024120 SELECTIVE DEMOLITION - Add1 2025-0228.pdf

PDF 37 KB Posted

Attached to
Z1DA--Remodel Fort Wayne Chapel 610A4-22-203
Solicitation number
36C25025B0010
Issued by

About this file

This is a Selective Demolition specification section (02 41 20) from an addendum dated February 28, 2025 for the Fort Wayne Chapel Remodel project at the Northern Indiana VA Healthcare System (Project #610A4-22-203).

The specification details requirements for selective demolition work including removal of designated building construction, equipment and fixtures, salvaging selected materials, utility identification, and coordination with new construction and project phasing. Key requirements include: submitting shop drawings showing demolition areas and sequencing; conforming to applicable codes for demolition safety and dust control; notifying VA COR and utility companies before starting work; protecting existing structures and utilities; erecting temporary partitions and barriers; minimizing interference with Medical Center operations; and proper handling of any hazardous materials discovered. The execution section specifies procedures for preparing the site, protecting remaining structures, disconnecting utilities, salvaging materials, grinding concrete floors smooth after wall removal, and disposing of waste materials sustainably. All work must be coordinated with the VA COR and performed by appropriately skilled trades.

View the file

Other files

File Type Posted
OF1419 Bid Abstract.xlsx XLSX spreadsheet
Amendment 6 - Conference Call Info.pdf PDF
36C25025B0010 A0005.pdf PDF
D1 - evo6-open.pdf PDF
000110 TABLE OF CONTENTS - Add1 2025-0228.pdf PDF
Ft Wayne VA Chapel - Lead Paint Report.pdf PDF
A1 EM - Cove_LED_SPEC.pdf PDF
D1 EM - evo6-open.pdf PDF
RFIs and Responses for Remodel Fort Wayne Chapel.docx DOCX document
Ft Wayne VA Chapel - Asbestos Report.pdf PDF
Ft Wayne VA Chapel - ICRA PCRA.pdf PDF
A1 - Cove_LED_SPEC.pdf PDF
36C25025B0010 Amendment A0004.pdf PDF
D2 - KUZ1862833_specsheet.pdf PDF
A2 - upld.pdf PDF
A3 - Acolyte 1.0 Static White Micro RibbonLyte.pdf PDF
2025-0228 FWVA Chapel DRAWINGS Add1.pdf PDF
013526 SAFETY REQUIREMENTS - Add1 2025-0228.pdf PDF
087100 DOOR HARDWARE - Add1 2025-0228.pdf PDF
X1 - edg-edgr.pdf PDF
Amendment 3 - Bid Due Date Extension.pdf PDF
610A4-22-203 Remodel Fort Wayne Chapel Sign in sheet.pdf PDF
Environmental Requirements.docx DOCX document
Amendment 36C25025B0010 A0002.docx DOCX document
36C25025B0010 A00001.pdf PDF
610A4-22-203 - BID specs.pdf PDF
36C25025B0010 Solicitation.pdf PDF
Wage Determination.txt TXT text file
Contractor Certification Regarding Safety and Environmental.docx DOCX document
610A4-22-203 - BID Drawings.pdf PDF
610A4-22-203 Basis of design cutsheets.pdf PDF
VHA Directive 1192 01.pdf PDF
RFI Form.doc DOC document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Remodel Fort Wayne Chapel – Northern IN VA Healthcare System

Addendum #1 – 02/28/2025 VA Project Number: 610A4-22-203

SELECTIVE DEMOLITION

02 41 20 - 1

SECTION 02 41 20

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Removal of designated building construction, equipment, and fixtures.

2. Salvaging selected materials

3. Identification of utilities.

4. Coordination with new construction and project phasing

B. Related Sections:

1. Division 01 – General Requirements

2. Division 26 – Electrical

1.2 SUBMITTALS

A. Submittals for Review:

1. Shop Drawings: Provide drawings that indicate areas for demolition, removal sequence, project phasing, storage areas and location and construction of temporary work.

1.3 REGULATORY REQUIREMENTS

A. Conform to applicable code for demolition work, safety of structure, and dust control.

B. Notify the VA COR and utility companies before starting work and comply with their requirements.

C. Conform to applicable codes when hazardous or contaminated materials are discovered.

D. Do not close or obstruct exits.

1.4 PROJECT CONDITIONS

A. Review demolition requirements in Electrical specification sections.

B. Minimize interference with Medical Center’s streets, walks, public rights-of-way, and adjacent facilities. Coordinate interior building access needs for personnel with VA COR.

C. If hazardous materials are discovered, notify VA COR and await instructions.

D. If any of the following conditions are encountered, cease work immediately, notify VA COR and Architect, and await instructions:

1. Materials or conditions encountered differ from those designated in the Contract Documents.

PART 2 - PRODUCTS

Not used

Remodel Fort Wayne Chapel – Northern IN VA Healthcare System

Addendum #1 – 02/28/2025 VA Project Number: 610A4-22-203

SELECTIVE DEMOLITION

02 41 20 - 1

PART 3 - EXECUTION

3.1 PREPARATION

A. Erect temporary partitions, barricades, warning devices, and controls as required to maintain a safe site and protect the existing structure to remain. Coordinate requirements with the VA COR.

B. Provide protective coverings and supports for construction designated to remain.

C. Protect existing structure from damage during demolition and construction.

D. Temporarily / permanently disconnect utilities as required.

E. Identify and confirm all materials to be salvaged with the Owner and

Architect prior to beginning demolition. Determine methods for protection and storage of salvaged items during construction as approved by the Owner.

3.2 DEMOLITION

A. Remove existing construction to extent indicated and as necessary to join new work to existing. Do not remove more than is necessary to allow for new construction.

B. Salvage, store and protect from damage all materials designated by the owner to remain or designated for reuse or relocation. Review requirements with the Owner prior to commencing demolition.

C. Do not damage work designated to remain.

D. Minimize noise and spread of dirt and dust within the existing building. See Division 01 specifications for noise and dust control requirements.

E. Assign work to trades skilled in procedures involved.

F. Concrete Floor: Grind smooth uneven areas of concrete floor under masonry or other walls that have been demolished. Prepare concrete floor to receive new flooring.

G. Plug ends of disconnected utilities with threaded or welded caps.

H. Protect and support active utilities designated to remain. Post warning signs showing location and type of utility and type of hazard.

I. Remove and dispose of waste materials off site and in a sustainable manner.

- - - E N D - - -

File details come from the government source that posted it. Updated .