This document provides details on a federal contract opportunity for emergency department expansion services at the Salt Lake City VA Medical Center. The contractor will be required to provide all materials and labor to construct an 18,500 square foot addition and renovate 4,000 square feet to expand the emergency department and support areas. The scope of work includes architectural, civil, electrical, mechanical, and structural design and construction services. The project budget is between $10-20 million. This opportunity is designated as a 100% set-aside for service-disabled veteran-owned small businesses. Offerors must be verified and listed in the Vendor Information Pages database to be considered for award. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8'

EV2

EV3

E26A

P R O

TE

C

T EXISTIN

G

AD

JO

IN

IN

G W

ALLS

, FLO

O R S

S

TR

U C

TU

R

E,SYSTEM

S A N D R

O O

F FR

O M

D

AM

A G E

EXIT

EXIT

EXIT

1' - 3"

APPROX. F.V.

93' - 5"

APPROX. F

.V

APPROX. F

.V

9'

- 6

APPROX. F.V.

44' - 0"

8 8

GENERAL NOTES - DEMOLITION

A. CONTRACTOR SHALL VISIT SITE PRIOR TO BIDDING IN ORDER TO BECOME FAMILIAR WITH

ALL EXISTING CONDITIONS.

B. ALL ITEMS TO BE SALVAGED FOR RE-USE OR TO OWNER ARE TO BE PROTECTED AND

REMOVED AND RE-INSTALLED WITHOUT DAMAGE.

C. ALL DEMOLITION DEBRIS, TRASH, AND/OR REMOVED ITEMS SHALL BE HAULED OFF SITE AND

DISPOSED OF IN A LEGAL MANNER.

D. SEE CIVIL DRAWINGS FOR CIVIL INFORMATION.

E. SEE MECHANICAL DRAWINGS FOR MECHANICAL INFORMATION.

F. SEE ELECTRICAL DRAWINGS FOR ELECTRICAL INFORMATION.

G. SEE PLUMBING DRAWINGS FOR PLUMBING INFORMATION.

H. CONTRACTOR SHALL REPAIR TO EXISTING CONDITION ANY EXISTING FINISH DAMAGED

DURING DEMOLTION OR CONSTRUCTION.

I. PRIOR TO START OF DEMOLITION MEET W/ OWNER TO SELECT ALL ITEMS TO BE SALVAGED.

J. DEMOLISH, REMOVE, AND DISPOSE OF ALL ITEMS SHOWN DASHED ON DEMOLITION PLAN.

INCLUDE ALL RELATED UTILITIES AND ACCESSORIES.

K. CONTRACTOR TO VERIFY ALL EXISTING CONSTRUCTION AND DIMENSIONS - IF CONDITIONS

VARY FROM DRAWINGS NOTIFY THE ARCHITECT.

L. CONTRACTOR SHALL REPAIR TO LIKE NEW CONDITION ANY EXISTING FINISH DAMAGED

DURING DEMOLITION OR CONSTRUCTION.

M. EXISTING ROOFING SYSTEM IS A FULLY ADHERED PVC SYSTEM. ALL REPAIRS SHALL BE

PERFORMED BY A CERTIFIED INSTALLER IN ACCORDANCE W/ MANUFACTURERS

REQUIREMENTS IN ORDER TO MAINTAIN WARRANTY.

N. CONTRACTOR SHALL BE FULLY RESPONSIBLE TO PROTECT THE EXISTING BUILDINGS, FROM

ANY WATER PENETRATION OR ASSOCIATED DAMAGE DURING THE ENTIRE COURSE OF

DEMOLITION AND CONSTRUCTION. INCLUDED ALL NECESSARY PRECAUTIONS & MEASURES IN

THE BASE BID.

O. SEE SITE DEMOLITION PLAN FOR SITE ELEMENTS.

P. SALVAGE ALL DOOR HARDWARE TO VA LOCKSMITHS

Q. GENERAL CONTRACTOR IS RESPONSIBLE TO REMOVE ALL HAZARDOUS MATERIALS IN

ACCORDANCE WITH SPECIFICATION SECTION 02 8212.19

TRACY D.

STOCKING

NO.

135781

S

T A

E OF U

H

TAT

A R C H I T

E C

TL

IC

E

N S E D

A

B

C

D

E

F o n e e ig h t in c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

F

IN

A L C

O N

S T

R U

C T

IO

N

D O

C U

M E

N T

S

CONSULTANTS: ARCHITECT / ENGINEERS: SEAL:

Revisions: Date:

Drawing Title

Approved: Project Director

Project Title

Location

Date Checked Drawn

Drawing Number

Building Number

Project Number

Dwg. _____ of _____197

8/11/2015

URGENT CARE AND SUPPORT EXPANSION

VAMC SALT LAKE CITY, UTAH 84148

Banks Fredrickson

660-332

AD101

LEVEL 1 DEMOLITION PLAN

08-11-2015

3/32" = 1'-0"AD101

1 LEVEL 1 DEMOLITION

DEMOLITION KEYED NOTES

1 DEMOLISH EXISTING BUILDING COMPLETELY, INCLUDING, BUT NOT LIMITED TO DOORS,

WINDOWS, WALLS, COLUMNS, TUNNEL SYSTEMS, FOUNDATIONS (EXCEPT WHERE CALLED

OUT TO REMAIN), ROOFING AND PARAPET, ETC.

2 PARTIALLY DISASSEMBLE AND MODIFY EXISTING CURTAIN WALL SYSTEM TO

ACCOMMODATE NEW CONSTRUCTION. SEE STRUCTURAL.

3 REMOVE TUNNEL SYSTEMS SHOWN SHADED COMPLETE. TUNNEL FOUNDATION SYSTEMS

ARE APPROXIMATELY 4' WIDE X 5' DEEP WITH 6" WIDE STEM WALLS AND A 6" SLAB AT

TUNNEL BOTTOM

4 DEMOLISH WALL

5 REMOVE DOOR, FRAME AND HARDWARE COMPLETE

7 PROTECT IN PLACE EXISTING BRIDGE. MODIFY CURTAIN WALL SYSTEM @ BRIDGE TO

ACCOMODATE NEW ROOFING SYSTEM. SEE WALL SECTION FOR TIE-IN HEIGHTS &

DETAILS.

8 PROTECT IN PLACE EXISTING COLUMN, FOUNDATION SYSTEM AND BEAM ABOVE

9 CUT NEW OPENING IN EXISTING WALL. TRIPLE WYTHE BRICK WALL TO ACCOMMODATE

NEW DOOR WAY

10 DO NOT REMOVE FOUNDATION SYSTEM AT THIS AREA.

11 DEMOLISH SINK AND CASEWORK

12 CHASE FOR ROOF DRAIN PIPING -PROTECT IN PLACE

14 CUT NEW OPENING FOR DOOR IN EXISTING WALL. SEE FLOOR PLANS AND DOOR

SCHEDULE.

15 DEMOLISH WINDOW

16 SYSTEMS FURNITURE SALVAGE TO OWNER.

17 DEMOLISH/MODIFY ACOUSTICAL LAY-IN CEILING AS NECCESSARY FOR NEW WORK

18 DEMOLISH/MODIFY FLOORING AS NECCESSARY FOR NEW WORK

19 FIRE EXTINGUISHER CABINET REMOVAL AND SALVAGE FOR REUSE

20 1 HOUR CONSTRUCTION BARRIER FROM SLAB BELOW TO SLAB ABOVE. EXISTING WALLS

CAN BE USED AS CONSTRUCTION BARRIERS IF THEY MEET THE 1 HOUR AND

SLAB-TO-SLAB CRITERIA, OR CAN BE MODIFIED TO MEET IT.

21 DEMOLISH EXISTING SLAB

22 REMOVE A PORTION OF THE ACOUSTICAL LAY IN CEILING AS NECESSARY FOR NEW

CONSTRUCTION

23 REMOVE A PORTION OF VCT FLOORING AS NECESSARY FOR NEW CONSTRUCTION

24 ALL EXISTING FINISHES TO REMAIN

26 SAW CUT FLOOR FOR NEW DUCT WORK

REF SHEET:NOT TO SCALE

KEYPLAN - ADDITION

N O R T H

SEE ALTERNATE 'H' ON SHEET AE001

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. of

Revisions: Date

CONSULTANTS:

VAMC, Salt Lake City, UT 84148

ARCHITECT/ENGINEERS:

VAMC Urgent Care Addition

2015-01-12

B.04

Office of

Construction and Facilities

Management

1490 S. Price Road, Suite 302, Chandler, AZ 85286 office: (480) 244-3355 www.engineeredwithlayton.com

F I N

A L

C

O N

S T

R U

C T

I O

N

D

O C

U M

E N

T S

SEAL:

324 S. State St., Suite 400

Salt Lake City, UT 84111

800-678-7077, 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

2766 S. Main Street

Salt Lake City, Utah 84115 801.355.5656 bhb@bhbengineers.com

BUILDING 4 - PARTIAL DEMOLITION FLOOR PLAN

SCALE: 1/8" = 1'-0"

ENLARGED - PARTIAL BUILDING 4 - DEMOLITION FLOOR PLAN

SCALE: 1/4" = 1'-0"

FLOOR LEGEND

DEMOLITION KEY NOTES

GENERAL NOTES

ENLARGED - PARTIAL BUILDING 4 - DEMOLITION REFLECTED CEILING PLAN

SCALE: 1/4" = 1'-0"

AD101
Sheets
AD101 - LEVEL 1 DEMOLITION PLAN
AD102
AD102A
AE100
AE101
AE101A
AE101B
AE101C
AE101D
AE102
AE103
AE141
AE141A
AE141B
AE141C
AE141D
AE161
AE201
AE202
AE301
AE302
AE303
AE304
AE305
AE451
AE452
AE453
AE454
AE455
AE456
AE501
AE502
AE510
AE530
AE540
AE550
AE551
AE560
AE561
AE570
AE571
AE572
AE581
AE582
AE601
AE602
AI101
AI501
AI601

File details come from the government source that posted it. Updated .