This document is an amendment to a federal solicitation providing key details for a construction project to replace four elevators at a Veterans Affairs medical center. The project involves general construction work including replacing the hoistways and entrances for elevators P-14, P-15, and P-11 under the base bid. Add alternates include replacing elevator S-12 under Alternate 2 and replacing oil/water separators for the elevators under Alternate 3. The amendment addresses questions from potential offerors, clarifies scope details, and revises the pricing schedule. Offerors must bid all line items with a 365-day period of performance. The Department of Veterans Affairs is the contracting agency.

View the file

Other files

File Type Posted
36C25722B0027 0011.docx DOCX document
36C25722B0027 0010.docx DOCX document
36C25722B0027 0009.docx DOCX document
Supplemental Information.pdf PDF
36C25722B0027 0008.docx DOCX document
36C25722B0027 0007.docx DOCX document
IMG_0415.pdf PDF
36C25722B0027 0006.docx DOCX document
36C25722B0027 0005.docx DOCX document
IMG_0416.jpg JPG image
36C25722B0027 0004.docx DOCX document
Sign-in-Sheet Pre-Bid Site Visit.pdf PDF
36C25722B0027 0003.docx DOCX document
VAAR 852.236-92.pdf PDF
Door Controller DC1000 Data Sheet.pdf PDF
Dwg 6 Cfig 6 Selective Elevator Monitor Inside of Elev Rev3.pdf PDF
Pre Bid - Sign In Sheet.pdf PDF
36C25722B0027 0001.docx DOCX document
36C25722B0027_2.docx DOCX document
VA AM Elevator Replacement 100 CD Specifications.pdf PDF
VA AM Elevator Replacement 100 CD Drawings 04192022 SM.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 08-03-2022 671-20-128 Department of Veterans Affairs Network Contracting Office, NCO17 2002 Scott Blvd.

Temple TX 76504 Department of Veterans Affairs Network Contracting Office, NCO17 2002 Scott Blvd.

Temple TX 76504 To all Offerors/Bidders

36C25722B0027

X X X

See continuation on Page 2:

Joyce Mills Contracting Officer A. Amendment 0002 is issued to provide the following:

· Consolidated RFIs with responses

· Revised Schedule B-Add Alternates 8-3-2022

· Door Controller DC 1000 Data Sheet

· Dwg 6 Cfig 6 Selective Elevator Monitor Inside of Elev Rev3 B. General Requirements, 1.3 STATEMENT OF BID ITEMS, is changed to read as follows:

1.3 Statement of Bid Items(s)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, replacement or necessary removal of existing structures and construction and certain other items. Work to include refurbishing door frame surrounds to like new condition.

B. ADD ALTERNATE NO. 1: Add to REPLACE Elevators P-14, P-15 and P-11 Hoistway and entrance assembly C. ADD ALTERNATE NO. 2: Add to REPLACE Elevator S-12 D. ADD ALTERNATE NO. 3: Add to REPLACE THE OIL/ WATER SEPARATORS FOR Elevators P-14, P-15, P-11 and S-12

C. VAAR Provision 852.236.92 is hereby incorporated in full text (see attached).

Consolidated RFIs 36C25722B0027:

1. Alternate #1 and CLIN 0004 per Amendment #1 Bid Schedule is identified as ‘Deduct’. Replacing elevator hoistway entrances rather than refurbishing them would result in an additive price. Request bid form for Alternate #1 & CLIN 0004 be revised to read ADDITIVE alternate instead of Deduct.

A: See Revised Schedule B 8-3-2022

1. Detail 1/AS200 Rear Elevation detail for elevator P11 appears to be a depiction of a front elevation and is missing keynotes. Please verify elevation for Detail 1/AS200 and provide keynotes. Assume the rear elevation should receive a keynote 24. Please confirm.

A: Detail 1/AS200 Rear Elevator detail for elevator P11 should have elevation/section key note 19 and 10 applied to it. Key note 19 in for the stainless steel elevator doors

1. There is insufficient detail on what is required regarding the embossed corian for the walls of P11 elevator. We’ve been told that this is a very expensive finish option to the cost of the elevator. Please confirm corian with logos and words is intended for P11 elevator location or if finishes used in P14 and P15 elevators are acceptable in lieu of corian with logos and words.

A: The details for the P11, P14, and P15 shows a solid surface panels not necessarily corian

4. Is replacing the sling and platform necessary or can it be saved for value engineering?

A: The contractor can provide a proposal request to provide this as an option.

5.Upon review of the provided documents, it appears that the specifications were written for theinstallation of a new elevator and not the modernization of the existing cars. This specificationcannot be used for this project and will not allow prospective bidders to accurately quote the job.Will the VA please provide a revised specification that describes the modernization of theelevators rather than the installation of new ones.
A: See Section 14 24 00, 1.1, A update to read:

This section specifies the engineering, furnishing, installation and renovation of the electric hydraulic elevator systems as describe herein and indicated on the contract drawings.

See the Sheet Key Notes for refurbishing options and directives.

6.. Period of Performance: With as many supply-chain issues that the construction industry is facing,please allow for long lead items to be delivered prior to issuing a Notice to Proceed. Otherwise, a360-day performance period will not be sufficient considering the phasing for P-14 and P-15 elevators.
A: Due to the CLC building still being occupied P14 and P-15 cannot be done at the same time.Please planed delivery dated accordingly

7.. Project Design: Is this a design-build project?

A: This is not a design-built project. The contract will be required to submit shop drawings

8.. Floor to floor dimension: What is the dimension from finish floor to the underside of deck aboveat each floor? Please provide elevation drawings for the floor level that incorporates theinterstitial and pipe space l levels.
A: There is no interstitial space for the elevators. Elevator P14 and P15 are in the CLC with oninterstitial. Elevator P11 and S12 are in areas of the main building without and interstitial.
9.. HVAC Controls: Will the new HVAC equipment need to be tied into the hospital BAS or is it alllocal?Please provide the company name of the required HVAC controls contractor if BASintegration is required.
A: The equipment rooms will tie into the BAS. Use Entech Sales and Service
10. Fire Alarm: Please provide the company name of the fire alarm contractor that provides servicesto the VA.
A: Use Firetrol Protection System
11. Fire Alarm Design: The notes on the plans referencing FA work are brief and lack details. Isthere an equipment schedule or additional clarifications? The specifications don’t appear to bejob-specific either. Please clarify exactly what needs to be done to the existing FA systemfor thisproject.
A: The fire sprinkler should be installed to meeting the ASME A17.1 2019
12.. Differing Site Conditions or Discrepancies: If a differing site condition or discrepancy in thedesign documents is found after bidding the project, please confirm that the VA will handle thisas a ‘change’ to the contract.
A: changes to the project will be handle by the FAR changes clauses
13. Section 013526-14, para 1.7: Normally on VA projects, a superintendent can perform SSHOduties in addition to Quality Control Manager duties. Due to its relatively small size, is thatacceptable on this project? This will save the VA a considerable amount of money.
A: The contractor can bundle multiple roles into the same person, but the contractor must state soin writing.
14. Section 013526-16, para 1.9B: Is a Certified Safety Professional monthly inspection required orcan thesuperintendent perform this work?
A: The superintendent can provide the monthly inspection only if the contractor in writing thatthe person is designated the Certified Safety Professional.
15. Warranty and Service: Please confirm that the elevator contractor is supposed to warrantymaterial and installation, along with service the elevators for a period of one year.
A:The VA exist service contractor will not provide maintenance service for the elevator duringthe installer Warranty service period.

16. Section 010000, 1.19: Is professional photography required on this project?

A: professional photos are required, but only for elevator P14 and P15.
17. Infection Control Barriers: Are the barriers to be installed as shown on the drawings or asdescribed in the specification. They differ in some respects. See section 013526-28, para 1.14D.A: provide infection control barriers are in drawing and specs. The differ that would not be usedfor the specs on page 013526-28 in the treated plywood. Please don’t use wood products toconstruct the temporary construction partitions
19. Negative Air Machines: Is negative air required in each work area? If so, the infection barriersprovide a rather small work area that will likely not allow for a machine. Please clarifywhat isto be done.
A: Negative air is required for the project. The intend is to have the elevator hoist way in an negative air environment. Despite the small work area, negative air is intendent to include the volume of air in the elevator hoist.
20. Negative Air Temporary Duct: If negative air is required, where do contractors exhaust the air?These areas are not likely to have existing exhaust duct nearby.
A:negavtive air is required. Exhaust air though a window or roof.
21. Testing Laboratory: What work items require the testing lab involvement? If this is in referenceto new concrete equipment pads is it necessary?
A: The VA will provide a concrete testing lab.
22. VA Storage Items: Will the VA remove all storage items that are in the work area beforecontractors mobilize? During the site visit there were multiple work areas that containedsubstantial amounts of storage items. Work cannot occur in those locations until they have beencleared.
A: The VA will move government equipment and items not related to the elevator project for the contractor being work.
23. GI-103, Detail #2 - Infection Control Door Card Reader: Is a card reader required or can thecontractor provide door hardware sets that work with the VA AAAJ keys?
A: There is no card reader required to access the work site. To access the work site pleaseprovide a Schlage CO-100 cypher lock. The lock is to be turn over to the VA after project.
24. GI-103, Detail #2 – Triatek Monitor: Is this required? If so, does the VA have more informationon this equipment so contractors know what to provide?
A: use TriaTek FMS-1655 pressure monitor that will continuously monitor room pressure to thelife span of the project.
25. WanderGuard Equipment Integration: What does this consist of? The plans and specs aresomewhat vague. Please have the WanderGuard manufacturer provide specifics on what we haveto do.
A: please see Dwg 6 – Cfig 6 – Selective Elevator Monitor @ Inside of Elev Rev3.pdfAnd Door Contoller DC 1000 Data Sheet.pdf
26. Fire Sprinkler System: Is there any fire sprinkler work required other than what is shown in theplumbing drawings? There are a few fire suppressions notes on the plumbing drawings yet thegeneral fire protection notes on drawing PP-001 place the accuracy and burden of the fireprotection design on the contractor. Note 3. States: ‘Sprinkler head layout and piping shall bedesigned and installed…’. Again, is this a design-build job? If not, this note should be deleted andthe designer of record should provide this information so contractors know what to bid.
A: The fire sprinkler should be installed to meeting the ASME A17.1 2019
27. ED-101, GN#6: When will overtime, evening, and weekend work be required? Contractorscannot accountfor this work if we do not know when the VA will require it.
A: Work for this project can be done during normal business hours.
28. EP-201, New Breakers: The one-line diagram is showing two new 225-amp 3 pole breakers to beinstalled in existing Switchboard ‘EDP1’. Please provide the manufactures name of theswitchboard along withmodel and serial number and a picture of where in the switchboard thetwo breakers will be installed.
A: A new site visit can be scheduled to find this information. The VA is currently getting the switch gear upgraded.
29. Roof Warranty: Is the existing roof under warranty? If so, what roofing contractor currentlyholds the warranty? Will the requirement to infill and patch the roof void the warranty?
A: The is no roof Warranty left on the CLC roof
28. Roof As-Built Drawings: Please provide the existing roof as-built drawings so contractors knowwhat the construction is.
A: See Sheet MH-201, Details 6 and 7; also see Sheet GI-002, General Notes, Item 5.
30. Non-Proprietary Elevator Equipment: Please confirm that all elevator equipment is to be non-proprietary and serviceable with open-market equipment.
A: The VA confirms the contractor to use Non-Proprietary Elevator Equipment and serviceablewith open-market equipment.
31. Buy-American Equipment: Please confirm that all equipment installed on the project is to meetthe Buy-American clause.
A: Contractor is to comply with all applicable FAR requirements including the “Buy Americanclause”.
32. Deductive Alternate #3: Should CLIN #0013 remove only two oil/water separators if CLIN#0012 already removes elevator S-12 and presumably the third oil/water separator?
A:

SECTION B – SCHEDULE OF PRICES/DESCRIPTION

REVISED 8-3-2022

DESCRIPTION: The contractor shall provide all labor, supervision, materials, and equipment to complete all required project work in strict accordance with the SOW, Specificaitons, and Drawings to Replace Elevators P-14, P-15, P11, and S-12, located at the Audie L. Murphy VAMC 7400 Merton Minter, San Antonio, Texas.

** NOTE: Award shall be made on the Base Bid unless the base bid is less than the allocated funding for the project. If the base bid is less than allocated funding, award shall be made on the basis of a Bid Alternate(s) beginning with Bid Alternate #1 and proceeding through Bid Alternate #3 in order to accommodate allocated funding. Offerors must bid all items in order to be considered.

FAR 36.205 Statutory Cost Limitations states: Solicitations containing one or more items subject to statutory cost limitations shall state - The applicable cost limitation for each affecting item in a separate schedule; That an offer which does not contain separately-prices schedules will not be considered; and That the price on each schedule shall include an approximate apportionment of all estimated direct costs, allocable indirect costs, and profit.

BASE BID:

ITEMUNIT TOTAL
NO. DESCRIPTION OF SERVICEQTYPRICE AMOUNT
0001PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY FOR
GENERAL CONSTRUCTION,
ALTERATIONS, REPLACEMENT OR
NECESSARY REMOVAL OF EXISTING
STRUCTURES AND CONSTRUCTION AND
CERTAIN OTHER ITEMS. WORKTO INCLUDE
REFURBISHING DOOR FRAME
SURROUNDS TO LIKE NEW CONDITION.
AT THE VAMC SAN ANTONIO TEXAS
IN ACCORDANCE WITH THE PROVIDED
SOW, SPECIFICATIONS AND DRAWING(S) TO
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM I)
0002PERFORMANCE AND PAYMENT1 ea$__________ $_________
BONDS

TOTAL (0001 & 0002) $__________

Total number of days for completion: 365 calendar days

BID BASE BID - ADD ALTERNATE #1 + (Base Bid + ADD Alternate #1):

0003BASE BID: PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY FOR
GENERAL CONSTRUCTION,
ALTERATIONS, REPLACEMENT OR
NECESSARY REMOVAL OF EXISTING
STRUCTURES AND CONSTRUCTION AND
CERTAIN OTHER ITEMS. WORKTO INCLUDE
REFURBISHING DOOR FRAME
SURROUNDS TO LIKE NEW CONDITION.
AT THE VAMC SAN ANTONIO TEXAS
IN ACCORDANCE WITH THE PROVIDED
SOW, SPECIFICATIONS AND DRAWING(S) TO
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM I)
0004AND TO INCLUDE ADD ALTNATE #1:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE ELEVATORS P-14, P-15 AND P-11

HOISTWAY AND ENTRANCE ASSEMBLY

LOCATED AT THE VAMC

SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM B)
0005PERFORMANCE AND PAYMENT1 ea$__________ $_________
BONDS

TOTAL (0003, 0004, & 0005) $_________

Total number of days for completion: 365 calendar days

BASE BID - ADD ALTERNATE #2 + (Base Bid + ADD #1 and #2):

0006BASE BID: PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY FOR
GENERAL CONSTRUCTION,
ALTERATIONS, REPLACEMENT OR
NECESSARY REMOVAL OF EXISTING
STRUCTURES AND CONSTRUCTION AND
CERTAIN OTHER ITEMS. WORKTO INCLUDE
REFURBISHING DOOR FRAME
SURROUNDS TO LIKE NEW CONDITION.
AT THE VAMC SAN ANTONIO TEXAS
IN ACCORDANCE WITH THE PROVIDED
SOW, SPECIFICATIONS AND DRAWING(S) TO
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM I)
0007AND TO INCLUDE ADD ALTNATE #1:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE ELEVATORS P-14, P-15 AND P-11

HOISTWAY AND ENTRANCE ASSEMBLY

LOCATED AT THE VAMC

SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM B)
0008AND TO INCLUDE ADD ALTNATE #2:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE ELEVATORS S-12

LOCATED AT THE VAMC

SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM C)
0009PERFORMANCE AND PAYMENT1 ea$__________ $_________
BONDS

TOTAL (0006, 0007, 0008 & 0009) $_________

Total number of days for completion: 365 calendar days

BASE BID-ADD ALTERNATE #3 + (Base Bid + ADD Alternates #1, #2, and #3):

0010BASE BID: PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY FOR
GENERAL CONSTRUCTION,
ALTERATIONS, REPLACEMENT OR
NECESSARY REMOVAL OF EXISTING
STRUCTURES AND CONSTRUCTION AND
CERTAIN OTHER ITEMS. WORKTO INCLUDE
REFURBISHING DOOR FRAME
SURROUNDS TO LIKE NEW CONDITION.
AT THE VAMC SAN ANTONIO TEXAS
IN ACCORDANCE WITH THE PROVIDED
SOW, SPECIFICATIONS AND DRAWING(S) TO
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM I)
0011AND TO INCLUDE ADD ALTNATE #1:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE ELEVATORS P-14, P-15 AND P-11

HOISTWAY AND ENTRANCE ASSEMBLY

LOCATED AT THE VAMC

SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM B)
0012AND TO INCLUDE ADD ALTNATE #2:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE ELEVATORS S-12

LOCATED AT THE VAMC

SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM C)
0013AND TO INCLUDE ADDIONVE ALTNATE #3:
PROVIDE ALL NECESSARY1 JB $________ $_________
LABOR, MATERIALS, AND
EQUIPMENT NECESSARY TO
REPLACE THE OIL/ WATER SEPARATORS FOR
ELEVATORS P-14, P-15, P-11
LOCATED AT THE VAMC
SAN ANTONIO TEXAS IN ACCORDANCE
WITH THE PROVIDED SOW, SPECIFICATIONS
AND DRAWING(S) .
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEM 3)
0014PERFORMANCE AND PAYMENT1 ea$__________ $_________
BONDS

TOTAL (0010, 0011, 0012, 0013 & 0014) $_________

Total number of days for completion: 365 calendar days

See attached document: Door Controller DC1000 Data Sheet.

See attached document: Dwg 6 Cfig 6 Selective Elevator Monitor Inside of Elev Rev3.

See attached document: VAAR 852.236-92.

Replace Elevator P-14, P-15, P-11 & S-12, Project No. 671-20-128