This pre-solicitation notice is for a construction project to build a new chiller plant at the Omaha VA Medical Center in Omaha, Nebraska. The project requires building a new chiller plant adjacent to the existing boiler plant to house two centrifugal chillers and relocate a temporary chiller. It will be constructed to accommodate future campus growth. An existing metal storage shed will be removed. The estimated construction cost is $10-20 million. The solicitation number is 36C26318B0065 and will be posted on February 8, 2022, containing specifications, drawings and bidding information. An organized site visit will be held prior to the March 8, 2022 proposal due date. The 550-day period of performance will begin at notice to proceed. The awardee must provide performance and payment bonds within 10 days of award. This opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26322R0065 0004.docx | DOCX document | |
| 36C26322R0065 0003.docx | DOCX document | |
| Addendum Plan SheetsPart-4.pdf | ||
| Addendum specs 040822.pdf | ||
| Addendum Plan SheetsPart-2.pdf | ||
| Addendum Plan SheetsPart-6.pdf | ||
| Addendum Plan SheetsPart-1.pdf | ||
| Addendum 040822.pdf | ||
| Addendum Plan SheetsPart-7.pdf | ||
| Addendum Plan SheetsPart-3.pdf | ||
| Addendum Plan SheetsPart-8.pdf | ||
| Addendum Plan SheetsPart-5.pdf | ||
| Geotechnical Report Terracon no 05215161R01.pdf | ||
| HMS VA Omaha 103119.pdf | ||
| S02_Specs - Volume 1 revised.pdf | ||
| S02_ATTACH - Specs - Volume 2 (1376 pages).pdf | ||
| Omaha VA Chiller photos.pdf | ||
| S02_ATTACH - Drawings (132 pages).pdf | ||
| 36C26322R0065 Final.docx | DOCX document | |
| Site Vist Sign In sheet.pdf | ||
| 36C26322R0065 0001.docx | DOCX document | |
| 36C26322R0065.docx | DOCX document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
04-04-2022
636-22-4-5988-0002
636-18-304 36C263
Department of Veterans Affairs Network 23 Contracting Office (NCO 23) 111 South 18th Plaza, Suite C38 Omaha NE 68102-2077
36C263
Department of Veterans Affairs Network 23 Contracting Office (NCO 23) 111 South 18th Plaza, Suite C38 Omaha NE 68102-2077 To all Offerors/Bidders
36C26322R0065 03-11-2022
X
X
X March 12, 2022 at 2:00 pm CDT
636-3620162-5988-854200-3220 23NR9WA20
Project: 636-18-304, Construct Combined Energy Plan Phase 1 (Chiller Plant), Omaha, Nebraska VA Contracting POC: Sharon Spohn, Phone: 402-996-3522, Email: sharon.spohn@va.gov
A. This amendment is issued to provide answers to several questions, see page 2.
Sharon Spohn NCO 23 Contracting Officer
VA-VHA-2020-645FFEAB
Questions-Answers – March 30, 2022
| No. |
| Questions |
| Answers |
| 1. |
| For Factor 1 – Experience and Factor 3-Key Personnel Experience, will the Government please consider the use of 10-Point Size Font? |
| For Factor 1 and Factor 3, it is ok to use 10-point font size. |
| 2. |
| The schedule has some conflicts between the chiller data and tower data. The chiller has 3750 GPM listed for condenser flow and the tower schedule shows 4500 GPM. This makes a completely different tower selection if we go from 3750 to 4500 per chiller. What is the reason behind the discrepancy? Please clarify. |
| The flow rate on the cooling tower is the “design Selection” an addendum under separate cover will follow to add “Operating” Values to be consistent with the chiller schedule. |
| 3. |
| We are going to quote Tower Tech for the cooling towers on the project. |
| The specifications only have provisions for an “all” stainless steel cooling tower. Alternative materials were reviewed during design with the government. All other options were removed and will not be allowed. |
| 4. |
| Is this project sales tax exempt? If the project is sales tax exempt, will the government/VA provide a sales tax exemption certificate? |
| This project is NOT sales tax exempt. A Form 17 will NOT be provided. |
| 5. |
| Please confirm if the listed SSHO position can be double-hatted with a qualified superintendent? |
| No, the SSHO position cannot be the same person as a qualified superintendent. |
| 6. |
| Can the VA release the Geotechnical report? |
See attached report – Geotechnical report -Terracon no 05215161R01.
| 7. |
| What is the depth of the foundation piers? |
See Drawing Sheet S-1.2
| 8. |
| Please clarify the VA’s preferred method of submission for proposals? Will electronic copies via email be sufficient? |
| Please submit one hard copy with a CD of the proposals. Be sure to separate technical factors in Volume 1 and pricing factors in Volume 2. Electronic is not sufficient. |
| 9. |
| What temperature and pressure will this system need to be rated at? The chiller water system is specified at 160 PSI @50F deg. |
| The pressure rating at 50F is 160psig and 80F is 125 psig (237fthd) |
| 10. |
| Confirm the proposal due date. |
The proposals are due April 12th.
| 11. |
| Please provide a specification for the chillers. |
| Refer to section 23 64 00 Packaged Water Chillers in Volume 2. |
| 12. |
| Please provide a soils report - Terracon Report 05215161. [reference sheet s-1.1, Site Preparation for soil supporting foundations] |
| See attached report. |
| 13. |
| Specification 26 11 16-2.3 calls for liquid filled transformers (FR3 high fire point), however, floor plans show the substation transformers to be indoor in a NEMA 1 environment. That electrical room does not seem to be a vault. Liquid transformers cannot be used indoors unless in a vault (or with silicone insulating liquid that most manufacturers do not use anymore). Vendor requests that these be changed to dry type transformers, either VPI or cast to allow safe installation in the rooms indicated. |
| The electrical room meets the requirements for indoor installations per the NEC with liquid confinement with the less-flammable liquid and a fire sprinkler system in the building. Liquid confinement will be added in Addendum #1 consisting of a 12” high metal pan/barrier around the transformer section to act as containment of minor leaks with depressing the electrical room 6” for full leak containment. |
| 14. |
| Specification 26 23 00 LV switchgear section 2.1.A.2 calls for front access switchgear. This ANSI rated switchgear is normally specified as front and rear accessible, not just front. The floor plans on XX-EP-101 show that there is sufficient access to both the front and rear of the gear (5 feet or more as scaled on the LV side). Additionally, for front only access switchgear, the number of sections would have to be doubled from what is shown on the floor plan and the 1 line, adding significant width to the low voltage switchgear lineups. |
| Addendum #1 will revise this to front and rear access. |
| 15. |
| Can the contractor bid groved mechanical fittings, in addition to welded and sweat? Normally the hydronic specification has a provision for this as contractor’s option. The VA master specification is silent on this option (doesn’t prohibit it) in Division 23. |
| Grooved pipe connectors are allowed for connections of valves per specifications. Additional grooved piping connections are upon allowance of local VA representative. |
| 16. |
| On sheet 17-MPD100, they indicate a field report (Report No. 636-18-304 dated October 22, 2019) that contains photos of the areas that are requiring asbestos abatement. No where in the documents does it contain this report with photos. During site visit we could not visibly see any possible asbestos containing materials in the area noted for demolition. We need the report to properly bid this project. |
| See Photos attached. |
| 17. |
| In specification section 02 82 13.13, they note to remove asbestos using a glove bag method. Further in the spec then also note to build an enclosure to perform abatement. Do to conflicting notes in this section, can we get verification that if we follow state of Nebraska regulations for abatement, this will be adequate. |
| The use of “glovebag(s)” for the abatement of asbestos-containing thermal system insulation in the absence of a work site containment, the abatement contractor shall comply the requirements of the Nebraska Asbestos Control Program Title 178 Chap. 22. |
Ref. 178 NAC 22-011 - “Establish general security and management work practices”.
| 18. |
| Specification 26 23 00 LV switchgear section 2.1.A.2 calls for front access switchgear. This ANSI rated switchgear is normally specified as front and rear accessible, not just front. The floor plans on XX-EP-101 show that there is sufficient access to both the front and rear of the gear (5 feet or more as scaled on the LV side). Additionally, for front only access switchgear, the number of sections would have to be doubled from what is shown on the floor plan and the 1 line, adding significant width to the low voltage switchgear lineups. |
| See response to RFI #14. |
| 19. |
| Please confirm that the binder cover, cover letter, table of contents, and page dividers don’t count against the page limit. |
| The binder cover, cover letter, table of contents, and page dividers, DO NOT count against the page limit. |
| 20. |
| Sheet AI-000 shows 4 phases. Are these to be project areas and not phases? Please confirm that all areas show on this drawing are part of the solicitation documents as it pertains to this contract, which the Government has labeled “Phase 1” and are not phases of a future contract. |
| These are phases (areas for work to be performed) within this particular contract and correspond with project phasing per MEP drawings. |
| 21. |
| CU-111, CD-111, CS-400 Area 4, CS-413, CU-113, and every page of the drawings depicting this area shows electrical transformers and switches that are to be deleted or relocated. This plan indicates that the Building 17 Transformer is being deleted and chilled water lines are to be installed in its place. Is this transformer to be removed in the scope of this project? |
| Building 17’s transformer will not be relocated. The Air-Handling Tower construction project will relocate the existing pad-mounted switch east of the Building 17 transformer to the location as shown on 0-ES-101 and called out by Keyed Note 2. Refer to 0-ESD101 for existing electrical equipment scope in the vicinity of Building 17 that serves the Temporary Chiller Connex Container that will be relocated to the new Energy Plant. |
| 22. |
| Existing Underground Hydronic Lines noted for removal are believed to be 14” lines that were installed over top of 24” ductile iron encased in concrete at various intervals. Are the 24” ductile iron lines and concrete to be removed as well as the 14” lines? |
| Only removal of underground 14” lines are within the scope of project. |
| 23. |
| Please provide the scheduled shaft diameter to be used for bidding. [reference sheet S1.207 Typical Footing Detail] |
| Refer to Sheet S-4.1 |
| 24. |
| Please provide the schedule vertical reinforcement to be used for bidding [reference sheet S1.207 Typical Footing Detail] |
| Refer to Sheet S-4.1 |
| 25. |
| Should the situation arise, how is the VA going to handle the payment of stored materials? Will the VA require proof of payment from the contractor to the suppler before allowing it to be billed to the VA? Will the VA allow full payment? Partial Payment? |
FAR 52.232-5 Payments under Fixed-Price Construction contracts must be followed. The CO may authorize material delivered on site and preparatory work done to be taken into consideration.
| 26. |
| Specification 01 35 26 1.7 C states the Site Safety and Health Officer must to be a separate individual from the Superintendent and/or Quality Control Manager. However, can the appointed Quality Control Manager be the same individual as the Project Superintendent? |
| No. |
| 27. |
| Can the Commissioning Manager outlined in 01 91 00 1.10 A be the same individual as the project’s Superintendent, SSHO, or Quality Control Manager? |
| No. |
| 28. |
| Can mechanical pipe joints such as Victaulic for the HVAC systems are allowed on this project? |
| Refer to question 15 above. |
| 29. |
| Information needed on the heating water system: what temperature and pressure will this system need to be rated at? I see the chilled water system is specified at 160 PSI @ 50F deg. Please confirm/ clarify. |
| Refer to question 9 above. |
| 30. |
| On Sheet 0-MS-001 in reference to the 24” underground Chilled water supply and return piping after leaving the new Chiller plant and turning to the South we then need to cross the existing steam tunnel. What is the existing steam tunnel dimensions in reference to top of grade? Dimensions of existing steam tunnel into existing boiler house? |
| Existing steam tunnel exact dimensions and depth will need to be verified on site. |
| 31. |
| Are there any current site plans that can clarify where the electrical, piping or any other underground obstacles interfering with the proposed pipe routing? |
| Available information is shown on the Drawings. |
| 32. |
| On Sheet 0-MS-001 in reference to note 9 and 3. Do the new underground 24” Chilled water pipes tie into the existing 16” and 12” Condenser water lines? This is unclear? |
| New chilled water lines do not tie into existing condenser water lines. Existing condenser lines to be removed as part of 0-MSD001. |
| 33. |
| Are there any Seismic requirements? According to the forces listed, with Site class = D the SDC = A, this project would exempt from seismic certification. |
The only thing that mentions vibration isolation is on drawing O-M-503 detail 2 and on drawing O-M-504 detail 2 & 3.
Refer to Seismic requirements as listed 01 45 35.
| 34. |
| Have the temporary chillers been sized? (Other than the note on sheet 0-MS-001 note 10, temp chillers to meet or exceed 1250 tons) |
Temporary chillers must be sized as shown on drawings.
| 35. |
| Do you have the temp chillers held for this project? According to the Trane chiller rental (your current rented chiller) they are out of rentals for this project duration. |
| Temp chillers shall be the responsibility of the contractor and this work. |
| 36. |
| There are notes to move and/or relocate enclosed chillers, please clarify if that chiller will remain on site as the new temporary ones gets put online while the new ones are installed? |
| Existing enclosed chiller relocations on the site as per drawings. Refer to Phasing for additional information. |
| 37. |
| Does the material have to be 100% American made materials? |
The simple answer is “yes”, but follow FAR 25.200 for Buy American Act – Construction Materials.
| 38. |
| What piping on the roof of the chiller building needs heat traced? Is it make up water, the tower drains and the condenser water? |
| Make up water, condenser water, sweeper system, and drains require heat tracing. |
| 39. |
| For Factor 1 – Experience, will the VA consider changing the requirements from projects that are 100% completed to projects that are 75% completed? |
| My recommendation is that most of the vendors competing on this project are going to have issues with the size. It is best value – put your best projects on your proposal. |
| 40. |
| Since most subcontractors are not known at the time of bid, it will be difficult to obtain subcontractor company and key personnel resumes. With that in mind, will the contractors that do not submit resumes for subcontractors be ranked lower than those that do provide subcontractor resumes? |
| Include the subcontractor that you are most likely to go with, if needed. Please follow the evaluation factors on page 9 thru 15 of the solicitation. The main emphasis is the prime contractor. |
| 41. |
| Can a contractor submit multiple subcontractor resumes for the same positions (e.g., three electricians) since the contractor may not be able to determine which subcontractor will be used at the time of bid document preparation? |
| You can submit multiple resumes, but keep in mind resumes are included in the 40 page limitation. |
| 42. |
| Please confirm CMU block fill to be "Pea Gravel Concrete" is considered "course grout" per ASTM C476. |
| Pea gravel concrete utilizes pea gravel as the aggregate. |
| 43. |
| Please advise if special consideration will be needed for the "Abandoned coal conveyor tunnel" for the installation of concrete piers 4, 8 & 12? |
| Contractor to remove abandoned concrete where necessary for new construction. |
| 44. |
| Please advise if special consideration will be needed to protect the basement of Bldg. 2 during the foundation and pier installation along column line "D" of the new chiller? |
| That will depend on contractor’s selected means and methods of work. |
| 45. |
| The pier schedule does not include the pier depth. Please confirm pier lengths are 66ft, based on 1196.5' FF - 4'-0" (detail S1.201 grade beam) - 1126.5 ' (bearing elevation per S1.207) = 66ft length. |
| See sheet S-1.2 |
| 46. |
| Drawing Note #3 says the new stacked concrete block wall is to "match existing." Is the existing wall structural or decorative in nature? Will this require tie-backs and a delegated design? Detail 3/C-503 is not specific. |
| Stacked retaining wall system will need to support traffic loads on existing access road west of the new wall. Style to match existing on site. Submit engineered manufacturer design as a submittal. |
| 47. |
| Electronic v. Hard Copy Submission: Please advise if this is a hard copy (overnight) or electronic (via email) submission. If hard copy, we respectfully request that the Government change this to electronic submission via email. As pricing is usually not released from the trades until the last minute, it would be advantageous for the Government to allow for electronic submission, so Offerors are afforded the ability to receive and provide the best pricing. |
| One (1) Hard copy with disk |
| 48. |
| Neither sheet 0-TS-101 or 0-ES-101 indicates the number or size of conduits within the electrical duct banks. Please provide the number of ducts and the quantity and size of conduits required. |
| XX-E-601’s feeder schedule and one-line diagram indicate the conduit sizes and cabling for the electrical duct bank. Detail 1 on XX-T-601 indicates the communications conduit sizes and cabling requirements for the telecom duct bank. Clarification of the Keyed Notes on 0-TS-101 and 0-ES-101 will be made to reference these sheets in Addendum #1. |
| 49. |
| Are there any profile drawings for the new chilled water distribution? |
| No. |
| 50. |
| Will the government provide existing utility profile drawings in the areas for the new chilled water and MV electrical duct bank? |
| No such drawings exist. |
| 51. |
| M-401 | Drawing identifies to remove existing pumps from the existing chiller box. Is the contractor to assume that all hydronic specials (valves, strainers, triple duty valves, etc.) will be removed? Is it the intent for the contractor to remove all associated piping and make new piping connections once the temp plant is relocated? |
| Correct. Remove all existing piping and specialties to make new connections. |
| 52. |
| 0-MSD001 | Key Note – 7 | Please confirm that the temp chillers refrigerant will be removed prior to relocation. Should the contractor assume to remove chillers oil charge prior to relocation and charge with new oil once relocated? |
| Correct. |
| 53. |
| Please provide an equipment submittal for the Trane Temp Chiller that will be relocated. |
Refer to existing Chiller schedule on 0-M-601.
| 54. |
| 0-MD-201 | Bold lines references ‘remove existing chiller, cooling tower and associated components’ - while the Chiller ‘X’ and cooling tower is marked as ETR. Please confirm which is correct. |
| This chiller is to be removed from existing location and relocated. Cooling tower to be removed. Will clarify in upcoming addendum. |
| 55. |
| 0-M-201 | U/G CWS/R distribution piping references leaving the new chilled water plant at 24” and entering Building 17 on (17-MP-100) as 18”. Please provide the location at which the contractor shall transition from 24” to 18” CWS/R U/G piping. |
| Refer to 0-MS-001 Site plan for location. |
| 56. |
| 0-M-201 | Ambulatory Care CWS/R Distribution – As the lines are bolded, is the CW Pump part of this project or is it existing? |
| Per plans these lines to not appear bold and are outside of the current scope. |
| 57. |
| Trane Absorber (CH-1) in Bldg. 17. Is this chiller operational and part of the stations chilled water line-up? |
| Chiller is operation and to be demolished per 17-MPD100. |
| 58. |
| During the site visit it was mentioned that there was a temporary air-cooled chiller onsite near Bldg. 17 as shown on drawing 0-M-001. Is this chiller in place and operational? If it is in operation, is the contractor to assume the 14” CWS/R piping is installed as shown on 17-MP-100 and 0-MS-001? Please provide any submittal data for this chiller. |
| There are no known temporary air cooled chillers as part of this scope of work. |
| 59. |
| 0-M-001 | References ‘provide power to temporary chillers’. Please provide location of power for the temp chillers as it is not referenced on any of the drawings. |
| This shall be the responsibility of the contractor. |
| 60. |
| “Cathodic protection” is mentioned nine (9) times in the specification, however, there is no cathodic protection specification under DIV. 26. Is cathodic protection required on this project? |
| Cathodic protection is required as indicated in the specifications. Provide protection as required and designed by a corrosion specialist meeting NACE requirements listed within the relevant specs. A separate Division 26 spec will not be required. |
| 61. |
| Spec 23 2 23.2.1g – Please confirm that all centrifugal pumps shall be factory tested. |
| Factory testing is required as indicated in the specifications. The Government retains the option to witness testing and notice shall be given when testing is performed in accordance with the specifications. |
| 62. |
| The vast majority of Division 26 requires factory testing on conductors, switchgear and ATS etc. Please confirm that the government will require this. If yes, will the government require witness testing as well? |
| Factory testing is required as indicated in the specifications. The Government retains the option to witness testing and notice shall be given when testing is performed in accordance with the specifications. |
| 63. |
| 01 00 00 1.2-D indicates “testing laboratory retained by Department of Veterans Affairs,” however, 01 45 29 1.1 states “retained by General Contractor.” Who is to retain the Testing Laboratory? |
| The general contractor is responsible for testing laboratory costs. |
| 64. |
| 02 82 13.1.1.B.1.a | Please provide photos 3/3A from AMI Hazardous Material Report dated October 29, 2019. |
| See photos attached |
| 65. |
| 02 82 13.1.1.B.1.b | Please provide photos 8/8A from AMI Hazardous Material Report dated October 29, 2019. |
| See photos attached |
| 66. |
| Who is the controls contractor for the hospital? |
| Refer to Specifications 23 09 23 Part 1, subsection F. |
| 67. |
| Will potholing and site survey for the existing underground water lines and new water lines be by the Owner 3rd party, the GC or subcontractor? |
| The general contractor will be responsible for utility safety/locating. |
| 68. |
| Can you please provide a spec for the temporary chillers? |
| Temporary chillers shall be responsibility of contractor. |
| 69. |
| Is the phasing plan mandatory or can we develop a different one? |
Phasing plan is suggested. Building must have full cooling capacity as required.
| 70. |
| What are the working hours? |
The working hours are 7:00 am to 4:30 pm (local Time) – see specification 01 00 00-1 (f).
| 71. |
| Are there Small Business subcontracting goals? |
Since you are a small business, a small business subcontracting plan or goals are not required.
| 72. |
| Are road closures/shutdowns the responsibility of the GC of the sub? |
| Our contract is with the Prime contractor, so most coordination should come thru the prime. |
| 73. |
| Is past performance for subcontractors on similar projects required? |
| This is your choice. See the evaluation factors. |
| 74. |
| Refer to Drawing Sheet 02-MPD101, General Note A. references a Hazardous Building Materials Inspection Report 636-18-304, Dated October 22, 2019. |
Please provide a copy of this referenced HBMI Report.
Report attached.
| 75. |
| Refer to Sheet GI-002, there was a computer glitch when printing this sheet, words not printed out correctly. |
Please provide a corrected Sheet GI-002.
This is General Information Sheet to be include in addendum if not provided before.
| 76. |
| Volume 2 of the Specifications does not include a specification section for the Water-Cooled Chillers. |
Please provide a specification for the desired chillers.
Refer to 23 64 00 Packaged Water Chillers, Page 499.
| 77. |
| Refer to Sheet 0-MS-001, KN #10 indicates a location for (2) two temporary chillers, Total Capacity to Meet or Exceed 1250Tons. This may mean (3) Three Temporary Chillers would be required, based on the Trane Rental Fleet configurations. |
1. Please provide a specification for these temporary chillers.
1. What existing chillers will these be taking the place of or supplementing?
Total capacity requirements are the specifications. Chillers may be rented from any fleet rental and are not limited to only those of Trane and may be at discretion of contractor. Quantity as listed is only a minimum and additional chillers to meet capacity requirements may be used at contractor discretion.
These chillers will be supplementing removal or offline of the CH-1 and CH-2 as per existing chiller schedule.
| 78. |
| Refer to Sheet 0-MS-001, KN #11 specifies the supply and return piping for the Temporary Chillers. The temporary piping is detailed on Sheet 17-MP-100. This piping cannot be installed until the demo is completed as specified on Sheet 17-MPD100. |
Please confirm the Absorption Chiller and associated piping as detailed on Sheet 17-MPD100 can be demolished prior to connecting the Temporary Chillers.
This must be coordinated with phasing plan. New temporary taps shall be responsibility of contractor and temporary piping is expected to be above grade.
| 79. |
| Refer to Sheet 0-MSD-001, KN #6 specifies “Existing Temporary Chiller” to be relocated per new work. |
Please confirm this temporary chiller can be removed/relocated prior to completing the new piping in Building 17 and connection of the Temporary Chillers shown on Sheet 0-MS-001.
This is expected and should be coordinated with any seasonal or shoulder month operations.
| 80. |
| Refer to Sheet 0-MS-001, KN #5 indicates Existing Temporary Chiller to Be Relocated per New Work. “Refer To 1/0-MS-002 For New Location.” |
Please confirm this is the New Location for the “Temporary Chiller” noted by KN #6 on Sheet 0-MSD001.
0-MSD001 is a demolition sheet and does not indicate new locations.
| 81. |
| Refer to Sheet 0-M-001, The General Notes specify to move “Existing Chiller (CH-B)” in Phase 2. Sheet 0-MS-001 indicates existing ACC Outdoor Modular Chiller (CH-B) To Remain. Which Chiller is “CH-B”? |
| 0-M-001 refers to Chiller CH-2 per existing Chiller Schedule. |
0-MS-001 refers to CH-E per Existing Chiller schedule. This will be clarified in addendum.
| 82. |
| Refer to Sheet 0-MSD-001, KN #8 indicates to remove the existing cooling tower with the “Trane Conex Chiller”. |
Does this Cooling Tower service any other chiller than the “Trane Conex Chiller”?
This is correct. The cooling tower only serves this chiller.
| 83. |
| On Sheet 0-MS-001 in reference to the 24” underground Chilled water supply and return piping leaving the new Chiller plant and turning to the South we then need to cross the existing steam tunnel. |
1. What is the existing steam tunnel dimensions in reference to top of grade?
1. What are the dimensions of the existing steam tunnel into the existing boiler house?
This is to be confirmed by the contractor.
| 84. |
| Please provide As-Built site plans that can clarify where the electrical, piping or any other underground obstacles interfering with the proposed pipe routing? |
| All known information has been shown on the drawings. |
| 85. |
| On Sheet 0-MS-001 in reference to |
notes 9 and 3.
Do the new underground 24” Chilled water pipes tie into the existing 16” and 12” Condenser water lines? This is unclear.
Refer to response 30 above.
| 86. |
| Refer to Sheet 0-ES-101, the electrical site plan does not provide any information concerning the Temporary Chillers. |
1. Please specify any electrical requirements for the Temporary Chillers.
1. What electrical panel, breaker sizes, should it be on emergency power?
0-ES-101 shows the requirements for relocating the existing transformer and main switch that are adjacent to the temporary chiller that will be relocated by Division 23. The temporary chiller includes an existing motor control center that will be relocated with the chiller and addresses power to the internal components. Refer to XX-E-601 for additional information on these requirements. This will not be on any emergency power except for what is backed up by the VA Whole Campus Standby Generator.
| 87. |
| Refer to Sheet 0-M-501, Detail #6 indicates a minimum depth of 42” to the top of pipe. On Sheet XX-E-501, Detail #3 GN #3 indicates minimum depth of 24” to the top of the duct bank. The Phasing Plan on Sheet 0-M-001 indicates the electrical duct bank is in Phase 1 and the new chilled water lines are in Phase 3. Since the Chilled Water lines are deeper, they should be installed first. |
Please confirm the Phasing Plan can be modified to allow the Chilled Water lines to be installed prior to the Electrical Duct Bank.
Final exact phasing may be at the choice of the contractor with sections of piping being installed at different times throughout the project as required.
| 88. |
| Please provide the geotechnical report referenced in the structural general notes (Dwg 36) Dwg 37 (S-1.2) Detail S-1.207 provides a bearing elevation of 1126.5’. Please confirm this is the correct elevation. |
| See attached report. |
| 89. |
| Dwg 37 (S-1.2) Detail S-1.207 shows spiral reinforcing. Please confirm that rebar rings will be acceptable in lieu of continuous spiraled rebar. |
| Use continuous spiral reinforcing steel as shown on typical pier detail |
| 90. |
| Page 9 of 96 paragraph 21 states that funding is NOT presently available, and won’t be available until Sept 30th, 2022 possibly Nov. 30th 2022. Please confirm if this is correct. |
| Funding is NOT presently available. The VA plans to award as soon as possible. |
| 91. |
| General note 25 on AS230 does not match the roof plan drawing with regards to condensing units, exhaust fans, and the roof hatch. Please advise which prevails, the general note or the roof plan. |
| Roof Plan prevails |
| 92. |
| Warranty requirements in general note 27 on drawing AS230 do not match the requirements in the spec 07 54 23 (20 yrs. vs 10 yrs.). Please confirm which prevails. |
| Spec 07 54 23 prevails |
| 93. |
| Dwg. 124 Sheet 0-TS-101 Note 3 Refers to Coordinating location and routing of new Comm lines to the Main server room for Building 1 with COR. Please provide COR coordination drawings to insure accurate pricing. |
| Communications contractor to field verify desired routing and final path to main server room. Coordination drawings do not exist. Coordination with COR shall be performed to ensure access in the working hospital is scheduled to ensure maintaining hospital operations. |
| 94. |
| Please provide the ICRA requirements for routing the new comm. lines to Building 1 server room. |
| Architectural response/revision required. |
| 95. |
| Please provide a specification or style of “Allan Block” for the retaining wall. |
| Match existing walls on site. Note that this wall will need to support traffic loads from access road to west side of wall. |
| 96. |
| Would the VA accept “Vertica-Pro Block” in lieu of “Allan Block” for the retaining wall? |
| The VA will not pre-approve “or equal” products before award. |
| 97. |
| Please confirm that the CQC System Manager must be must be on-site during Construction, and an employee of the SDVOSB contractor per Volume 1 Specification page 126 paragraph B |
| Yes, the CQC System manger must be on site during construction. |
| 98. |
| Please confirm that the SSHO Will need to maintain a presence on site during all construction activities per Volume 1 Specifications page 90 Paragraph D. |
| Yes a SSHO will need to maintain a presence on site during all construction activities. |
| 99. |
| Please confirm that the SSHO must be a separate qualified individual from the contractor’s superintendent/CQC manager per Volume 1 Specifications page 90 Paragraph C. |
| Yes, the SSHO MUST be a separate qualified individual from the superintendent/CQC Manager. |
| 100. |
| Please confirm the SSHO must be an employee of the SDVOSB contractor. |
| Yes, the SSHO must be an employee of the SDVOSB contractor (prime). |
| 101. |
| Who is the controls contractor for the hospital? |
| Refer to response 66 above – Specification 23 09 23 Part 1 |
| 102. |
| Will the VA provide utility locates? |
| All known utilities are shown on the plans. |
| 103. |
| Please confirm the legend and detail 1 on drawing sheet AI-100 are correct. Looks like it may be missing a rated assembly on the legend. |
Legend is correct. To clarify, IT CLOSET and EMERGENCY ELECTRIC are 2 hr. rooms. Remainder of wall along grid line 2 is to be 1 hr.
| 104. |
| Is it acceptable to grout in place the abandoned chiller utility lines? |
No. Old lines are to be removed and backfilled.
| 105. |
| Can solid plastic toilet partitions be used? |
VA standards do not allow for plastic partitions. Ceiling-mounted metal partitions must be used.