RFI 1-27 - Valiant Construction - Questions with Answers.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Z2DA--657-20-101JB FCA-Renovate Space for Whole Health Clinic
Solicitation number
36C25522R0058
Issued by

About this file

This document is a table containing questions and answers related to federal contract solicitation number 36C25522R0058 to renovate space for a Whole Health Clinic at the Jefferson Barracks VA Medical Center in Louisville, KY. The solicitation is seeking a contractor to complete renovations of approximately 11,318 square feet, including demolition, structural alterations, and mechanical, electrical and plumbing work. Bid and RFI due dates have passed, with an award notice expected within 30 days of selection and work to be undertaken during normal business hours. The selected contractor will be required to coordinate with the VA to use the Procore project management software, provide a designated parking and storage area on site, and participate in commissioning with the VA's third party agent. Hazardous material reports were previously conducted and tax exemption certificates will be provided. Clarification was also provided on systems requirements, including for fire alarms, nurse call, and structural steel.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Project Title:Renovate Space for Whole Health ClinicCity/State:Louisville, KY
Solicitation #:36C25522R0058Phone #:615-294-0006
Project Loc.Jefferson Barracks VA Medical CenterTo:Maria Hoover - CO
Bid Date:Office:NCO 15
RFIs Due:Address:3450 S. 4th Street Trafficway
Updated:City/State:Leavenworth, KS
RFI #Description:RFI From:Date Submitted:Spec / Plan
Section:Reply Needed:Date Answered:
1Will the owner accept the use of the industry leading Procore Project Management software as the primary submittal and data
tracking tool for this project?Valiant4/20/22Generalyes5/17/22
2Where will the designated parking & laydown area be for workers
accessing the construction site?Valiant4/20/22ParkingVA Response Required. Drawing A-002 shows Conex storage location and vicinity parking locations.5/17/22
3Does the contract includes liquidated damages? If the owner temporarily shuts down or suspends the project (i.e. for noise), will
extended general conditions cost and time be added to theValiant4/20/22LDno5/17/22
4We anticipate certain construction activities to generate high levels
of noise. Please confirm that only the Contracting Officer can suspend work via written notification to the Contractor.Valiant4/20/22Generalyes5/17/22
5Has the entire work area been checked for asbestos, lead based
materials and/or other hazardous materials? Is there a reportValiant4/20/22AbatementA comprehensive asbestos, lead and mold inspection was conducted of all accesible areas within the project limits. I believe the inspection report would have been included in the bid package.5/17/22
6Is this project tax exempt, and will the CO/COR provide the
necessary tax exempt certificatesValiant4/20/22Taxyes, the tax exemption certificate will be issued on the pre-construction conference.5/17/22
7The Contracting Officer will then NTP to the awardee after the contract award is made. What is the approximent duration between
issuing the award and issuing the NTP?Valiant4/20/22NTPwithin 30 day from award5/17/22
8Will owner require GC’s to develop and submit coordination
drawings in Revit?Valiant4/20/22GeneralVA Response Required
9Can the owner please provide a single drawing that clearly states floor to ceilings hieights for the construciton area? This is used to
ensure that the above ceiling utilities will fit in the above ceilingValiant4/20/22GeneralDrawing S-301 shows floor to floor heights and graphically illustrates both the floor slab and existing concrete beams. Ceiling heights are listed on AC112
10Will the contractor be authorized to build a temporary office inside
the space in lieu of renting an office trailer for the duration of theValiant4/20/22GC Temp OfficeVA Response Required
11What is the approximate Square Footage of the project? Please confirm that the space will be free from debris and free standing
medical equipment, office supplies, etc.Valiant4/20/22SF11,318 s.f. VA Response Required
12Please confirm that the project is to be completed during normal
working hours, not nights and weekends.Valiant4/20/22Working HoursVA Response Required
13Is AISC (American Iron and Steel Certification) required for the
structural steel fabrication and/or erection for this project?Valiant4/20/22SteelSee Specification Section 05 12 00 STRUCTURAL STEEL FRAMING for fabrication and installation requirements.5/17/22
14Are any expansion joints required for this project?Valiant4/20/22Expansion JointsNo
15Please confirm that the owner will be contracting directly with a third- party commisioning agent for commisioning the project and that the Contractor is only to include partcipation/coordination with the
Commissioning Agent.Valiant4/20/22CommissioningProvide commissioning as specified5/17/22
16What is the current nurse call system manufacturer?Valiant4/20/22Nurse CallContractor to provide the West Com nurse call system as specified, Local STL Communications, Mr. Scott Mosler, scottm@stlcom.com, 314-205-7105, 515-895-47855/17/22
17Who is the owners's service provider for the fire alarm system? Can
you please provide contract information?Valiant4/20/22Fire AlarmVA Response Required
18Please confirm that the owner will provide fire watch during the
period of time that the fire supression system is not in service.Valiant4/20/22Fire WatchContractor to provide.
19Can a floor plan for the first floor be distributed for coordination of demolition and put back on the floor below?Valiant4/20/22PlumbingPlumbing work located on the First floor is identified on the Secod Floor plans. A First Floor Plan can be provided for reference. Contact the VA COR for plans of the recently renovated First Floor East wing.5/13/22
20Are any of the above floors relying on waste or supply lines that are
being called to be removed?Valiant4/20/22PlumbingWe do not anticipate that any floors above are relying on the sanitary piping being removed.5/13/22
21Page 1 of solicitation states names of two people to email
submission to and then on page 9 we are given two other different individuals. Can we confirm who shall be receiving the submission?Valiant4/20/22ProposalPlease refer to amendment 2 to the solicitation5/17/22
22Are there any page limitations or format required?Valiant4/20/22ProposalNo5/17/22
23Do we need to include Reps and certs in the price proposal?Valiant4/20/22Proposalno5/17/22
24Will you allow CPARS in Lieu of PPQ or with first page of PPQ filled
out?Valiant4/20/22ProposalCPARS or PPQ is accepted5/17/22
25Please confirm that VV is owner supplied and installed and CC is
Contractor supplied and installed.Valiant4/20/22I-601CORRECT5/13/22
26Please confirmed the work requirements for work needed to be
done on the 1st floor. Hour restrictions? Containment requirements?Valiant4/20/22GeneralVA Response Required
27Can an ICRA plan be provided for the first floor?Valiant4/20/22ICRAICRA measures shown on documents. Above ceiling work on First floor to be in mobile carts - coordinate with COR5/17/22
28Valiant
29Valiant
30Valiant
31Valiant
32Valiant
33Valiant
34Valiant
35Valiant
36Valiant
37Valiant
38Valiant
39Valiant
40Valiant
41Valiant
42Valiant
43Valiant
44Valiant
45Valiant
46Valiant
47Valiant
48Valiant
49Valiant
50Valiant
51Valiant
52Valiant
53Valiant
54Valiant
55Valiant
56Valiant
57Valiant
58Valiant
59Valiant
60Valiant
61Valiant
62Valiant
63Valiant
64Valiant
65Valiant
66Valiant
67Valiant
68Valiant
69Valiant
70Valiant
71Valiant
72Valiant
73Valiant
74Valiant
75Valiant
76Valiant
77Valiant
78Valiant
79Valiant
80Valiant
81Valiant
82Valiant
83Valiant
84Valiant
85Valiant

File details come from the government source that posted it. Updated .