This is Amendment 3 to Solicitation 36C25526R0159 for the installation of a dedicated pharmacy air handler at a Department of Veterans Affairs facility (Project 589A4-25-102), issued by the VA Network Contracting Office in Leavenworth, Kansas. The amendment extends the deadline for receipt of offers to September 11, 2026 at 2:00 PM CDT and provides revised contract documentation to all offerors and bidders.
The primary purpose of this amendment is to furnish three sets of revised drawings (Parts 1, 2, and 3) that replace the original drawings submitted with the initial solicitation, along with a pre-bid sign-in roster. The amended drawings do not override previous amendment documents (Amendment 2). Offerors must acknowledge receipt of this amendment prior to the extended submission deadline through one of three methods: completing and returning the amendment form, acknowledging receipt on each copy of the offer submitted, or providing separate written or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt by the specified deadline may result in offer rejection.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 07 81 00 Applied Fireproofing.pdf | ||
| 36C25526R0159 0004.pdf | ||
| Final Drawings Part-3.pdf | ||
| Final Drawings Part-1.pdf | ||
| Final Drawings Part-2.pdf | ||
| PRE-BID SIGN IN ROSTER.pdf | ||
| 07_8100-001_Fireproofing_Mfr_Literature.pdf | ||
| 589a4-25-102_Addendum 02_260828.pdf | ||
| 01 00 00 General Requirements RX.pdf | ||
| 36C25526R0159 0002.docx | DOCX document | |
| Finish schedule from drawings.pdf | ||
| 01 33 23- Shop Drawings Product DAta and Samples.pdf | ||
| finish schedule from specs.pdf | ||
| 01 00 10 - MEDICAL CENTER REQUIREMENTS RX.pdf | ||
| Phasing info.pdf | ||
| 01 32 16-15 Project Schedules RX.pdf | ||
| 01 91 00 General Commissioning Requirements RX.pdf | ||
| 36C25526R0159 0001.docx | DOCX document | |
| S02-Final Specifications 1068 pages.pdf | ||
| 36C25526R0159.docx | DOCX document | |
| P09-Final Drawings Part-2 Pages 37.pdf | ||
| P09-Final Drawings Part-1 Pages 37.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 08-31-2026 589A4-25-102 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 To all Offerors/Bidders
36C25526R0159
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 09-11-2026 2PM CDT Install Dedicated Pharmacy Air Handler, 589A4-25-102
The purpose of this modification is to provide the following documents:
a. Revised drawings Part 1, Part 2 and Part 3. These drawing replace the original drawing submitted with the Solicitation. These drawings do not override amendment 2 documents.
b. Pre-Bid sign in roster.
CONTINUATION PAGE
See attached document: PRE-BID SIGN IN ROSTER.
See attached document: Final Drawings Part-1.
See attached document: Final Drawings Part-2.
See attached document: Final Drawings Part-3.
Amendment 3 - 36C25526R0159- Install Dedicated Pharmacy Air Handler -589A4-25-102
File details come from the government source that posted it. Updated .