This document is an infection control risk assessment form for a hospital construction and renovation project. The form outlines a 14-step process for identifying the class of precautions required based on the type of construction project, patient risk groups affected, and areas surrounding the project. Details include classifying project types from inspection activities to major demolition, determining affected patient risk groups from low to highest, and using a matrix to match project type and patient risk to the appropriate class and level of infection control activities. The form also includes steps to identify the specific site of activity, ventilation and utility issues, containment measures, risks of water damage, work hours, isolation room capacity, hand washing sinks, and responsibility for project monitoring.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Robert J. Dole VA Medical Center Infection Control Risk Assessment for Hospital Construction & Renovation
Please complete the form and return to Infection Prevention & Control.
Project Title & Number:
Project Contracting Officer Representative:
Job Site Supervisor:
Area of Work:
Estimated Start Date:
Estimated End Date:
Signatures:
Project COR
Job Site Supervisor
Infection Prevention & Control
Published in Environment of Care® News, Joint Commission Resources, 2021.
File Name: Infection Control Risk Assessment for Hospital Construction and Renovation
© 2021 The Joint Commission. May be adapted for internal use. Page 1 of 5
Infection Control Risk Assessment for Hospital Construction and Renovation
Health care facilities work to keep individuals healthy. When an organization begins a construction, renovation, or demolition project, it needs to assess the risks to its infection prevention and control efforts. This infection control risk assessment matrix can help organizations identify what steps need to be taken to ensure the health of the individuals served.
STEP 1 Using the following table, identify the type of construction project activity (Types A–D).
Write the type of activity on the line provided below.
TYPE A
Inspection and noninvasive activities Includes but is not limited to the following:
• Removal of ceiling tiles for visual inspection only (for example, limited to one tile per 50 square feet)
• Painting (but not sanding)
• Wall covering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls or access to ceilings other than for visual inspection
TYPE B
Small-scale, short-duration activities that create minimal dust Includes but is not limited to the following:
• Installation of telephone and computer cabling
• Access to chase spaces
• Cutting of walls or ceiling where dust migration can be controlled
TYPE C
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies Includes but is not limited to the following:
• Sanding of walls for painting or wall covering
• Removal of floor coverings, ceiling tiles, and casework
• New wall construction
• Minor ductwork or electrical work above ceilings
• Major cabling activities
• Any activity that cannot be completed within a single work shift
TYPE D
Major demolition and construction projects Includes but is not limited to the following:
• Activities that require consecutive work shifts
• Activities that require heavy demolition or removal of a complete cabling system
• New construction
STEP 1. ___________________________________________________________________________________
STEP 2
Using the following table, identify the patient risk groups (low–highest risk) that will be affected.
If more than one risk group will be affected, select the higher-risk group. Write the group(s) on the line provided below.
LOW RISK MEDIUM RISK HIGH RISK HIGHEST RISK
• Behavioral therapy or counseling rooms
• Common areas
• Conference rooms
• Offices
• Cardiology
• Echocardiography
• Endoscopy
• Nuclear medicine
• Physical therapy
• Radiology/MRI
• Respiratory therapy
• Cardiac care units
• Emergency department
• Labor and delivery room
• Laboratories
(specimen)
• Medical units
• Any area caring for immunocompromised patients
• Burn units
• Cardiac catheterization labs
• Central sterile supply
• Intensive care units
© 2021 The Joint Commission. May be adapted for internal use. Page 2 of 5
• Recreational facilities
• Waiting rooms
• Newborn nurseries
• Outpatient surgery
• Pediatrics
• Pharmacy
• Postanesthesia care units
• Surgical units
• Negative-pressure isolation rooms
• Oncology
• Operating rooms
(including C-section rooms)
STEP 2. ___________________________________________________________________________________
STEP 3 Match the Patient Risk Group (Low, Medium, High, Highest) with the planned Construction Project Type (A, B, C, D) on the following matrix, to find the Class of Precautions (I, II, III or IV) or level of infection control activities required. Class I–IV Precautions are delineated below. Write the class or level in the line provided.
PATIENT RISK GROUP TYPE A TYPE B TYPE C TYPE D
Low-Risk Group I II II III/IV
Medium-Risk Group I II III IV
High-Risk Group I II III IV
Highest-Risk Group II III/IV III/IV IV Note: Infection Prevention and Control department approval will be required when the Construction Activity and Risk Level indicate that Class III or Class IV control procedures are necessary.
STEP 3. ___________________________________________________________________________________
DURING CONSTRUCTION PROJECT UPON COMPLETION
Class I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace a ceiling tile displaced for visual inspection.
1. Clean work area upon completion of task.
Class II
1. Provide active means to prevent airborne dust from dispersing into atmosphere.
2. Water-mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tape.
4. Block off and seal air vents.
5. Place dust mat at entrance and exit of work area.
6. Remove or isolate HVAC system in areas where work is being performed.
1. Wipe work surfaces with cleaner/disinfectant.
2. Contain construction waste in tightly covered containers before transport.
3. Wet mop and/or vacuum with HEPA– filtered vacuum before leaving work area.
4. Upon completion, restore HVAC system where work was performed.
© 2021 The Joint Commission. May be adapted for internal use. Page 3 of 5
DURING CONSTRUCTION PROJECT UPON COMPLETION
Class III
1. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers (that is, sheetrock, plywood, plastic) to seal area from nonwork area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within work site using HEPA–equipped air-filtration units.
4. Contain construction waste in tightly covered containers before transport.
5. Cover transport receptacles or carts. Tape covering unless solid lid.
1. Wipe work surfaces with cleaner/disinfectant.
2. Contain construction waste in tightly covered containers before transport.
3. Wet mop and/or vacuum with HEPA– filtered vacuum before leaving work area.
4. Upon completion, restore HVAC system where work was performed.
Class IV
1. Isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers (that is, sheetrock, plywood, plastic) to seal area from nonwork area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within work site using HEPA–equipped air-filtration units.
4. Seal holes, pipes, conduits, and punctures appropriately.
5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site, or they can wear cloth or paper coveralls that are removed each time they leave the work site.
6. All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.
1. Do not remove barriers from work area until completed project is inspected by the organization’s Safety and IC departments or other leadership and is thoroughly cleaned by the Environmental Services department or other leadership.
2. Remove barrier material carefully to minimize spreading of dirt and debris associated with construction.
3. Contain construction waste in tightly covered containers before transport.
4. Cover transport receptacles or carts. Tape covering unless solid lid.
5. Vacuum work area with HEPA–filtered vacuums.
6. Wet mop area with cleaner/disinfectant.
7. Upon completion restore HVAC system where work was performed.
STEP 4 Identify the areas surrounding the project area, assessing potential impact.
UNIT BELOW UNIT ABOVE LATERAL LATERAL BEHIND FRONT
RISK GROUP RISK GROUP RISK GROUP RISK GROUP RISK GROUP RISK GROUP
© 2021 The Joint Commission. May be adapted for internal use. Page 4 of 5
STEP 5 Identify specific site of activity (for example, patient rooms and medication room).
STEP 6 Identify issues related to ventilation, plumbing, and electrical in terms of the occurrence of probable outages.
STEP 7
Identify containment measures, using prior assessment. What types of barriers (for example, solids walls)? Will HEPA filtration be required?
(Note: Renovation/construction area shall be isolated from the occupied areas during construction and shall be negative with respect to surrounding areas.)
STEP 8 Consider potential risk of water damage. Is there a risk due to compromising structural integrity (for example, wall, ceiling, and roof)?
STEP 9 Work hours: Can or will the work be done during non–patient care hours?
STEP 10 Do plans allow for adequate number of isolation/negative airflow rooms?
STEP 11 Do the plans allow for the required number and type of hand-washing sinks?
STEP 12
Does the infection prevention and control staff agree with the minimum number of sinks for this project? (Verify against Facility Guidelines Institute design and construction guidelines for types and area.)
STEP 13 Does the infection prevention and control staff agree with the plans relative to clean and soiled utility rooms?
STEP 14 Plan to discuss the following containment issues with the project team (for example, traffic flow, housekeeping, debris removal [how and when]).
© 2021 The Joint Commission. May be adapted for internal use. Page 5 of 5
APPENDIX Identify and communicate the responsibility for project monitoring that includes IC concerns and risks. The ICRA may be modified throughout the project. Revisions must be communicated to the project manager.
HEPA, high-efficiency particulate air; HVAC, heating, ventilating, and air-conditioning; IC, infection prevention and control; ICRA, infection control risk assessment
Source: Adapted from Judene Bartley, Epidemiology Consulting Services, Inc. Beverly Hills, MI. © 2002. Updated 2017. May be adapted for internal use.
| Step 3 Response: [ ] |
| Step 1 Response: [ ] |
| Step 2 Response: [ ] |
| Step 6: |
| Step 5: |
| Step 7: |
| Step 8: |
| STEP 9: |
| Step 10: |
| Step 11: |
| Step 12: |
| Step 13: |
| Step 14: |
| Appendix: |
| UNIT BELOW: |
| UNIT ABOVE: |
| LATERAL: |
| LATERAL 2: |
| BEHIND: |
| FRONT: |
| Project Title & Number: |
| Job Site Supervisor: |
| Area of Work: |
| Project COR: |
| Start Date: |
| End Date: |
File details come from the government source that posted it. Updated .