36C26322R0065 0001.docx

DOCX document 97 KB Posted

Attached to
Y1DZ--PN: 636-18-304, Construct Combined Energy Plant Phase 1 (OM)
Solicitation number
36C26322R0065
Issued by

About this file

This document contains a federal solicitation and related questions and answers regarding a construction project. The Department of Veterans Affairs is soliciting proposals to construct a new chiller plant adjacent to an existing boiler plant on the Omaha VA medical center campus. The project scope includes furnishing all labor, materials and equipment to demolish an existing metal shed, construct the new chiller plant building to house two centrifugal chillers and relocate a temporary chiller, with the design to allow for future expansion. The estimated cost is between $10-20 million. Proposals are due on March 8, 2022. The anticipated award date is July 30, 2022, with a 550 calendar day period of performance starting from the notice to proceed. The solicitation is set aside for service-disabled veteran-owned small businesses. The questions and answers provide additional clarification on the proposal requirements and evaluation criteria.

View the file

Other files

File Type Posted
36C26322R0065 0004.docx DOCX document
36C26322R0065 0003.docx DOCX document
Addendum Plan SheetsPart-4.pdf PDF
Addendum specs 040822.pdf PDF
Addendum Plan SheetsPart-2.pdf PDF
Addendum Plan SheetsPart-6.pdf PDF
Addendum Plan SheetsPart-1.pdf PDF
Addendum 040822.pdf PDF
Addendum Plan SheetsPart-7.pdf PDF
Addendum Plan SheetsPart-3.pdf PDF
Addendum Plan SheetsPart-8.pdf PDF
Addendum Plan SheetsPart-5.pdf PDF
Geotechnical Report Terracon no 05215161R01.pdf PDF
HMS VA Omaha 103119.pdf PDF
S02_Specs - Volume 1 revised.pdf PDF
S02_ATTACH - Specs - Volume 2 (1376 pages).pdf PDF
Omaha VA Chiller photos.pdf PDF
S02_ATTACH - Drawings (132 pages).pdf PDF
36C26322R0065 0002.docx DOCX document
36C26322R0065 Final.docx DOCX document
Site Vist Sign In sheet.pdf PDF
36C26322R0065.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

636-22-4-5988-0002

636-18-304 36C263

Department of Veterans Affairs Network 23 Contracting Office (NCO 23) 111 South 18th Plaza, Suite C38 Omaha NE 68102-2077

36C263

Department of Veterans Affairs Network 23 Contracting Office (NCO 23) 111 South 18th Plaza, Suite C38 Omaha NE 68102-2077 To all Offerors/Bidders

36C26322R0065 03-22-2022

X

X

X March 12, 2022 at 2:00 pm CDT

636-3620162-5988-854200-3220 23NR9WA20

Project: 636-18-304, Construct Combined Energy Plan Phase 1 (Chiller Plant), Omaha, Nebraska VA Contracting POC: Sharon Spohn, Phone: 402-996-3522, Email: sharon.spohn@va.gov

A. This amendment is issued to provide answers/questions and post the sign in sheet.

B. The questions/answers provided at the site visit are on page 2.

C. The list of attendees at the site visit are attached.

Sharon Spohn NCO 23 Contracting Officer

VA-VHA-2020-645FFEAB

Questions-Answers – 22 March 2022

No.
Questions
Answers
1.
On page 8 of 96, “15. SOLICITATION QUESTIONS” it says that “Questions will be accepted up to the close of business 2:00 pm March 2, 2022. What is the correct date?

The correct question due date is at 2:00 pm on March 30, 2022.

2.
On Page one of the SF 1442, should it be “550 calendar days after receiving award” or “520 days after receiving notice to proceed?”
Both are actually correct with the assumption of taking 30 calendar days after award to get bonding and hold the pre-construction meeting. For all contractual items use: “520 calendar days after receiving Notice to Proceed.”
3.
SF 1442 Block 13.d identifies our bids to be valid for 90 days. Solicitation Page 9 Paragraph 21 notes Funds are not presently available and continues with “The Government anticipates funds will become available by September 30, 2022. Despite submitting proposal on the current bid date or a later bid extension date, the bids will expire before September 30, 2022. With inflation and material shortages and inability to hold pricing for long periods, how does the government plan to address the delay in making award until end of Fiscal Year?

This is a good question… The funds are not currently on site, but they will do the best to get them within 90 calendar days. If we have to, we will issue amendments to all of the contractors who submitted proposals to accept an extension of acceptance period and provide a new proposal, if needed.

4.
Factor 1- Experience. Will the government accept Design Build projects for complete replacement of multiple chillers at VA Campus that included complete removal and replacement of multiple chillers, piping, circulation pumps, controls and retrofit concrete basin cooling tower with values less than $5M?

We will not tell you what to put in your proposal – put your best foot forward. This is best value. You need to present a package that shows that you can do similar work. If it is not similar, it may still be taken into consideration – just not rated as high. We recognize that this project is for $20M and several SDVOSB’s may not have experience over $10M.

5
Factor 4- Draft Schedule. This factor requires schedules to assume an award date of July 30, 2022. This presumes construction activities will begin according to this measure and impacts cost assumption. If award as stated in Paragraph 21 does not happen until end of Fiscal Year, added costs may be required due delayed start and Winter work. Please clarify how this condition will be addressed if award is delayed per Paragraph 9?

This schedule is for comparison purposes only. This is to show you know what steps are required. How much have you thought out the process? Once awarded, a revised firm schedule will be required.

Keep in mind, with an assumption of award date on July 30, 2022, that also assumes that the Notice to proceed will be issued on August 30, 2022.

6.
Solicitation Page 16. No deductive Alternates are listed on the Bid Schedule. Does the government plan to issue Deductive Alternative schedule of options should the Base project exceed the undefined government budget should all proposals exceed the limit forcing Solicitation cancellation?

There are no deduct alternatives on this project.

See attached document: Site Visit Sign In (2 pages).