This document provides an overview of a construction project for Electronic Health Records Management Infrastructure Upgrades at the Robert J. Dole VA Medical Center campus in Wichita, Kansas. The project involves near-complete recabling of telecommunications infrastructure across 25 buildings, including replacement of all fiber optic cabling, conduit, and installation of new conduit and fiber. Additional work includes upgrades to telecommunications rooms, security and access control systems, and mechanical, electrical and plumbing systems. Bids are due on February 4, 2022 and shall be submitted electronically to the contracting officer at the Department of Veterans Affairs Veterans Health Administration. A bid guarantee of 20% of the bid price is required with submissions. Upon award the selected contractor must provide payment and performance bonds valued at 100% of the contract amount prior to receiving notice to proceed.
View the file
Other files for this federal contract opportunity
Show all 50
Z2DA--589A7-21-700 EHRM Infrastructure Upgrades has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J A N U A R Y 1 4 , 2 0 2 2
PROJECT 589A7-21-700
EHRM Infrastructure Upgrades - Robert J. Dole VA Medical Center - Wichita, KS
Pre-Bid Site Walk
AGENDA
Introductions
Overview of Project
Project Challenges
Bid Documents Available for use
Bidding Procedures & Close Date
Site Walk
Existing Telecom Room Building 1
INTRODUCTIONS
PROJECT TEAM
VA team –
Department Of Veterans Affairs
VA Medical Center
4101 South 4th Street
Leavenworth, KS 66048
913.946.1126
Sean P. Jackson, Contracting Officer
Sean.Jackson@va.gov
Jon Lutmer – Contracting Specialist
Nicholas Howard – Primary COR
Chris Berry – Day to day Project Oversight
New Telecom room location – Building 2
Triple C Team –
Mat Perkins, AIA – Vice President
Kevin Luke, PE – Engineering Dept Quality Manager
Shannon Pollard Maden, AIA – Architect/Project Manager
Kristy McDermott, NCIDQ – Interior Designer
OVERVIEW OF PROJECT
Project Introduction To prepare the VA campus for EHRM Upgrades, main campus of Robert J. Dole VA Medical Campus will require a near-complete re-cabling of the main hospital and associated buildings.
This project will include all materials and labor to replace all telecommunications cable, outlets, and associated equipment for buildings in this project at the Robert J. Dole VA Medical Campus.
Multiple buildings on campus include Buildings B1, B1A, B1B, B1C, B2, B3, B4, B5, B5B, B6, B7, B11, B12, B13, B16, B19, B20, B21, B26, B29, B34, B59, B60, B61, and B62.
The scope also includes replacement of all fiber optic cabling, conduit and providing new conduit, fiber and manholes serving the buildings' Telecommunications Rooms (TR) in accordance with the drawings and specifications.
Contractor is to coordinate with the Fiber Installer:
Janice Bowers - CHC Consulting 785-806-2828
Areas of work include:
• 25 buildings on campus
• New Fiber Service to all buildings
• New Technology rooms and equipment
• New MEP systems for TR’s
• New Security (PACS) devices
• See Specifications and drawing packages for site and each building.
• ACM/Lead abatement is required, and third-party oversight is mandatory throughout the abatement process.
• The cost of which is part of the contractor's scope. An abatement plan shall be submitted prior to mobilization.
• Third party inspections are required as stated in specification 01 00 00 general requirements.
Cost is paid by Contractor
• Each building shall be a separate CLIN as identified in specification 01 00 00 general requirements. Construction Cost Estimate Breakdowns are provided for each CLIN (Appendix
A to the General Requirements 01 00 00)
• The contractor shall adhere to all Infection Control (ICRA) requirements and shall submit plans prior to mobilization.
• All site activities shall be coordinated with the COR throughout the duration of the project.
• This project must be CERNER compliant per the EHRM program directive.
A commissioning plan and commissioning agent resume shall be submitted with contractor bids.
Commissioning will be phased by building.
• See 01 91 00
• The commissioning agent (CA) shall be a third-party Entity, shall be a professional engineer (PE) experienced, certified and approved by the VA COR. All costs associated with commissioning shall be born By the
Contractor.
• The contractor shall conduct a commissioning plan review at the construction kick off meeting and shall identify roles and
Responsibilities of all individuals. All contact information shall be provided at that time.
New Telecom room location – Building 3
Drawing packages are broken out separately for site and each building.
Some packages are in multiple pdf’s to meet download sizes.
Total of:
• 21 building packages
• 1 site package
• 1 specification (in multiple downloads)
Each package is organized similarly with general information, then information for each discipline.
Architecture sheets show new TR room locations.
At the end of each discipline is a sheet showing Basis of Design equipment items.
For Example - FX900, M900, E900 and
T900 series sheets.
Project Challenges
Project challenges
• The work for all (21) buildings and site work shall be completed in a maximum of 425 days. This will require working on multiple buildings simultaneously with multiple crews to achieve the overall construction period duration for the entire project.
• The entire project must be completed and commissioned prior to the “Go-Live” date for the Cerner software. The station has identified the follow sequence of buildings in terms of priority to be completed.
1. Group 1 (Most Critical) – Buildings 1 & 1B, 3, 5 & 5B, 26, 29, 34, 60, 62
2. Group 2 – Buildings 2, 4, 7, 19, 59, 61
3. Group 3 (Least Critical) – Buildings 6, 11, 12, 13, 16, 20, 21
• Based on the approved schedule by the VA COR (and based on approved Project Schedule and Phasing plan submittals), multiple buildings shall be renovated simultaneously to meet Construction Schedule requirements.
• However, any required shutdowns shall be limited to one at a time to minimize the impact on Facility
Operations.
Project challenges
• The buildings and site shall remain occupied and functional throughout the project.
• All construction is to be performed in one phase during normal working hours as much as feasible. Off-hours premium time is included for noise abatement and utility shutdowns only.
• Shutdowns shall be limited to 8 hours maximum and scheduled for minimal interference with hospital operations.
New Telecom room location – Building 5
Bidding Documents Available For Use
Bidding Documents Available for Use
• Basis of Design Documents Available for bidding @ Sam.gov:
(https://Beta.sam.gov/) o Construction Drawings o Specifications
• Specifications
• Drawing packages per Building and Site
• Bid form Template (excel file with tabs)
• The error when opening drawing pdfs on
Adobe Acrobat or Adobe Reader is a graphic issue with a stamp signature. It Does Not affect any information needed for bidding.
Bidding Documents Available for Use
• Bid form Template (excel file with tabs)
• Bids shall identify CLIN 01 – CLIN 22 as separate bid line items. See 01 00 00
Appendix A “Sample Bid Form” for format.
• Bids will not be reviewed if they are not formatted per the attached template in
Appendix A.
Bid Procedures and Close Date
Bidding Procedures and Close Date
• Bids Due: February 4, 2022 – 2:00 CST
• emailed to sean.jackson@va.gov and jonathan.lutmer@va.gov
A bid guarantee in the amount of 20% of the bid price is required and must be submitted with your proposal submission.
After award of the contract a Payment Bond and a Performance Bond in the amount of 100% of the contract value are due prior to a Notice to Proceed Letter being issued
• Technical Questions due: January 21, 2022 – 2:00 CST
• All technical questions must be submitted in writing to the issuing office via email to:
sean.jackson@va.gov and jonathan.lutmer@va.gov
• No hard copies of the solicitation or drawings will be provided; and telephone requests or questions will NOT be accepted.
• The subject line must read: "589A7-21-700 – ERHM Infrastructure Upgrades”
Updates and Amendments will be posted to: sam.gov
Join us for a Site Walk