGH REVIEW OF THE HAZARD CLASSIFICATIONS WILL BE DONE. ANY MODIFICATIONS WILL BE INCLUDED IN THE CONFORMANCE SET. |
| VA Response | 41 | Confirm if clean agent system is present in existing data center. | Clean agent system is not included in the scope of this project. |
| Fire Protection | 42 | Confirm existing fire alarm devices in existing data center are in compliance with NFPA 101 and NFPA 72. | Modification to the fire alarm system in the data center is not included in the scope of this project. |
| VA Response | 43 | Confirm no modification to fire alarm system in existing data center is required. | Modification to the fire alarm system in the data center is not included in the scope of this project. |
| Architecture | 44 | Plan 1 on Drawing 1-A205 indicates an entry door to be removed at Plan South. What is the Door Number associated with this opening which appears to be utilized in Plan 2 on Drawing 1-A205 and possibly scheduled on Drawing A-410? | Door should be designated A001Eand is scheduled on Door Schedule sheet A-410. |
| Architecture | 45 | Plan 1 on Drawing 1-A205 indicates D85 – “Existing Raised Floor to be removed” however, The Room Finish Schedule on Drawing A-400 indicates E-RF – Existing Raised Floor finish for Rooms A001 and A001E. Keyed Note 1 and 48 on Plan 2 on Drawing 1-A205 indicate “Floor and Base as scheduled” and “No Floor, Base, or Ceiling this Room” respectively. Please clarify the Floor Finish requirements for Rooms A001 and A001E. | Entire existing raised floor assembly to be removed. Room A001 will have no new floor scheduled. Room A001E shall have a concrete sealed floor (C). |
| Architecture | 46 | If the Existing Raised Floor referenced above is to be removed, please advise on the following: a. How is the Floor Elevation transition to be handled? b. How is the horizontal “scar” at the perimeter of the rooms to be handled since the rooms are not scheduled to have the existing walls painted? c. What is the condition of the Floor substrate below the Existing Raised Floor? | A. Existing raised floor is on existing main floor level, no transition. B. Do not understand question but raised floor is only about 6" above main floor. C. Concrete floor is below the existing raised floor, the condition is unknown but assumed in poor condition due to prior leaks in that room. |
| Architecture | 47 | Please confirm that Elevation 1/A440 and Section 2/A440 noted on Plan Detail 3 on Drawing 1-A241 should be revised to 3/A-411 and 4/A-411 respectively. | 3/A-411 and 4/A4-11 correct. |
| Architecture | 48 | Keyed Note 7 (“FP Keyed Notes – Renovation”) is included within numerous Drawings, (example: Drawing 1-A206), and states “…reference Technology Drawings for more specific direction, extent, and mounting height.”. Although the Technology Drawings indicate 16” A.F.F., to what height does the plywood extend? We are having difficulty finding this specific direction. Please advise. | The fire retardant, 4'W x 8'H sheet of plywood is to be mounted vertically, with the bottom of the sheet to be 16" A.F.F. on all walls. |
| Architecture | 49 | Keyed Note 13 is indicated in Photo 25 on Drawing A-431 and seems to be pointing to Furniture. Please confirm that the VA is responsible for removing all Furniture. | VA to remove non-fixed furniture |
| Architecture | 50 | Please confirm that Keyed Note 35 indicated in Plan Detail 3 on Drawing 1-A250 should be Keyed Note 38. | KN #35 should be KN #38 at corridor. Disregard KN# 35 at new wall labeled 'P-3'. |
| Architecture | 51 | Plan Detail 4 on Drawing 1-A241 indicates Keyed Note R1 for the Ceiling Finish (No Ceiling) at Room TR A455A however, the Room Finish Schedule on Drawing A-400 indicates Ceiling Type AT-1. Please advise. | Ceiling should be E-S (exposed structure) not AT-1. |
| Architecture | 52 | What is the Wall Type for the new North wall of Room A502A? Please refer to Plan Detail 3 on Drawing 1-A250. | Partition type 'P-1' per General Note 11. |
| Architecture | 53 | Please confirm that Keyed Note 16 indicated at 2 Window locations in Plan Detail 3 on Drawing 1-A271 should be Keyed Note 35. | Correct, should be KN #35. |
| Architecture | 54 | Please confirm Floor-To-Floor Heights for Buildings 1, 2, 3, 21, and 30. | VA still reviewing. |
| Architecture | 55 | Plan Detail 3 on Drawing 2-A212 indicates work for Rooms B2A106A and B2A106B however said rooms are not identified on either the Room Finish Schedule on Drawing A-400 or the Door Schedule on Drawing A-410. Please advise. Note: Photos 78 and 79 are indicated on Drawing A-435. | These rooms were deleted per Addendum. Delete this sheet (not sure why it appears on this set). |
| Architecture | 56 | Room Finish Schedule Remark 11, “New Gypsum Board over existing stud framing where existing tile and substrate wainscot removed.”, is listed on Drawing A-401. Please advise as to where this condition occurs. | Disregard, Remark 11. will be revised to read "this keyed note not used.", as it is not applicable. |
| Architecture | 57 | Please confirm Keyed Note 31 shown on Plan Detail 3 on Drawing 2-A251. | Disregard KN #35, not applicable. |
| Architecture | 58 | Please confirm Keyed Note 27 shown on Plan Detail 3 on Drawing 2-A251 and indicate extent of work. | KN #27 correct, approximate length is 24'. |
| Architecture | 59 | Please indicate the extent of work associated with Keyed Note D27 shown on Plan Detail 1 on Drawing 2-A251. | 30' approximately. |
| Architecture | 60 | Please confirm Keyed Note 2 adjacent to Door Opening 7A137 shown on Plan Detail 3 on Drawing 2-A271. | Disregard KN #2, not applicable here as door/frame assembly is new. |
| Architecture | 61 | Please confirm Partition Type P-4A at window locations shown on Plan Detail 3 on Drawing 3-A210. | P-4A' is correct. Optional to infill with gypsum bd./studs as wall will be covered up by plywood. |
| Architecture | 62 | Please confirm Keyed Note D2 shown on Plan Detail 1 on Drawing 21-A220. | Disregard KN #D2, not applicable since door/frame assembly is to be replaced. |
| Architecture | 63 | Please confirm Keyed Note 2 adjacent to Door Opening BC113 shown on Plan Detail 3 on Drawing 30-A201. | Disregard KN #2, not applicable here as door/frame assembly is new. |
| Architecture | 64 | Please confirm Keyed Note D29 shown on Plan Detail 1 on Drawing 30-A201. | D29 should be D27. |
| Architecture | 65 | Please confirm Keyed Notes 53 and 58 shown on Plan Detail 1 on Drawing 30-A213. | KN #53 should be D53 (only 1 light fixture). Disregard KN #58. |
| Architecture | 66 | Keyed Notes appear to be missing on Plan Detail 3 on Drawing 30-A220. Please advise. | Add KN #1 at floor. Add KN #7 at N, E and W walls. Reference RFS, sheets A-400 and A-401. |
| Architecture | 67 | Please confirm Door Opening 2C156A as depicted on Plan Details 1 and 3, Drawing 30-A222 and Keyed Note D14. | Door openings depicted correctly, disregard KN #D14. |
| Technology | 68 | TECH: Disregard the KN-6 in street pointing to an existing underground pathway between two manholes. | |
| Multi-discipline | 69 | Please provide a clear Site / Civil Drawing which indicates pavement areas versus turf areas. Reference current Drawings C-100, AS100, and C-TN-300 which are not adequate in this regard. | The only turf areas that will be disturbed by underground construction are between Bldg. 3 and Parking Garage, Bldg. 28. Refer to sheet C-TN-300, Keyed Notes 7, 8, 9. |
| Architecture | 70 | Please provide the size for the Vision Panel for Door Type B indicated on Drawing A-411. | 6" x 27" lite at ABA compliant height. |
| Architecture | 71 | Please confirm Door Schedule Remark Number 1 indicated for Door Number TR A107 on Drawing A-410. Is this Remark applicable for this project? | Disregard Remark 1, not applicable and will be revised to read "this keyed note not used." Add Remark #3. |
| Architecture | 72 | Is Door Schedule Remark Number 3 applicable for Door Numbers TR 121 and TR A107 indicated on Drawing A-410? | Yes Remark #3 is correct, disregard Remark 2 (not applicable). |
| Architecture | 73 | Please confirm that Door Schedule Remark Number 7 indicated on Drawing A-411 is not applicable for this project? | Disregard Remark #7, not applicable and will be deleted. |
| Architecture | 74 | General Note 5 for the Door Schedule on Drawing A-411 indicates “All existing doors scheduled to remain shall be stripped, sanded, and stained or primed/painted to match adjacent existing doors.”. Please clarify this requirement and provide examples as to the scope and extent. | Limited to doorway(s) in immediate area. EXAMPLE: Sheet 1-A210 indicates new door on existing frame. This existing frame is to be striipped, preped and painted. For the most part this is typical in locations documented. |
| Architecture | 75 | FP Keyed Note 3 indicates “Provide Room Sign Per New Standard.” Please provide further information and/or Specification. | Drawings will be provided to depict signage standards. General design standards can be found on the VA TIL in design manual "VA Signage PG-18-10". |
| Architecture | 76 | We are having difficulty locating ICRA Plans, Details, Specifications, etc. Please advise. | Drawings will be provided to clarify at locations requiring such. Typically what is expected is the provision of a temporary plastic partition with a zipper door. In some cases a gypsum board partition may be required. Provide sticky mats at all areas where work occurs ven if partition not required. |
| VA Response | 77 | Documentation issued during the Sources Sought period for this project contained a “Construction Statement of Work” dated December 31, 2025 (5 pages). Section 3 and Section 5 of the referenced document indicate that the Working Hours for the project are 5:00pm to 5:00am on Monday through Friday. The current documentation issued for Solicitation 36C77626R0063_1 does not contain Working Hour requirements. Please advise. We do note that the SAM.gov link that does contain a Work Hour statement within the Project Description. | VA still reviewing. |
| VA Response | 78 | Please refer to Specification Section 01 00 00.1.13.A. Please advise / fill-in as to the “TBD” references. | The Contractor may use existing non-public use service elevators in Buildings 1 and 2. The contractor will need to plan and receive approval from the COR prior to elevator use. Blanket approval for elevator usage is not provided. |
| VA Response | 79 | Please confirm that the Contractor’s Site Safety and Health Officer (SSHO) must be on-site during all construction operations and shall have no duties other than that as the SSHO as defined. | Correct. SSHO must be present on-site during construction operations with duties only as the SSHO and a separate indivudual from the superintendent and/or QCM. |
| VA Response | 80 | Please confirm that the Contractor’s Superintendent cannot be designated as the Contractor’s Site Safety and Health Officer (SSHO) as indicated in Specification Section 01 35 35.1.7. | See 79 |
| VA Response | 81 | Please confirm that the Contractor’s Superintendent cannot be designated as the Contractor’s Quality Control Manager as indicated in Specification Section 01 35 35.1.7. | See 79 |
| VA Response | 82 | Is the Contractor’s “Quality Control Manager” identified in Specification Section 01 35 35.1.7 the same as the Contractor’s “CQC System Manager” identified in Specification Section 01 45 00.3.4? | The Quality Control Manager named in Spec is the same as the Contractor Quality Control System Manager identified in Spec 01 45 00 3.4. |
| VA Response | 83 | Please confirm that the Contractor’s Superintendent can be designated as the Contractor’s CQC System Manager as indicated in Specification Section 01 35 35.1.7, subject to the qualifications defined. | Per Spec 01 45 00 3.4B, the CQC system manager serves as project superintendent in addition to quality control. |
| VA Response | 84 | Please confirm that the Commissioning Agent (CxA) identified in Specification Section 01 91 00 will be appointed, retained, managed, and be paid for by the VA. | Correct, the Commissioning Agent is appointed and managed by the VA as a contract separate from the construction contract. |
| Technology | 85 | Drawing TN-003 Sub Phase C- 3.5, states the installation of a temporary umbilical cable and to coordinate the location of said cable. Item 3.5 provides a lot of detail about the umbilical cable but where is this cable running to and from? | The intent of the umbilical cord is to provide connectivity within the data center, from the service provider demarc, located in the data center, to the core switches as they are moved to new racks. |
| Technology | 86 | What is row X on drawing 2-TN-437.SB distribution obligation to the MDA cabinets. Should row X be depicted on 2-TN-434.SB? | The equipment in Row X is service provider demarc and core switches. The equipment in Row X will be moved, in phases to Row N. |
| Technology | 87 | Drawing 2-TN-437.SB Denotes the 12”cable cable tray between G13 and X13 as existing. The previous drawing 2-TN-436.SB does not show that cable tray. Is this tray existing or not? | The cable tray sections indicated between G13 and X13 and between A13 and F13 on sheet 2-TN-437.SB is are sections of cable tray that will be provided and installed by the Contractor. |
| Technology | 88 | Drawing 2-TN-434.SB does not depict HDA (Horizontal distribution are) and ED (Equipment Distribution) cabinets as defined in the spec. Is this drawing depiction correct? | Yes this drawing is correct. The MDA cabinets will be the only new cabinets to be provided and installed by the Contractor. There are no HDA cabinets and the ED cabinets are existing. |
| Technology | 89 | Drawing 2-TN-441.SB and drawing 2-TN-449.SB are these duplicate drawings? | There is not a sheet 2-TN-449.SB. |
| Technology | 90 | Are the line diagrams of drawing 2-TN-434.SB correct? Is the drawing depicting the distribution of all cabling from MDA-A and MDA-B to row T, J, & G cabinets? | Yes this drawing is correct. The MDA cabinets shall be connected to the ED cabinets in Rows T, J, and G. |
| Technology | 91 | Drawing 2-TN-437.SB keynotes call out the re-use of existing cabinets. Are the PDU’s ad depicted on drawing 2-TN-435.SB to be re-used or new PDU’s are to be furnished and installed? | The only new cabinets are the MDA's in Row N. The PDU's are existing, refer to the electrical drawings for additional details on the PDU's. |
| Technology | 92 | Are there additional UPS and Z-PDS requirements for each cabinet & rack, or populate the racks and cabinets as shown on drawing 2-TN-438.SB & 2-TN-439.SB? | There are no rack mounted UPS or Z-PDS in the Data Center. Refer to 2-TN-435.SB Bldg. 2 Data Center Power Plan. |
| Technology | 93 | Drawing 2-TN-434.SB row T depicts (8) cabinets for the row. Drawing 2-TN-437.SB depicts 9 cabinets in row T. Which is correct? | Both sheets are correct. Sheets 2-TN-438.SB and 2-TN439.SB are showing existing cabinets with the existing designations. Sheet 2-TN-434.SB shows the final configuration and the new grid coordinate system. |
| Technology | 94 | Drawing T-002, Responsibility Matrix states “Wireless Network - Guest/Patient/Other Network WLAN (WAPs)” are CF/CI (Contractor furnished/contractor installed). Is this an accurate statement? If so what are the WAP requirements, p/n, warranties, enclosures etc. for a fully functional system. | The WAP's for VA Internal and Guest Network are existing. There are no new WAP's. The Contractor will remove and reinstall the WAP's. |
| Technology | 95 | To meet EHRM requirements, all new cable is to be in conduit. WAO that are “free air/loose” down to a data location, what is the VA’s estimated quantity that is loose and not in conduit? Surface mount raceway will need to be included for loose in wall WAO’s. |
Niznik, Benjamin J. (VHACLE): Niznik, Benjamin J. (VHACLE):
| The intent is, to the extent possible, to reuse the existing outlet box and conduit pathway. Where the existing cable pathway is the wall cavity, then the Contractor will reuse that same pathway. The majority of the WAO's use the wall cavity as the cable pathway. | |||
| Technology | 96 | What are the copper patch cord requirements for the project? Example1- every 1 cat6a cable installed, install 2 patch cords (1 at the TR and 1 at the field), Example 2- Every 2 cable WAO, install (1 at the TR and 1 at the field). Please clarify. | The Contractor shall provide two Category 6A patch cables for every installed Category 6A cable according to Specifications Section 271619. The patch cables shall be the same color as the modular jacks and be 7 ft. and 10 ft. in length. |
| Technology | 97 | What are the fiber optic patch cord requirements? Example 1- Every 2 strand of fiber provide 2 duplex patch cords (1 at each end). Please clarify. | The Contractor shall provide two fiber optic patch cables for each strand of fiber; aqua OM-4 multi-mode for multi-mode strands and yellow OS-2 single mode for single mode strands. Patch cables shall be Duplex-LC to Duplex-LC with reversed polarity. |
| Technology | 98 | Vertical wire manager called out in PRFERRED PRODUCT SCHEDULE on T-002 is Vertical manager with door, 6.5"W x 10.25"D x7', white Legrand/Great Lakes MM20VMD706-W /, this is a 6” wire manager. 1-TN-401.B note 2, calls out a 10” wide wire manager. Which is it a 10” or 6”? | Single TR racks shall have 10" wide vertical managers on each side. Two racks or more shall have 10" wide vertical managers on each end with 10" wide vertical managers between racks. |
| Technology | 99 | On many of the TR design drawings the second rack is shaded out, for future. Is the contractor expected to supply the additional rack, wire manager, PDU’s, UPS to the VA? If the contractor is expected to supply the future materials to the VA, will it be expected to add a ZONE PDU so the correct 2 rack configuration meets the VA standard? | Grayed out racks, marked for future are for reference only. The Contractor shall install racks as shown, allowing space for the future rack. |
| Technology | 100 | In reference to the backbone drawing TN-600, is the ask of Keynotes 1 & 2 correct? Keynote 1 & 2 are asking for a 48 strand OM4 and a 24 strand OS1 as the standard campus backbone to each TR (primary & secondary). Is this the correct ask for the backbone cabling? | Yes, TN-600 is correct. The Contractor shall install fiber optic backbone cable in accordance with Specifications Section 271000, 271323, and as shown on TN-600 and the various TR layout sheets. |
Sheet2
| Discipline | Item # | Type | Division | Question | Column1 | Answer | |
| 1 | Rooftop Rigging | Div 05 / 23 | Setting the structural steel and CRAC units on the roof will require a heavy crane pick from the street level. Will the VA assist in expediting the necessary street closure/lane restriction permits with Baltimore City DOT, or is this entirely on the contractor? | Critical | |||
| 2 | Roof Warranty | Div 07 | Installing the new Division 05 rooftop steel requires penetrating the existing roof membrane. Who is the manufacturer of the existing roof, and who holds the active warranty so we can utilize certified installers for the flashing? | High | |||
| 3 | Phasing vs POP | Div 01 / SOW | The project requires 5 phasing zones, heavy 2nd-floor demolition, and long-lead rooftop CRAC units within a 365-day POP. Will the VA extend the POP to accommodate documented manufacturer delays for the HVAC and Electrical gear? | Critical | |||
| 4 | ICRA | ||||||
| Contradiction | 001A-P02a / SOW | Drawing 001A-P02a shows temporary poly access points, but the SOW requires ICRA levels from the bid enclosures. Will VA Infection Control permit poly access points, or are hard-wall anterooms strictly required? | High | ||||
| 5 | Firestopping Scope | Div 07 / SOW | The SOW mandates sealing "existing penetrations." Will the VA establish a fixed "Existing Firestop Allowance" (e.g., $50,000) to ensure all bidders evaluate this unquantifiable risk equally? | High | |||
| 6 | Fire Alarm Matrix | Spec 28 31 | Who is the proprietary incumbent Fire Alarm vendor for the Baltimore VAMC, so we may request a quote for the required programming and NFPA 72 matrix integration? | High | |||
| 0 |