675-106 Addendum 02.pdf
PDF 21 MB Posted
- Solicitation number
- 36C77626R0035
About this file
This file contains a comprehensive addendum (Addendum No. 02, dated April 17, 2026) to the construction contract documents for project 675-106, the Expand Radiology and Oncology project at Lake Nona Orlando VA Healthcare System. The addendum consists of 120 pages with 2 specification sections and 22 drawing sheets that supplement and amend the original drawings and specifications to address Requests for Information received during the bidding process and provide design clarifications.
Key changes outlined in the addendum include: revised responsibility for obtaining a Commissioning Agent (assigned to the VA), addition of Phase 0 for rough-in installation of utilities in the First Floor Interstitial Level, updated Phase 3 demolition plan incorporating ICRA and PCRA requirements with ante rooms at construction entrances, modifications to waiting room door hardware including a magnetic hold open for door 241A and an auto operator with hands-free wave-to-open actuator for door 241B, replacement of discontinued welded sheet vinyl flooring (WSV-1) with a new pattern and addition of WSV-2 for MRI scan rooms, removal of hydraulic bollards replaced with manual removable bollards, and electrical changes including life safety branch power for automatic door operators. The document includes extensive specifications for general commissioning requirements (Section 01 91 00), door hardware (Section 08 71 00) with detailed hardware sets for various door types, architectural details, fire alarm systems, plumbing and medical gas piping, electrical routing and schedules, and telecommunications infrastructure. The contract requires acknowledgment of the addendum on the Form of Proposal, and all changes become part of the Contract Documents upon receipt.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
524 Fernwood Drive, Altamonte Springs, Florida 32701 | rdcjpa.com | 800.362.1523
Addendum No. 02
Date: April 17, 2026
Project: 675-106
Expand Radiology and Oncology at Lake Nona
Orlando VA Healthcare System
13800 Veterans Way
Orlando, FL 32827
This Addendum supplements and amends the original Drawings and Specifications for the above referenced project. This Addendum shall be forwarded to all Prime Bidders and all appropriate building code authorities. This Addendum shall be taken into account in the preparation of bids and shall become a part of the Contract Documents.
Receipt of this Addendum must be acknowledged on the Form of Proposal.
Questions or comments should be directed to the Contracting Officer per the Solicitation.
This addendum consists of 120 pages, 2 Specification sections and 22 Drawing sheets.
General
The addendum consists of revised drawings and specifications to address RFI’s received during the bidding process along with revisions providing clarification.
1. Responsibility for Commissioning Agent
a. The VA shall be responsible for obtaining the Commissioning Agent for the project.
2. Updated Phasing Narrative
a. The addition of Phase 0 was added to allow work to commence in the First Floor
Interstitial Level for the rough-in installation of new utilities for Fire Protection, Plumbing, Mechanical, Electrical and Telecommunications prior to the start of construction for the new building expansion in Phase 1.
3. Updated Phase 3 Demolition Plan per ICRA & PCRA requirements
a. Ante rooms will be required to be put in place during Phae 3 for all construction entrances from the existing hospital areas into the demolition / construction area.
4. Updated Waiting Room Door Hardware for patients utilizing mobility devices
a. The entrance door (241A) from the corridor into the Waiting Room was revised to include a magnetic hold open to keep the door in the open position during normal business hours. The magnetic hold open will require connection to the fire alarm to allow release of door when alarm is activated.
b. The door leading from Zone 2 Passageway back into the Waiting Room (241B) has been revised to add an auto operator with a hands-free wave-to-open door actuator to open the door to allow patients to exit unassisted.
5. Updated Welded Sheet Vinyl Flooring
a. Previously specified WSV-1 has been discontinued by the manufacturer. A new pattern in the same series has been selected and revised in the Finish Legend.
b. WSV-2 noted to be installed in the MRI scan rooms has been added to the Finish
Legend.
6. Civil changes
a. Provided additional notes for clarification of site elements.
b. Hydraulic bollards have been removed and were replaced with manual removable bollards
7. Electrical changes
a. Clerical notes for electrical contractor and the conduit routing plan in the interstitial space.
b. Life safety branch power for automatic door operators.
Specifications
1. 01 91 00 General Commissioning
a. The responsibility for obtaining the Commissioning Agent was revised to the VA.
2. 08 71 00 Door Hardware
a. Hardware set 7.1 was added for door 241B & 8.0 revised for door 241A to reflect updated hardware required for Waiting Room doors.
Drawings
Note: Drawing revisions have been clouded in and tagged to reference to Addendum #2.
General
1. Sheet GI200 – Phasing Plans - Overall
a. Added Phase 0 for Interstitial level rough-in work and noted staff transition period between Phases 2 & 3.
2. Sheet GI205 – Phase 3 Plans
a. Added keynotes 1.27, 1.28 and 1.29 for clarification during construction.
Civil
3. Sheet CS-051 – Demolition Plan
a. Provided additional notes for clarification.
4. Sheet CS-101 – Site Plan
a. Added storage pad for removable bollards.
5. Sheet CS-151 – Grading & Drainage Plan
6. Sheet CS-171 – Utility Plan
7. Sheet CS-601 – Site Details
b. Added removable bollard details and storage rack.
Architectural
8. Sheet AD102 – Demolition Plan – Phase 3
a. Added keynote 2.27 to clarify requirement of Ante room construction entrance within the hospital area.
9. Sheet AD103 – Demolition Elevation & Sections
a. Expanded keynote 2.19 and added note to the elevation to clarify 2’-0” removal of existing precast panel as noted on demolition plans.
10. Sheet AE105-N – Note Plan – Phase 2
a. Added keynote 8.35 to locate touchless hand wave door actuator for door 241B.
11. Sheet AE601 – Door Schedule & Details
a. Revised door hardware for doors 241A and 241B.
12. Sheet AF601 – Finish Legend & Details
a. Revised WSV-1 and added WSV-2 to the Finish Legend.
Fire Alarm
13. Sheet FA001 – Fire Alarm Legends & Symbols
a. Updated symbols legend to include added devices.
14. Sheet FA101.2 – First Floor Plans – Fire Alarm – New Work Phase 2
a. Updated floor plan to include new hold open device.
b. Update floor plan to relocate fire alarm pull station.
Plumbing
15. Sheet PD114.1 – First Floor Plan – Plumbing Med Gas, Demolition – Phase 1
a. Updated sheet reference in coded notes.
Electrical
16. Sheet E-101 – Electrical Routing Plan
a. Added clerical note to describe expectations for conduit routing as it relates to the drawings and contractor means and methods.
17. Sheet EP101.2 – First Floor Plans – Elec. Equipment – New Work – Phase 2 – Area A
a. Updated floor plan to include life safety power for automatic door operators.
18. Sheet EP101.3 – First Floor Plans – Elec. Equipment – New Work – Phase 3 – Area A & B
a. Updated floor plan to show life safety power for automatic door operator.
19. Sheet E-802 – Electrical Schedules
a. Updated panel schedules to show automatic door operators on life safety branch power
20. Sheet E-803 – Electrical Schedules
21. Sheet E-804 – Electrical Schedules
Telecommunications
22. Sheet TN101.2 – First Floor Plans – Data/Access Control/SSTV – New Work Phase 2
a. Updated floor plan to include new coded note annotation.
b. Updated Coded Notes to include additional details for door auto opener.
End of Addendum No. 02
675-106 GENERAL COMMISSIONING REQUIREMENTS
Expand Radiology and Oncology at Lake Nona 04-01-22 VAMC Orlando, FL
01 91 00 - 1
SECTION 01 91 00
GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
1.1 COMMISSIONING DESCRIPTION
A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form the basis of the construction phase commissioning process and procedures. The Commissioning Agent shall add, modify, and refine the commissioning procedures, as approved by the Department of
Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed scheduling for all commissioning tasks.
B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the Division 7, Division 21, Division 22, Division 23, Division 26, Division 27, Division 28, and Division 31 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not intended to duplicate services. The Contractor shall coordinate the work required by individual specification sections with the commissioning services requirements specified herein.
C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services shall be provided and copies of documentation, as required by those specifications shall be submitted to the VA and the Commissioning Agent to be indexed for future reference.
D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 7, Division 8, Division 21, Division 22, Division
23, Division 26, Division 27, Division 28, and Division 31 series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.
E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA’s operational needs. The commissioning process shall encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy phases is intended to achieve the following specific objectives according to the contract documents:
1. Verify that the applicable equipment and systems are installed in accordance with the contact documents and according to the manufacturer's recommendations.
2. Verify and document proper integrated performance of equipment and systems.
3. Verify that Operations & Maintenance documentation is complete.
01 91 00 - 2
4. Verify that all components requiring servicing can be accessed, serviced and removed without disturbing nearby components including ducts, piping, cabling or wiring.
5. Verify that the VA’s operating personnel are adequately trained to enable them to operate, monitor, adjust, maintain, and repair building systems in an effective and energy-efficient manner.
6. Document the successful achievement of the commissioning objectives listed above.
F. The commissioning process does not take away from or reduce the responsibility of the
Contractor to provide a finished and fully functioning product.
1.2 CONTRACTUAL RELATIONSHIPS
A. For this construction project, the Department of Veterans Affairs contracts with a Contractor to provide construction services. The contracts are administered by the VA Contracting Officer and the COR as the designated representative of the Contracting Officer. On this project, the authority to modify the contract in any way is strictly limited to the authority of the Contracting
Officer.
B. In this project, only two contract parties are recognized and communications on contractual issues are strictly limited to VA COR and the Contractor. It is the practice of the VA to require that communications between other parties to the contracts (Subcontractors and Vendors) be conducted through the COR and Contractor. It is also the practice of the VA that communications between other parties of the project (Commissioning Agent and Architect/Engineer) be conducted through the COR.
C. Whole Building Commissioning is a process that relies upon frequent and direct communications, as well as collaboration between all parties to the construction process. By its nature, a high level of communication and cooperation between the Commissioning Agent and all other parties
(Architects, Engineers, Subcontractors, Vendors, third party testing agencies, etc.) is essential to the success of the Commissioning effort.
D. With these fundamental practices in mind, the commissioning process described herein has been developed to recognize that, in the execution of the Commissioning Process, the Commissioning
Agent must develop effective methods to communicate with every member of the construction team involved in delivering commissioned systems while simultaneously respecting the exclusive contract authority of the Contracting Officer and COR. Thus, the procedures outlined in this specification must be executed within the following limitations:
1. No communications (verbal or written) from the Commissioning Agent shall be deemed to constitute direction that modifies the terms of any contract between the Department of
Veterans Affairs and the Contractor.
2. Commissioning Issues identified by the Commissioning Agent will be delivered to the COR and copied to the designated Commissioning Representatives for the Contractor and
01 91 00 - 3 subcontractors on the Commissioning Team for information only in order to expedite the communication process. These issues must be understood as the professional opinion of the
Commissioning Agent and as suggestions for resolution.
3. In the event that any Commissioning Issues and suggested resolutions are deemed by the
COR to require either an official interpretation of the construction documents or require a modification of the contract documents, the Contracting Officer or COR will issue an official directive to this effect.
4. All parties to the Commissioning Process shall be individually responsible for alerting the
COR of any issues that they deem to constitute a potential contract change prior to acting on these issues.
5. Authority for resolution or modification of design and construction issues rests solely with the
Contracting Officer or COR, with appropriate technical guidance from the Architect/Engineer and/or Commissioning Agent.
1.3 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 32.16.15 PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)
C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
D. Section 01 81 13 SUSTAINABLE CONSTRUCTION REQUIREMENTS
E. Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.
F. Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS.
G. Section 26 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS.
H. Section 27 08 00 COMMISSIONING OF COMMUNICATIONS SYSTEMS.
I. Section 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.
J. Section 33 08 00 COMMISSIONING OF SITE UTILITIES.
1.4 SUMMARY
A. This Section includes general requirements that apply to implementation of commissioning without regard to systems, subsystems, and equipment being commissioned.
B. The commissioning activities have been developed to support the VA requirements to meet guidelines for Federal Leadership in Environmental, Energy, and Economic Performance.
1.5 ACRONYMS
List of Acronyms
Acronym Meaning
A/E Architect / Engineer Design Team
AHJ Authority Having Jurisdiction
ASHRAE Association Society for Heating Air Condition and Refrigeration Engineers
BOD Basis of Design
01 91 00 - 4
List of Acronyms
Acronym Meaning
BSC Building Systems Commissioning
CCTV Closed Circuit Television
CD Construction Documents
CMMS Computerized Maintenance Management System
CO Contracting Officer (VA)
COR Contracting Officer’s Representative (see also VA-RE)
COBie Construction Operations Building Information Exchange
CPC Construction Phase Commissioning
Cx Commissioning
CxA Commissioning Agent
CxM Commissioning Manager
CxR Commissioning Representative
DPC Design Phase Commissioning
FPT Functional Performance Test
GBI-GG Green Building Initiative - Green Globes
HVAC Heating, Ventilation, and Air Conditioning
LEED Leadership in Energy and Environmental Design
NC Department of Veterans Affairs National Cemetery
NCA Department of Veterans Affairs National Cemetery Administration
NEBB National Environmental Balancing Bureau
O&M Operations & Maintenance
OPR Owner’s Project Requirements
PFC Pre-Functional Checklist
PFT Pre-Functional Test
SD Schematic Design
SO Site Observation
TAB Test Adjust and Balance
VA Department of Veterans Affairs
VAMC VA Medical Center
VA CFM VA Office of Construction and Facilities Management
VACO VA Central Office
VA PM VA Project Manager
VA-COR VA Contracting Officer’s Representative
01 91 00 - 5
List of Acronyms
Acronym Meaning
USGBC United States Green Building Council
1.6 DEFINITIONS
Acceptance Phase Commissioning: Commissioning tasks executed after most construction has been completed, most Site Observations and Static Tests have been completed and Pre-
Functional Testing has been completed and accepted. The main commissioning activities performed during this phase are verification that the installed systems are functional by conducting Systems Functional Performance tests and Owner Training.
Accuracy: The capability of an instrument to indicate the true value of a measured quantity.
Back Check: A back check is a verification that an agreed upon solution to a design comment has been adequately addressed in a subsequent design review
Basis of Design (BOD): The Engineer’s Basis of Design is comprised of two components: the
Design Criteria and the Design Narrative, these documents record the concepts, calculations, decisions, and product selections used to meet the Owner’s Project Requirements (OPR) and to satisfy applicable regulatory requirements, standards, and guidelines.
Benchmarks: Benchmarks are the comparison of a building’s energy usage to other similar buildings and to the building itself.. For example, ENERGY STAR Portfolio Manager is a frequently used and nationally recognized building energy benchmarking tool.
Building Information Modeling (BIM): Building Information Modeling is a parametric database which allows a building to be designed and constructed virtually in 3D, and provides reports both in 2D views and as schedules. This electronic information can be extracted and reused for pre-populating facility management CMMS systems. Building Systems Commissioning (BSC): NEBB acronym used to designate its commissioning program.
Calibrate: The act of comparing an instrument of unknown accuracy with a standard of known accuracy to detect, correlate, report, or eliminate by adjustment any variation in the accuracy of the tested instrument.
CCTV: Closed circuit Television. Normally used for security surveillance and alarm detections as part of a special electrical security system.
COBie: Construction Operations Building Information Exchange (COBie) is an electronic industry data format used to transfer information developed during design, construction, and commissioning into the Computer Maintenance Management Systems (CMMS) used to operate facilities. See the Whole Building Design Guide website for further information
(http://www.wbdg.org/resources/cobie.php)
01 91 00 - 6
Commissionability: Defines a design component or construction process that has the necessary elements that will allow a system or component to be effectively measured, tested, operated and commissioned
Commissioning Agent (CxA): The qualified Commissioning Professional who administers the
Cx process by managing the Cx team and overseeing the Commissioning Process. Where CxA is used in this specification it means the Commissioning Agent, members of his staff or appointed members of the commissioning team. Note that LEED uses the term Commissioning Authority in lieu of Commissioning Agent.
Commissioning Checklists: Lists of data or inspections to be verified to ensure proper system or component installation, operation, and function. Verification checklists are developed and used during all phases of the commissioning process to verify that the Owner’s Project Requirements
(OPR) is being achieved.
Commissioning Design Review: The commissioning design review is a collaborative review of the design professionals design documents for items pertaining to the following: owner’s project requirements; basis of design; operability and maintainability (O&M) including documentation;
functionality; training; energy efficiency, control systems’ sequence of operations including building automation system features; commissioning specifications and the ability to functionally test the systems.
Commissioning Issue: A condition identified by the Commissioning Agent or other member of the Commissioning Team that adversely affects the commissionability, operability, maintainability, or functionality of a system, equipment, or component. A condition that is in conflict with the
Contract Documents and/or performance requirements of the installed systems and components.
(See also – Commissioning Observation).
Commissioning Manager (CxM): A qualified individual appointed by the Contractor to manage the commissioning process on behalf of the Contractor.
Commissioning Observation: An issue identified by the Commissioning Agent or other member of the Commissioning Team that does not conform to the project OPR, contract documents or standard industry best practices. (See also Commissioning Issue)
Commissioning Plan: A document that outlines the commissioning process, commissioning scope and defines responsibilities, processes, schedules, and the documentation requirements of the Commissioning Process.
Commissioning Process: A quality focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that the facility and all of its systems, components, and assemblies are planned, designed, installed, tested, can be operated, and maintained to meet the Owner's Project Requirements.
01 91 00 - 7
Commissioning Report: The final commissioning document which presents the commissioning process results for the project. Cx reports include an executive summary, the commissioning plan, issue log, correspondence, and all appropriate check sheets and test forms.
Commissioning Representative (CxR): An individual appointed by a sub-contractor to manage the commissioning process on behalf of the sub-contractor.
Commissioning Specifications: The contract documents that detail the objective, scope and implementation of the commissioning process as developed in the Commissioning Plan.
Commissioning Team: Individual team members whose coordinated actions are responsible for implementing the Commissioning Process.
Construction Phase Commissioning: All commissioning efforts executed during the construction process after the design phase and prior to the Acceptance Phase Commissioning.
Contract Documents (CD): Contract documents include design and construction contracts, price agreements and procedure agreements. Contract Documents also include all final and complete drawings, specifications and all applicable contract modifications or supplements.
Construction Phase Commissioning (CPC): All commissioning efforts executed during the construction process after the design phase and prior to the Acceptance Phase Commissioning.
Coordination Drawings: Drawings showing the work of all trades that are used to illustrate that equipment can be installed in the space allocated without compromising equipment function or access for maintenance and replacement. These drawings graphically illustrate and dimension manufacturers’ recommended maintenance clearances. On mechanical projects, coordination drawings include structural steel, ductwork, major piping and electrical conduit and show the elevations and locations of the above components.
Data Logging: The monitoring and recording of temperature, flow, current, status, pressure, etc.
of equipment using stand-alone data recorders.
Deferred System Test: Tests that cannot be completed at the end of the acceptance phase due to ambient conditions, schedule issues or other conditions preventing testing during the normal acceptance testing period.
Deficiency: See “Commissioning Issue”.
Design Criteria: A listing of the VA Design Criteria outlining the project design requirements, including its source. These are used during the design process to show the design elements meet the OPR.
Design Intent: The overall term that includes the OPR and the BOD. It is a detailed explanation of the ideas, concepts, and criteria that are defined by the owner to be important. The design intent documents are utilized to provide a written record of these ideas, concepts and criteria.
Design Narrative: A written description of the proposed design solutions that satisfy the requirements of the OPR.
01 91 00 - 8
Design Phase Commissioning (DPC): All commissioning tasks executed during the design phase of the project.
Environmental Systems: Systems that use a combination of mechanical equipment, airflow, water flow and electrical energy to provide heating, ventilating, air conditioning, humidification, and dehumidification for the purpose of human comfort or process control of temperature and humidity.
Executive Summary: A section of the Commissioning report that reviews the general outcome of the project. It also includes any unresolved issues, recommendations for the resolution of unresolved issues and all deferred testing requirements.
Functionality: This defines a design component or construction process which will allow a system or component to operate or be constructed in a manner that will produce the required outcome of the OPR.
Functional Test Procedure (FTP): A written protocol that defines methods, steps, personnel, and acceptance criteria for tests conducted on components, equipment, assemblies, systems, and interfaces among systems.
Industry Accepted Best Practice: A design component or construction process that has achieved industry consensus for quality performance and functionality. Refer to the current edition of the NEBB Design Phase Commissioning Handbook for examples.
Installation Verification: Observations or inspections that confirm the system or component has been installed in accordance with the contract documents and to industry accepted best practices.
Integrated System Testing: Integrated Systems Testing procedures entail testing of multiple integrated systems performance to verify proper functional interface between systems. Typical
Integrated Systems Testing includes verifying that building systems respond properly to loss of utility, transfer to emergency power sources, re-transfer from emergency power source to normal utility source; interface between HVAC controls and Fire Alarm systems for equipment shutdown, interface between Fire Alarm system and elevator control systems for elevator recall and shutdown; interface between Fire Alarm System and Security Access Control Systems to control access to spaces during fire alarm conditions; and other similar tests as determined for each specific project.
Issues Log: A formal and ongoing record of problems or concerns – and their resolution – that have been raised by members of the Commissioning Team during the course of the
Commissioning Process.
Lessons Learned Workshop: A workshop conducted to discuss and document project successes and identify opportunities for improvements for future projects.
01 91 00 - 9
Maintainability: A design component or construction process that will allow a system or component to be effectively maintained. This includes adequate room for access to adjust and repair the equipment. Maintainability also includes components that have readily obtainable repair parts or service.
Manual Test: Testing using hand-held instruments, immediate control system readouts or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the ‘observation’).
Owner’s Project Requirements (OPR): A written document that details the project requirements and the expectations of how the building and its systems will be used and operated. These include project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
Peer Review: A formal in-depth review separate from the commissioning review processes. The level of effort and intensity is much greater than a typical commissioning facilitation or extended commissioning review. The VA usually hires an independent third-party (called the IDIQ A/E) to conduct peer reviews.
Precision: The ability of an instrument to produce repeatable readings of the same quantity under the same conditions. The precision of an instrument refers to its ability to produce a tightly grouped set of values around the mean value of the measured quantity.
Pre-Design Phase Commissioning: Commissioning tasks performed prior to the commencement of design activities that includes project programming and the development of the commissioning process for the project
Pre-Functional Checklist (PFC): A form used by the contractor to verify that appropriate components are onsite, correctly installed, set up, calibrated, functional and ready for functional testing.
Pre-Functional Test (PFT): An inspection or test that is done before functional testing. PFT’s include installation verification and system and component start up tests.
Procedure or Protocol: A defined approach that outlines the execution of a sequence of work or operations. Procedures are used to produce repeatable and defined results.
Range: The upper and lower limits of an instrument’s ability to measure the value of a quantity for which the instrument is calibrated.
Resolution: This word has two meanings in the Cx Process. The first refers to the smallest change in a measured variable that an instrument can detect. The second refers to the implementation of actions that correct a tested or observed deficiency.
Site Observation Visit: On-site inspections and observations made by the Commissioning
Agent for the purpose of verifying component, equipment, and system installation, to observe contractor testing, equipment start-up procedures, or other purposes.
01 91 00 - 10
Site Observation Reports (SO): Reports of site inspections and observations made by the
Commissioning Agent. Observation reports are intended to provide early indication of an installation issue which will need correction or analysis.
Special System Inspections: Inspections required by a local code authority prior to occupancy and are not normally a part of the commissioning process.
Static Tests: Tests or inspections that validate a specified static condition such as pressure testing. Static tests may be specification or code initiated.
Start Up Tests: Tests that validate the component or system is ready for automatic operation in accordance with the manufactures requirements.
Systems Manual: A system-focused composite document that includes all information required for the owners operators to operate the systems.
Test Procedure: A written protocol that defines methods, personnel, and expectations for tests conducted on components, equipment, assemblies, systems, and interfaces among systems.
Testing: The use of specialized and calibrated instruments to measure parameters such as:
temperature, pressure, vapor flow, air flow, fluid flow, rotational speed, electrical characteristics, velocity, and other data in order to determine performance, operation, or function.
Testing, Adjusting, and Balancing (TAB): A systematic process or service applied to heating, ventilating and air-conditioning (HVAC) systems and other environmental systems to achieve and document air and hydronic flow rates. The standards and procedures for providing these services are referred to as “Testing, Adjusting, and Balancing” and are described in the Procedural
Standards for the Testing, Adjusting and Balancing of Environmental Systems, published by
NEBB or AABC.
Thermal Scans: Thermographic pictures taken with an Infrared Thermographic Camera.
Thermographic pictures show the relative temperatures of objects and surfaces and are used to identify leaks, thermal bridging, thermal intrusion, electrical overload conditions, moisture containment, and insulation failure.
Training Plan: A written document that details, in outline form the expectations of the operator training. Training agendas should include instruction on how to obtain service, operate, startup, shutdown and maintain all systems and components of the project.
Trending: Monitoring over a period of time with the building automation system.
Unresolved Commissioning Issue: Any Commissioning Issue that, at the time that the Final
Report or the Amended Final Report is issued that has not been either resolved by the construction team or accepted by the VA. Validation: The process by which work is verified as complete and operating correctly:
1. First party validation occurs when a firm or individual verifying the task is the same firm or individual performing the task.
01 91 00 - 11
2. Second party validation occurs when the firm or individual verifying the task is under the control of the firm performing the task or has other possibilities of financial conflicts of interest in the resolution (Architects, Designers, General Contractors and Third Tier Subcontractors or
Vendors).
3. Third party validation occurs when the firm verifying the task is not associated with or under control of the firm performing or designing the task.
Verification: The process by which specific documents, components, equipment, assemblies, systems, and interfaces among systems are confirmed to comply with the criteria described in the
Owner’s Project Requirements.
Warranty Phase Commissioning: Commissioning efforts executed after a project has been completed and accepted by the Owner. Warranty Phase Commissioning includes follow-up on verification of system performance, measurement and verification tasks and assistance in identifying warranty issues and enforcing warranty provisions of the construction contract.
Warranty Visit: A commissioning meeting and site review where all outstanding warranty issues and deferred testing is reviewed and discussed.
Whole Building Commissioning: Commissioning of building systems such as Building
Envelope, HVAC, Electrical, Special Electrical (Fire Alarm, Security & Communications), Plumbing and Fire Protection as described in this specification.
1.7 SYSTEMS TO BE COMMISSIONED
A. Commissioning of a system or systems specified for this project is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel, is required in cooperation with the VA and the Commissioning
Agent.
B. The following systems will be commissioned as part of this project:
Systems To Be Commissioned
System Description
Fire Suppression
Fire Sprinkler Systems Wet pipe system, dry pipe system, pre-action system, special agent systems
Plumbing
Medical Vacuum Systems Packaged medical vacuum units, outlet certification, cross-connection verification
Waste Anesthesia Gas
Systems
Packaged Waste Anesthesia Gas units, outlet certification, cross-connection verification
01 91 00 - 12
Systems To Be Commissioned
System Description
Medical Gas Systems (other than Medical Air Systems)
Medical gas (oxygen, nitrogen, nitrous oxide, etc.) tank/manifold systems, outlet certification, cross-connection verification
HVAC
Noise and Vibration Control Noise and vibration levels for critical equipment such as Air
Handlers, Chillers, Cooling Towers, Boilers, Generators, etc.
will be commissioned as part of the system commissioning
Direct Digital Control
System**
Operator Interface Computer, Operator Work Station (including graphics, point mapping, trends, alarms), Network
Communications Modules and Wiring, Integration Panels.
[DDC Control panels will be commissioned with the systems controlled by the panel]
Steam/Heating Hot Water
System**
Boilers, boiler feed water system, economizers/heat recovery equipment, condensate recovery, water treatment, boiler fuel system, controls, interface with facility DDC system.
HVAC Air Handling
Systems**
Air handling Units, packaged rooftop AHU, Outdoor Air conditioning units, humidifiers, DDC control panels
HVAC Ventilation/Exhaust
Systems
General exhaust, toilet exhaust, laboratory exhaust, isolation exhaust, room pressurization control systems
HVAC Energy Recovery
Systems**
Heat Wheels, Heat Recovery Loops, AHU Integrated Heat
Recovery
HVAC Terminal Unit
Systems**
VAV Terminal Units, CAV terminal units, fan coil units, fin-tube radiation, unit heaters
Decentralized Unitary HVAC
Systems*
Split-system HVAC systems, controls, interface with facility
DDC
Hydronic Distribution
Systems
Pumps, DDC control panels, heat exchangers, Electrical
Grounding & Bonding
Systems
Witness 3rd party testing, review reports
Electrical System Protective
Device Study
Review reports, verify field settings consistent with Study
01 91 00 - 13
System Description
Low-Voltage Distribution
System
Normal power distribution system, Life-safety power distribution system, critical power distribution system, equipment power distribution system, switchboards, distribution panels, panelboards, verify breaker testing results (injection current, etc)
Lighting & Lighting Control**
Systems
Emergency lighting, occupancy sensors, lighting control systems, architectural dimming systems, theatrical dimming systems, exterior lighting and controls
Cathodic Protection
Systems
Review 3rd party testing results.
Lightning Protection System Witness 3rd party testing, review reports
Communications
Grounding & Bonding
System
Witness 3rd party testing, review reports
Structured Cabling System Witness 3rd party testing, review reports
Public Address & Mass
Notification Systems
Witness 3rd party testing, review reports
Nurse Call & Code Blue
Systems
Witness 3rd party testing, review reports
Security Emergency Call
Systems
Witness 3rd party testing, review reports
Duress Alarm Systems Witness 3rd party testing, review reports
Electronic Safety and Security
Grounding & Bonding Witness 3rd party testing, review reports
Physical Access Control
Systems
Witness 3rd party testing, review reports
Access Control Systems Witness 3rd party testing, review reports
Video Surveillance System Witness 3rd party testing, review reports
Fire Detection and Alarm
System
100% device acceptance testing, battery draw-down test, verify system monitoring, verify interface with other systems.
Site Utilities
Sanitary Sewerage Utilities City Sanitary Connection, Waste Treatment Systems
Integrated Systems Tests
01 91 00 - 14
System Description
Loss of Power Response Loss of power to building, loss of power to campus, restoration of power to building, restoration of power to campus.
Fire Alarm Response Integrated System Response to Fire Alarm Condition and
Return to Normal
Table Notes
** Denotes systems that LEED requires to be commissioned to comply with the LEED
Fundamental Commissioning pre-requisite.
1.8 COMMISSIONING TEAM
A. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning
Agent.
B. Members Appointed by Contractor:
1. Contractor’ Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team.
2. Contractor’s Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions.
C. Members Appointed by VA:
1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA will engage the CxA under a separate contract.
2. User: Representatives of the facility user and operation and maintenance personnel.
3. A/E: Representative of the Architect and engineering design professionals.
1.9 VA'S COMMISSIONING RESPONSIBILITIES
A. Appoint an individual, company or firm to act as the Commissioning Agent.
B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following:
1. Coordination meetings.
2. Training in operation and maintenance of systems, subsystems, and equipment.
3. Testing meetings.
4. Witness and assist in Systems Functional Performance Testing.
5. Demonstration of operation of systems, subsystems, and equipment.
01 91 00 - 15
C. Provide the Construction Documents, prepared by Architect and approved by VA, to the
Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.
1.10 CONTRACTOR'S COMMISSIONING RESPONSIBILITIES
A. The Contractor shall assign a Commissioning Manager to manage commissioning activities of the
Contractor, and subcontractors.
B. The Contractor shall ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.
C. The Contractor shall ensure that each installing subcontractor shall assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the following:
1. Participate in commissioning coordination meetings.
2. Conduct operation and maintenance training sessions in accordance with approved training plans.
3. Verify that Work is complete and systems are operational according to the Contract
Documents, including calibration of instrumentation and controls.
4. Evaluate commissioning issues and commissioning observations identified in the
Commissioning Issues Log, field reports, test reports or other commissioning documents. In collaboration with entity responsible for system and equipment installation, recommend corrective action.
5. Review and comment on commissioning documentation.
6. Participate in meetings to coordinate Systems Functional Performance Testing.
7. Provide schedule for operation and maintenance data submittals, equipment startup, and testing to Commissioning Agent for incorporation into the commissioning plan.
8. Provide information to the Commissioning Agent for developing commissioning plan.
9. Participate in training sessions for VA's operation and maintenance personnel.
10. Provide technicians who are familiar with the construction and operation of installed systems and who shall develop specific test procedures to conduct Systems Functional Performance
Testing of installed systems.
1.11 COMMISSIONING AGENT’S RESPONSIBILITIES
A. Organize and lead the commissioning team.
B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.
01 91 00 - 16
C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems relating to the Construction Documents.
D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre-Functional Checklists, Systems Functional Performance Testing; and project completion.
E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The
Commissioning Agent shall prepare and distribute minutes to commissioning team members and attendees within five workdays of the commissioning meeting.
F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.
G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.
H. Coordinate Systems Functional Performance Testing schedule with the Contractor.
I. Witness selected systems startups.
J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.
K. Witness and document Systems Functional Performance Testing.
L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.
M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.N.
Review operation and maintenance training program developed by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.
O. Prepare commissioning Field Observation Reports.
P. Prepare the Final Commissioning Report.
Q. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal Systems Functional Performance Testing. Also interview facility staff and identify
01 91 00 - 17 problems or concerns they have operating the building as originally intended. Make suggestions for improvements and for recording these changes in the O&M manuals. Identify areas that may come under warranty or under the original construction contract. Assist facility staff in developing reports, documents and requests for services to remedy outstanding problems.
R. Assemble the final commissioning documentation, including the Final Commissioning Report and
Addendum to the Final Commissioning Report.
1.12 COMMISSIONING DOCUMENTATION
A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited, to the following:
1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a detailed description of submittals that are required to support the commissioning processes.
Submittal dates shall include the latest date approved submittals must be received without adversely affecting commissioning plan.
2. Description of the organization, layout, and content of commissioning documentation
(including systems manual) and a detailed description of documents to be provided along with identification of responsible parties.
3. Identification of systems and equipment to be commissioned.
4. Schedule of Commissioning Coordination meetings.
5. Identification of items that must be completed before the next operation can proceed.
6. Description of responsibilities of commissioning team members.
7. Description of observations to be made.
8. Description of requirements for operation and maintenance training.
9. Schedule for commissioning activities with dates coordinated with overall construction schedule.
10. Process and schedule for documenting changes on a continuous basis to appear in Project
Record Documents.
11. Process and schedule for completing prestart and startup checklists for systems, subsystems, and equipment to be verified and tested.
12. Preliminary Systems Functional Performance Test procedures.
B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop
Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems
Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested. Preliminary Systems Functional Performance Test Procedures will be
01 91 00 - 18 provided to the VA, Architect/Engineer, and Contractor for review and comment. The Systems
Performance Test Procedure will include test procedures for each mode of operation and provide space to indicate whether the mode under test responded as required. Each System Functional
Performance Test procedure, regardless of system, subsystem, or equipment being tested, shall include, but not be limited to, the following:
1. Name and identification code of tested system.
2. Test number.
3. Time and date of test.
4. Indication of whether the record is for a first test or retest following correction of a problem or issue.
5. Dated signatures of the person performing test and of the witness, if applicable.
6. Individuals present for test.
7. Observations and Issues.
8. Issue number, if any, generated as the result of test.
C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre-Functional Checklists.
Pre-Functional Checklists shall be completed and signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The
Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing. Inaccurate or incomplete Pre-Functional Checklists shall be returned to the
Contractor for correction and resubmission.
D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application shall be included with data. Commissioning Agent Will compile test and inspection reports and test and inspection certificates and include them in systems manual and commissioning report.
E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The
Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results.
F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning
Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues
Log will identify and track issues as they are encountered, the party responsible for resolution, 01 91 00 - 19 progress toward resolution, and document how the issue was resolved. The Master
Commissioning Issues Log will also track the status of unresolved issues.
1. Creating an Commissioning Issues Log Entry:
a. Identify the issue with unique numeric or alphanumeric identifier by which the issue may be tracked.
b. Assign a descriptive title for the issue.
c. Identify date and time of the issue.
d. Identify test number of test being performed at the time of the observation, if applicable, for cross reference.