114121 Walk-In Coolers and Freezers.pdf
PDF 147 KB Posted
- Solicitation number
- 36C25020B0059
About this file
This document contains a federal contract solicitation and technical specifications for walk-in coolers and freezers. The solicitation is for project number 539-20-211 to correct deficiencies at the Veterans Administration Cincinnati VAMC. The solicitation will be released on August 10, 2020 via SAM.gov as an IFB set aside for SDVOSBs. The NAICS code is 238220 with a size standard of $16.5M. The project budget is between $500,000 to $1,000,000 and must be completed within 180 days of NTP. Bonds will be required. The specifications provide detailed requirements for walk-in cooler and freezer construction including panel materials, doors, lighting, condensing units, unit coolers, controls, alarms, identification, and testing. Freezers must be accessed through refrigerators.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MH111.pdf | ||
| ED000A - BASEMENT ELECTRICAL DEMO PLAN- AREA A.pdf | ||
| AE111.pdf | ||
| FX101 - FIRE PROTECTION BASEMENT PLANS.pdf | ||
| Asbestos Survey Report.pdf | ||
| AD112.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| EP000A - BASEMENT ELECTRICAL NEW WORK - AREA A.pdf | ||
| 2nd Sign in Sheet.pdf | ||
| 230511 Common Work Results for HVAC.pdf | ||
| MD101.pdf | ||
| AE101.pdf | ||
| 36C25020B0059 0002.docx | DOCX document | |
| AD111.pdf | ||
| 36C25020B0059 0001.docx | DOCX document | |
| Corbin Russwin Locksets Sole Source Justification - Redacted.pdf | ||
| S02 RFI Form.docx | DOCX document | |
| S02 Contractor EMR Certification Form.docx | DOCX document | |
| 539-20-211_Specifications (Combined).pdf | ||
| 100_ CD Drawings_Combined -07202020.pdf | ||
| 36C25020B0059.docx | DOCX document | |
| Wage Determination.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ft. Thomas VAMC: Project #539-20-211 Correct FCA Deficiencies
05-01-15
11 41 21 - 1
WALK-IN COOLERS AND FREEZERS
SECTION 11 41 21
WALK-IN COOLERS AND FREEZERS
PART 1 - GENERAL
1.1 DESCRIPTION:
A. This section specifies walk-in site assembled, refrigerators and freezers.
1.2 RELATED WORK:
A. Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B. Section 23 23 00, REFRIGERANT PIPING: Piping, pipe insulation and refrigerant.
C. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
D. Refer to the construction documents for the refrigeration equipment schedules and installation details.
E. Refer to the construction documents for the fire suppression system.
F. Refer to Division 26, ELECTRICAL for lighting and power requirements.
1.3 WARRANTY:
A. Construction Warranty: Comply with FAR clause 52.246-21, “Warranty of
Construction”.
B. Refrigeration Compressor Warranty: Manufacturer agrees to repair or replace compressors that fail in materials or workmanship within five (5) years from the date of final acceptance by the Government. Failure includes but is not limited to inability to maintain set temperature. Submit compressor warranty.
1.4 SUBMITTALS:
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Manufacturer's Literature and Data:
1. Walk-in units, including assembly instructions.
2. Condensing units, with mounting rack where required.
3. Unit coolers.
4. Temperature controls and alarms.
5. Diagrams and details of piping, wiring and controls.
C. Operational test reports.
D. Final field test reports.
E. Maintenance and operating manuals in accordance with Section 01 00 00, GENERAL
REQUIREMENTS.
11 41 21 - 2
F. Manufacturer’s compressor warranty.
1.5 APPLICABLE PUBLICATIONS:
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referenced in the text by the basic designation only.
B. Air-Conditioning and Refrigeration Institute (ARI):
420-08 ........................................ Unit Coolers for Refrigeration.
520-04 ........................................ Performance Rating of Positive Displacement
Condensing Units.
C. American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE):
15-10 .......................................... Safety Standard for Refrigeration Systems
D. ASTM International (ASTM):
A240/A240M-14 ....................... Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and For General
Applications
E84-11 ....................................... Surface Burning Characteristics of Building Materials
E. National Sanitation Foundation/American National Standard (NSF/ANSI):
7-09 ............................................ Commercial Refrigerators and Storage Freezers
F. National Fire Protection Association (NFPA):
70-14 .......................................... National Electric Code
G. Underwriters Laboratories, Inc. (UL):
207-08(R2014) .......................... Refrigerant-Containing Components and Accessories, Nonelectrical
471-10(R2014) .......................... Commercial Refrigerators and Freezers
1598-03(R2012) ........................ Luminaires
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS:
A. NSF Standards: Provide equipment that bears NSF Certification Mark certifying compliance with applicable standards.
B. UL Certification: Provide electric and fuel-burning equipment and components that are evaluated by UL for fire, electric shock, and casualty hazards according to applicable safety standards, and that are UL certified for compliance and labeled for intended use.
C. Regulatory Requirements: Install equipment to comply with the following:
11 41 21 - 3
1. ASHRAE 15, “Safety Code for Mechanical Refrigeration.”
2. NFPA 70, “National Electric Code.”
2.2 WALK-IN REFRIGERATOR/FREEZER CONSTRUCTION:
A. General: Prefabricated, sectional, all-metal clad, modular, designed for easy accurate field assembly.
B. Provide walk-in units manufactured for food service use conforming to NSF/ANSI 7, UL
207, and UL 471. Floor panel walk-in refrigerators and freezers with appropriate insulated floor assembly and polished aluminum finish floor.
C. Panel Construction:
1. General: Interchangeable, 1219 mm (48 inch) maximum width, 101 mm (4 inch) thick unless noted otherwise, filled with insulation. Double seal serrated neoprene rubber gaskets to assure air and vapor tight joints.
2. Corner panels: 90 degree angle, radiuses 15 mm (0.5 inch) inside and outside, with
305 mm (12-inch) dimensions each side.
3. Panel edges: Foam-in-place, tongue-and-grooved urethane to assure tight joints.
Provide double seal serrated neoprene rubber gaskets to assure air and vapor tight joints on the interior and exterior of each panel along every tongue.
4. Insulation: 101 mm (4 inch) minimum foamed-in-place polyurethane with manufacturer’s rated “K” factor of not more than 0.15, free rise design of not less than 27 kg per cubic meter (1.7 pounds per cubic foot), or in-place density of not less than 32 kg per cubic meter (2 pounds per cubic foot).
5. Door Panel and Door:
a. Provide channel thermal breaker type reinforcing steel frame around the entire perimeter of the door opening.
b. Door shall be an infitting flush-mounted type with dual flexible blade wiper gasket on the bottom, and a replaceable magnetic gasket on the top edge and along both sides.
c. Door shall be equipped with a minimum of three (3) hinges, for rough usage including aluminum diamond plate on inside of door panel and frame to a height of 915 mm (36 inches).
d. Provide hydraulic exterior door closer to prevent slamming and assure secure closing.
11 41 21 - 4
e. Door hinges and latch and strike assembly: Manufacturer's standard, self-closing cam-lift type hinges, for 915 mm (36 inch) door, chrome plated or polished aluminum finish, made to provide for locking, but with an inside safety release mechanism to prevent anyone from being locked inside when door is locked from outside.
f. Concealed, energy use selective, anti-sweat heater wire circuit: Provide sufficient heat to prevent condensation and frost formation at the door jambs and exterior edges of the door on all sides.
g. Thermometer: Manufacturer's standard, 50 mm (2-inch) minimum diameter, dial type, flush mounted in door panel.
6. Pressure relief port: Provide for all freezers operating at 18 degree C (0 degree F), or lower, two-way type ports, to allow for an increase or decrease of air pressure on the interior of the freezer to equalize with air pressure on the exterior. Provide ports with automatically controlled, UL approved anti-sweat heaters. Complete device to carry
UL Label and be assembled ready for connection. Install port in a wall panel away from the direct air stream flowing from the coils.
7. Floor Panels:
a. Floor Panel Strength: Capable of withstanding 28.7 kPa (600 pounds per square foot) uniform load.
b. Provide prefabricated floor panels of the same construction as wall/ceiling except with 1.9 mm (0.078 inch; 14 gauge) aluminum skin, sealed watertight. Furnish two (2) sets of erection tools, compatible with fasteners, with each unit.
D. Wherever compartment dimension exceed clear-span ability of ceiling panels, provide
I-beam support on exterior of ceiling or spline-hangers. Install 13 mm (1/2 inch) diameter steel rods through beam/hangers and secure to structure above. Beams or posts within compartments are not acceptable.
E. Rub rail wall protectors: Manufacturer’s standard, at floor line of walls exposed to traffic.
F. Lights: Provide high-efficiency rated two-tube fluorescent lamps in vapor-proof fixtures with safety shields. Lighting shall conform with UL 1598. Provide diffuser and ballast capable of operating in minus 23 degrees C (10 degrees F) temperature. Lights shall run full length of walk-in starting 610 mm (24 inches) from front panel and extending within
610 mm (24 inches) of back panel. Run between shelf rows to obtain 323 lux (30 foot-candles) at floor level regardless of any interior furnishings.
11 41 21 - 5
2.3 CONDENSING UNITS:
A. Comply with ARI Standard 520. Air cooled type as shown in construction documents.
B. Provide motor driven integral compressor, motor starter, condenser, receiver, common base, and safety/operational controls.
C. Receiver capacity shall not be less than 125 percent of system refrigerant charge.
D. For units racked above each other and for units installed in a closet, provide a factory fabricated steel rack extending approximately 1143 mm (45 inches) above the floor.
E. Do not locate compressors on top of refrigerators or freezers.
F. Provide positive oil lubrication and oil level indicating device for each compressor.
Provide water regulating valve for water cooled unit.
G. Compressor Motor: Squirrel cage induction type of ample size for continuous operating at maximum compressor performance. Provide inherent protection, in compressor terminal box, for each phase of motor.
H. Pressure Switches: Automatic reset low pressure switch, and automatic or manual reset high pressure cutout.
I. Air Cooled Condensing Units:
1. High efficiency type piped and automatically controlled to operate at lower head pressures during low ambient temperature conditions. Designed and weather-proofed for outdoor installation, to operate satisfactorily at winter ambient temperatures down to 15.6 degrees C (3.8 degrees F), and be provided with crankcase and receiver heaters.
2. The condenser fans shall be driven by permanent split capacitor motors.
2.4 UNIT COOLERS:
A. Comply with ARI Standard 420. Units shall be UL listed, forced-ventilation type.
Provide integral defrosting, internal or external refrigerant distributor, single or multiple fans and motors, drip-pan, deflectors, aluminum or baked-enamel steel housing, hangers, and all accessories. Unit coolers for kitchen walk-in units shall be NSF approved.
B. Motors: Permanent split capacitor type in accordance with Section 11 05 12, GENERAL
MOTOR REQUIREMENTS FOR EQUIPMENT. Provide motors with thermal overload protection and manual starting switch.
C. Drain Pans: Galvanized sheet steel. Provide additional drain pans under uncovered refrigerant connections, and interconnect them with main drain pan. For freezer units provide electrically heated drain pan.
11 41 21 - 6
D. Defrost Provision:
1. Refrigerators: Defrost to occur during compressor off cycle with evaporator fan running continuously.
2. Freezer defrost: Defrost by heating elements incorporated into coil and drain pan.
Operation of evaporator fan shall be delayed after defrost cycle until evaporator is cold enough to freeze any water droplets that are on evaporator coil. Defrosting unit shall be automatically controlled by an electric clock, refrigerant suction gas pressure sensing device, or by means of sensing increased air resistance due to ice accumulation.
2.5 MONITORING ALARM SYSTEM:
A. Provide an electronic monitoring and alarm system for each section of each unit.
1. System Components: Detecting thermostat, master control panel, interconnecting wiring, remote audible alarm, and defrost compensator. Provide dials showing temperatures and pilot lights, warning lights, switches, transformer, and buzzer, all as a part of the master control panel. Locate master control panel and remote audible alarm as indicated on construction documents. Provide power fuse to protect system components.
2. System Operation: Set alarms at 5 degrees C (10 degrees F) above and below specified operating temperatures.
B. Personnel Alarm: For each unit, provide separate audible alarm system operable from inside unit, for use of personnel unable to exit unit. Locate remote audible alarm where indicated on construction documents.
2.6 EQUIPMENT IDENTIFICATION REQUIREMENTS:
A. Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B. Identify all walk-ins, refrigeration equipment and alarm devices.
2.7 SPECIAL REQUIREMENTS FOR FREEZERS:
A. Provide entrance to freezers through a refrigerator of a higher temperature. Locate thermometer serving frozen freezer outside of higher temperature refrigerator used as entrance vestibule.
11 41 21 - 7
PART 3 - EXECUTION
3.1 INSTALLATION:
A. Assemble walk-in units and install refrigeration equipment as described in the respective manufacturer's instructions. Make panel joints tight and seal all panel penetrations to prevent condensation or frosting.
1. Unit cooler: NSF approval requires that the unit be suspended at 90 mm (3-1/2 inches) minimum distance below the ceiling to allow cleaning the top of the unit cooler.
2. Mount pipe, conduit, and instrumentation on the exterior and pass thru neatly drilled penetrations to the lights or other devices.
B. Piping, Pipe Insulation and Refrigerant: Provide in accordance with Section 23 23 00, REFRIGERANT PIPING.
C. Controls Installation: As specified in Section 23 09 23, DIRECT-DIGITAL CONTROL
SYSTEM FOR HVAC.
3.2 REFRIGERATOR/FREEZER START-UP, AND PERFORMANCE TESTS AND
INSTRUCTIONS:
A. Initial Start-up and Operational Test:
1. Provide all lubricants and accessories before initial start-up. Start and operate all equipment.
2. Follow the manufacturer’s procedures and place the systems under all modes of operation.
3. Supplement initial charges of lubricating oil to assure maximum operating capacity.
4. Adjust all safety and automatic control instruments. Record manufacturer’s recommended readings hourly.
5. Operational tests shall cover a period of not less than three (3) days. Submit operational test report.
B. Test Reports: Submit the final field test reports for each system tested, describing test apparatus, instrumentation calculations, and equipment data based on industry standard forms. Include in data:
1. Compressor and air moving device ampere readings.
2. Power supply characteristics, including phase imbalance, with 1/2 percent accuracy.
3. Thermostatic expansion valve superheat-value as determined by field test.
4. Sub-cooling.
11 41 21 - 8
5. High and low refrigerant temperature switch set-points.
6. Monitoring alarm system.
7. Low oil pressure switch set-point.
8. Defrost system timer and thermostat set-points.
9. Moisture content.
10. Ambient, condensing and coolant temperatures.
11. Capacity control set-points.
12. Field data and adjustments which affect unit performance and energy consumption.
13. Where final adjustments and settings cannot be permanently marked or drilled and pinned as an integral part of device, include adjustment and setting data in test report.
C. By arrangement with the Contracting Officer Representative (COR), 24 hours in advance, use the start-up and test period for required operation and maintenance instructions to VA personnel in accordance with Section 01 00 00, GENERAL REQUIREMENTS.
- - - E N D - - -