Drawings 621-23-106 Amendment 3.3.2023.pdf
PDF 34 MB Posted
- Solicitation number
- 36C24923B0007
About this file
This document outlines a solicitation for a construction project to restore the exteriors of five historical quarters buildings located at the James H. Quillen VA Medical Center. The scope of work includes replacing wood, installing water barriers and gutters, painting, conducting roof repairs, tuckpointing and repairing brick, and ensuring proper drainage away from the buildings. The period of performance is 400 calendar days from issuance of the notice to proceed. The contractor will be responsible for supervision, communication, planning, drawings, site visits, deliveries, inspections, and closeout according to the terms specified. Work will generally be performed during normal business hours from Monday through Thursday, and the contractor must coordinate any necessary outages or noisy work in advance with the contracting officer's representative.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Location:
Site:
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
COVER SHEET AND
INDEX SHEET
G-001
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS 621-23-106
JANUARY 31,
NJH
N/A
STATION MAP
NTS
SHEET INDEX
G-001 COVERSHEET AND INDEX SHEET
G-002 GENERAL PROJECT NOTES AND REFERENCES
G-003 SITE AND STAGING PLAN
A-001 BLDG 15 EXTERIOR ORIGINAL DRAWING SCANS
A-002 BLDG 15 EXTERIOR FRONT DETAILS
A-003 BLDG 15 EXTERIOR LEFT DETAILS
A-004 BLDG 15 EXTERIOR REAR DETAILS
A-005 BLDG 15 EXTERIOR RIGHT DETAILS
A-006 BLDG 45 EXTERIOR ORIGINAL DRAWING SCANS
A-007 BLDG 45 EXTERIOR FRONT DETAILS
A-008 BLDG 45 EXTERIOR LEFT DETAILS
A-009 BLDG 45 EXTERIOR REAR DETAILS
A-010 BLDG 45 EXTERIOR RIGHT DETAILS
A-011 BLDG 46 EXTERIOR ORIGINAL DRAWING SCANS
A-012 BLDG 46 EXTERIOR FRONT DETAILS
A-013 BLDG 46 EXTERIOR LEFT DETAILS
A-014 BLDG 46 EXTERIOR REAR DETAILS
A-015 BLDG 46 EXTERIOR RIGHT DETAILS
A-016 BLDG 47 EXTERIOR ORIGINAL DRAWING SCANS
A-017 BLDG 47 EXTERIOR FRONT DETAILS
A-018 BLDG 47 EXTERIOR LEFT DETAILS
A-019 BLDG 47 EXTERIOR REAR DETAILS
A-020 BLDG 47 EXTERIOR RIGHT DETAILS
A-021 SITE DETAILS
A-022 DELETED
JAMES H. QUILLEN VA MEDICAL CENTER
RESTORE EXTERIORS FOR QUARTERS BUILDINGS
PROJECT# 621-23-106
DEPARTMENT OF VETERANS AFFAIRS
MOUNTAIN HOME, TENNESSEE 37604
N/A
PROJECT SITE
REVISION 1 3.3.23
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
GENERAL PROJECT
NOTES AND
REFERENCES
G-002
621-23-106
JANUARY 31,
NJH
N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
GENERAL NOTES - EXISTING FACILITIES
1. THE GENERAL CONTRACTOR SHALL VERIFY ALL EXISTING DIMENSIONS AND FIELD CONDITIONS PRIOR TO DEMOLITION AND CONSTRUCTION. IF PROVIDED, THE GENERAL CONTRACTOR SHALL CAREFULLY EXAMINE EXISTING BUILDING DOCUMENTS. THE CONTRACTOR SHALL BRING ANY DISCREPANCIES TO THE IMMEDIATE
ATTENTION OF THE COR.
2. THE GERNAL CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF EXISTING ITEMS TO REMAIN AND EXISTING ITEMS TO BE REMOVED AND REINSTALLED DURING
DEMOLITION AND CONSTRUCTION.
3. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF ALL CONSTRUCTION ROUTES BEYOND THE AREAS OF WORK AND THE ROUTES MUST BE
RETURNED TO THEIR ORIGINAL CONDITION AT THE END OF THE PROJECT.
4. ALL EXISTING SERVICES AND UTILITIES SHALL BE MAINTAINED TO AREAS THAT ARE IN OPERATION AND SERVED BY THEM. COORDINATE ALL DISRUPTIONS OR DISCONTINUATIONS OF UTILITIES AND SERVICES WITH COR. NO SHUT DOWN OF EXISTING SERVICES IS ALLOWED TO OCCUR UNTIL RECEIVING THE COR'S WRITTEN APPROVAL OF THE SHUT DOWN SCHEDULE. PROVIDE TEMPORARY SERVICES AND/OR UTILITIES DURING INTERRUPTIONS AS REQUIRED AND APPROVED BY THE COR.
5. THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT DAMAGE TO THE VA'S AREAS ADJACENT TO CONSTRUCTION OR AREAS WHERE VARIOUS SYSTEM CONNECTIONS OR EXTENSIONS ARE REQUIRED. IN THESE AREAS, THE CONTRACTOR IS RESPONSIBLE FOR DAMAGE CAUSED BY LACK OF SUFFICIENT
PROTECTION FROM THE WEATHER AND FROM THE RESULTS OF ALL CONSTRUCTION ACTIVITY.
6. THE GENERAL CONTRACTOR SHALL MAINTAIN THE BUILDINGS IN A WEATHER TIGHT CONDITION AT ALL TIMES.
7. PROVIDE FIRE PROTECTION IN ACCORDANCE WITH THE REQUIREMENTS OF THE GOVERNING AUTHORITY.
8. DO NOT OVERLOAD THE EXISTING BUILDING STRUCTURE. MAINTAIN THE STRUCTURAL INTEGRITY OF ALL STRUCTURAL FRAMING MEMBERS AND SYSTEMS AT ALL
TIMES.
9. ALL DEMOLISHED MATERIAL, EXCEPT MATERIAL THAT IS LISTED OR MARKED BY THE COR FOR RETENTION, SHALL BECOME THE PROPERTY OF THE CONTRACTOR, AND IT SHALL BE DISPOSED OF. NO DEBRIS RESULTING FROM WORK SHALL BE LEFT IN THE CONSTRUCTION ROUTES BEYOND THE AREAS OF WORK.
10. REMOVAL OF A PARTICULAR ITEM SHALL INCLUDE ALL RELATED ITEMS, SUCH AS REMOVAL OF WALLS WOULD INCLUDE ASSOCIATED DOORS, HARDWARE, ELECTRICAL, PLUMBING, MECHANICAL, ETC. REFER TO DEMOLITION DRAWINGS FOR MORE INFORMATION. FOR ALL REMOVALS, THE GENERAL CONRACTOR SHALL
COORDINATE WITH ALL OTHER DISCIPLINES.
11. THE CONTRACTOR SHALL PROVIDE TEMPORARY SUPPORT FOR ITEMS NOT DEMOLISHED OR REMOVED AS REQUIRED UNTIL PERMANENT SUPPORT IS PROVIDED IN
THE FINAL CONSTRUCTION.
12. ALL OPENINGS IN EXISTING WALLS, CEILINGS AND FLOORS, WHICH ARE THE RESULT OF REMOVALS AND OTHER NEW CONSTRUCTION ACTIVITY, SHALL BE PATCHED WITH NEW MATERIALS THAT MATCH THE EXISTING MATERIALS. IF THE PATCH IS TO BE MADE IN FIRE RATED CONSTRUCTION, THEN THE PATCH MUST ACHIEVE THE REQUIRED FIRE RATING. THE PATCH SHALL BE FINISHED TO A LIKE NEW CONDITION TO MATCH THE EXISTING FINISH.
13. WHERE EXISTING SURFACES ARE TO BE REFINISHED OR ARE TO SERVE AS SUBSTRATE FOR THE ATTACHMENT OR APPLICATION OF NEW MATERIALS OR CONSTRUCTION, PREPARE OR ALTER THE EXISTING SURFACES AS NECESSARY TO PROPERLY ACCOMODATE THE NEW MATERIALS.
14. FIELD VERIFY SIZES AND DIMENSIONS OF EXISTING UTILITIES THAT IMPACT THE NEW WORK. DETERMINE THE SIZE AND LOCATION OF PENETRATIONS FROM THE EXISTING UTILITIES WITHIN THE NEW WORK. SEAL TIGHT TO ALL PENETRATIONS AND CAULK.
15. PENETRATIONS THROUGH EXISTING FIRE RATED CONSTRUCTION MUST BE PROPERLY CLOSED AND FIRE SAFED TO ACHIEVE THE PROPER FIRE RATING BY THE END
OF CONSTRUCTION OPERATIONS FOR EACH DAY.
16. NEW HOLES IN EXISTING ELEVATED FLOOR AND ROOF STRUCTURES FOR NEW WORK MUST BE COORDINATED WITH THE EXISTING STRUCTURE SO THAT CRITICAL
STRUCTURAL MEMBERS ARE NOT DAMAGED.
17. UNLESS OTHERWISE NOTED, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL EXISTING SALVAGED STOCK BEFORE ORDERING NEW MATERIAL.
GENERAL NOTES - DEMOLITION
1. ALL PLANS SHALL BE IN ACCORDANCE WITH CURRENT VA AND APPLICABLE TENNESSEE DEPARTMENT OF TRANSPORTATION STANDARDS.
2. CONTRACTOR SHALL OBTAIN A PERMIT FOR ALL CONSTRUCTION ACTIVITIES IN ACCORDANCE WITH LOCAL, STATE, AND FEDERAL REGULATION.
3. CONTRACTOR TO REMOVE/TRIM TREES ADN CLEAR AREAS AS NECESSARY TO COMPLETE ALL SITE WORK INCLUDIGN GRDING AND UTILITY WORK.
4. PROTECTION OF EXISTING TREES AND VEGETATION: PROTECT EXISTING TREES AND OTHER VEGETATION INDICATED TO REMIAN IN PLACE AGAINST UNNECESSARY CUTTING. BREAKING OR SKINNING OF ROOTS, SKINNING OR BRUSHING OF BARK, SMOTHERING OF TREES BY STOCKPILING OF CONSTRUCTION MATERIALS OR EXCAVATED MATERIALS WITHIN DRIP LINE. PROVIDE TEMPORARY GUARDS TO PROTECT TREES AND VEGETATION TO BE LEFT STANDING.
5. CONTRACTOR SHALL IMPLEMENT ALL SOIL AND EROSION CONTROL PRACTICES REQUIRED BY THE VETERANS ADMINISTRATION AND THE TENNESSEE EPA.
6. THE CONTRACTOR SHALL VERIFY THE LOCATION AND ELEVATION OF ALL EXISTING UTILITIES (INCLUDING THOSE LABELED PER RECORD DATA) PRIOR TO THE BEGINNING OF CONSTRUCTION OR EARTH MOVING ACTIVITIES. INFORM THE COR AND CO OF ANY CONFLICT DETRIMENTAL TO THE DESIGN INTENT.
7. FORTY-EIGHT HOURS BEFORE DIGGING IS TO COMMENCE, THE CONTRACTOR SHALL NOTIFY THE FOLLOWING AGENCIES: TENNESSEE 811 AND ALL OTHER AGENCIES WHICH MAY HAVE UNDERGROUND UTILITIES INVOVLING THIS PROJECT AND ARE NON-MEMBER OF TENNESSEE 811.
8. IF NECESSARY, SAWCUT EXISTING CONCRETE IN NEAT, STRAIGHT LINES TO CREATE A CLEAN JOINT.
9. CONTRACTOR TO GRADE LAWN AREAS TO DRAIN AWAY FROM BUILDING.
10. ALL GROUND SURFACE AREAS THAT HAVE BEEN EXPOSED OR LEFT BARE AS A RESULT OF CONSTRUCTION AND ARE TO FINAL GRADE AND ARE TO REMAIN SO SHALL BE SEEDED AND MULCHED AS SOON AS PRACTICAL IN ACCORDANCE WITH THE SPECIFICATIONS. SEED TALL FESCUE/RED FESCUE MIX; AVOID RYE.
11. REFER TO THE SPECIFICATIONS AND PROVIDED ASBESTOS AND LEAD-BASED PAINT REPORTS PROVIDED IN ORDER TO ASSESS REQUIREMENTS FOR ABATEMENT.
BUILDING CODE SUMMARY
APPLICABLE CODES AND STANDARDS
2018 INTERNATIONAL EXISTING BUILDING CODE
2018 INTERNATIONAL FIRE CODE
2018 INTERNATIONAL ENERGY CONSERVATION CODE
2020 NFPA 70 NATIONAL ELECTRICAL CODE
2021 NFPA 101 LIFE SAFETY CODE
2006 ABA ACCESSIBILITY STANDARDS FOR FEDERAL FACILITIES
SYMBOLS
GENERAL NOTES - NEW WORK
1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH APPLICABLE LOCAL, STATE, AND FEDERAL AUTHORITIES, CODES, RULES AND REGULATIONS.
2. THESE DOCUMENTS SHOW THE MINIMUM CONSTRUCTION REQUIREMENTS AND THE MINIMUM QUALITY OF WORK EXPECTED. MORE STRINGENT REQUIREMENTS STIPULATED WITHIN RELEVANT MANUFACTURER'S INSTALLATION INSTRUCTIONS WILL SUPERSEDE.
3. ANY UNFORSEEN OR UNCLEAR CONDITIONS SHALL BE REPORTED IN WRITING TO THE COR AND CO PRIOR TO PROCEEDING WITH WORK.
4. ANY CONFLICTS WITHIN THE DRAWINGS, BETWEEN THE DRAWINGS AND THE SPECIFICATIONS, OR BETWEEN THE DRAWINGS AND THE ACTUAL CONDITIONS AT THE SITE, ARE TO BE BROUGHT TO THE IMMEDIATE ATTENTION OF THE COR. THE CONTRACTOR SHALL NOT PROCEED WITH WORK UNTIL WRITTEN CLARIFICATION
FROM THE COR IS RECEIVED.
5. UNLESS OTHERWISE NOTED, ALL MATERIALS AND EQUIPMENT ARE TO BE INSTALLED PER THE APPLICABLE PROVISIONS OF THESE DOCUMENTS AND THE
MANUFACTURER'S INSTRUCITONS.
6. ALL THE MATERIASL USED ARE REQUIRED TO BE NEW UNLESS OTHERWISE NOTED AND/OR OF A QUALITY TO MEET OR EXCEED ALL APPLICABLE INDUSTRY STANDARDS WHERE SPECIFIED PRODUCTS OR MANUFACTURERS ARE NOT NOTED, THE CONSTRACTOR IS REQUIRED TO NOTIFY THE COR TO OBTAIN A MINIMUM
STANDARD OF QUALITY.
7. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR ALL MEANS, METHODS, AND TECHNIQUES FOR CONSTRUCTION.
8. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR JOB-SITE SAFETY INCLUDING BUT NOT LIMITED TO THE ADHERENCE TO OSHA REGULATIONS.
9. ALL ELECTRICAL AND MECHANICAL WORK SHALL BE PERFORMED BY PERSONNEL LICENSED IN THE STATE WHERE THIS PROJECT IS LOCATED.
10. REMOVE ALL DEBRIS PROPERLY FROM THE SITE. LOAD DEBRIS DIRECLTY ONTO TRUCKS OR INTO DUMPSTER FOR REMOVAL. DISPOSE OF DEBRIS LEGALLY. DO NOT BURN DEBRIS ON THE SITE. DO NOT ALLOW DEBRIS TO ENTER SEWERS. DO NOT ALLOW PILED DEBRIS TO ENDANGER STRUCTURES, BLOCK EXITS, OR INTERFERE WITH ROADWAYS. COMBUSTIBLE WASTE WHICH COULD CREATE A FIRE HAZARD SHALL NOT BE PERMITTED TO ACCUMULATE IN OR AROUND THE
CONSTRUCTION SITE.
11. THE GENERAL CONTRACTOR SHALL COORDINATE WITH ALL OTHER DISCIPLINES INCLUDING BUT NOT LIMITED TO MECHANICAL, ELECTRICAL, PLUMBING TO DETERMINE THE SIZE AND LOCATION OF ALL PENETRATIONS IN NEW CONSTRUCTION AS NEEDED. COORDINATE AND PROVIDE ALL OPENINGS. SEAL CONSTRUCTION TIGHT TO ALL PENETRATIONS AND CAULK. EXACT SIZE AND LOCATION OF ALL ROOF AND FLOOR OPENINGS SHOWN ON DRAWINGS SHALL BE
VERIFIED WITH THE ASSOCIATED SUB-CONSTRACTORS PRIOR TO CONSTRUCTION.
12. DO NOT SCALE DRAWINGS. DIMENSIONS SHALL GOVERN. ALL PLAN DIMENSIONS ARE TAKEN TO FINISH FACE OF CONSTRUCTION.
13. CONCEALED WOOD DOES NOT NEED TO BE FIRE RATED; WOOD THAT IS EXPOSED TO THE ELEMENTS SHOULD BE SEVERE WEATHER TREATED LUMBER.
14. THE CONTRACTOR SHALL PROVIDE TERMITE INSPECTION AND PROTECTION: SEE SPECIFICATIONS 31 31 16 TERMITE CONTROL.
15. THE BUILDING WILL REMAIN UNOCCUPIED DURING CONSTRUCTION. NEIGHBORING BUILDINGS AND PARKING AREAS WILL REMAIN OCCUPIED DURING
CONSTRUCTION.
16. ALL PROPOSED STORM SEWER, SURFACE, AND OTHER DRAINAGE FACILITIES ARE TO BE PRIVATE AND MAINTAINED BY OWNER. ALL STORM STRUCTURES ARE TO BE IN ACCORDANCE WITH TENNESSEE DOT STANDARDS UNLESS OTHERWISE NOTED. FOR EXACT LOCATIONS OF DOWN SPOUTS AND ROOF DRAINS COORDINATE WITH ARCHITECTURAL DRAWINGS. PLUMBING DRAWINGS AVAILABLE UPON REQUEST. ALL ROOF DRAINS, DOWNSPOUT AND STORM SEWER LINES TO
BE 6" PVC PIPE AT A SLOPE OF 2.5% UNLESS OTHERWISE SPECIFIED.
17. CONTRACTOR SHALL PRESENT SHOP DRAWINGS FOR APPROVAL OF JOIST REPAIR; COLUMN AND RAILING REPLACEMENTS; DOWNSPOUT CONNECTIONS AND EXTENSIONS; ROOF DETAILS TO INCLUDE FLASHING, CRICKETS, AND GUTTER CONNECTIONS; AND, OTHER WORK AS DISCUSSED IN SPECIFICATION 01 33 23 AND/OR
REQUEST BY COR.
18. NEW WORK TO MATCH EXISTING HISTORICAL LOOK OF WOOD SIDING, COLUMNS, GUTTERS, DOWNSPOUTS, STRAPS. AND ALL ASSOCIATED ACCESSORIES IN
KIND (COLOR, SHAPE, PROFILE, TEXTURE, MATERIAL, ETC).
X DETAIL/DRAWING NUMBER
XXXX SHEET LOCATION
X X SILT FENCE
UNDERGROUND DISCHARGE OF DOWNSPOUT
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
SITE AND STAGING PLAN G-003
621-23-106
NJH
N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
STAFF
PARKING
LOT
Phase 1
Phase 2
Phase 3
LEGEND
(PURPLE): STORM STEWER
(BLUE): WATER LINES
(YELLOW): GAS LINES
(RED): UNDERGROUND ELECTRICAL
(GREEN): SANITARY SEWER
Phase 4
East Tennessee State University Properties
East Tennessee State University Property
F1
A-021
F1
A-021
PROPOSED
LAYDOWN AREA
F1
A-021 F1
A-021
F1
A-021
JANUARY 31,
REVISION 1 3.3.23
GENERAL NOTES - SITE AND STAGING PLAN
1. PROJECT SHALL BE COMPLETED IN PHASES AS INDICATED ON
THIS SHEET.
2. THE SITE IS BORDERED NORTH, EAST, AND WEST BY COMMERCIAL
AND EAST TENNESSEE STATE UNIVERSITY PROPERTIES.
3. THE SITE IS LOCATED AROUND MATURE TREES AND EXISTING
HISTORIC FACILITIES THAT INCLUDE EXISTING BUILDINGS, PARKING,
MEDICAL CENTER, AND A CEMETARY.
4. CONTRACTOR CANNOT BLOCK ACCESS TO NEIGHBORING
BUILDINGS, ROADS, AND PARKING AREAS, INCLUDING CONEXES
ADJACENT TO BLDG 15. ANY TEMPORARY CLOSURES OR LIMITED
ACCESS DUE TO DELIVERIES MUST BE COORDINATED WITH THE COR
AND INCLUDE TRAFFIC CONTROL MEASURES.
5. POTENTIAL LAYDOWN AREA AS SHOWN TO BE FINALIZED PRIOR
TO PROJECT START DATE. LAYDOWN AREA PLAN AND ASSOCIATED
REQUIREMENTS, SUCH AS CONSTRUCTION FENCE, GRAVEL, AND SILT
FENCE IF NECESSARY, TO BE APPROVED BY COR.
EROSION AND SEDIMENT CONTROL PROGRAM
1. PRIOR TO THE REMOVAL OF SHRUBS, INSTALLATION OF SEDIMENT
CONTROL MEASURES, TRENCHING, OR GRADING, THE CONTRACTOR
SHALL CALL FOR THE INSPECTIO OF DIVIDISON OF WATER
RESOURCES OF THE TENNESSEE DEPARTMENT OF ENVIRONMENT AND
CONSERVATION (TDEC) PRIOR TO THE START OF ANY LAND
DISTURBING ACTIVITY. CONTRACTOR TO VERIFY EXISTING SITE
CONDITIONS AND ESTABLISH LIMITS OF DISTURBANCE (LOD).
2. CONTRACTOR WILL REMOVE SHRUBS ADJACENT TO THE
BUILDINGS UNDER CONSTRUCTION; SHUBS WILL NOT BE REPLACED.
WHEN TREES ARE LOCATED WITHIN THE LIMITS OF CONSTRUCTION,
CONTRACTOR WILL INSTALL TEMPORARY TREE PROTECTION: SEE
SHEET A-021. NOTE: EXISTING TREES AND SHRUBS NOT SHOWN ON
DRAWING.
3. DURING ACTIVE CONSTRUCTION, CONTRACTOR SHALL INSTALL
SILT FENCE FIVE FEET FROM THE ACTIVE DIGGING AREA FOR GUTTER
DOWNSPOUTS AND EXTENSIONS OF DISCHARGES.
4. SITE TO BE INSPECTED AT THE END OF EACH DAY AND AFTER
EACH RAINFALL BY THE SUPERINTENDENT OR HIS REPRESENTATIVE.
5. WHERE CONSTRUCTION VEHICLE ACCESS PAVED PUBLIC ACCESS
ROADS ON CAMPUS, SEDIMENT SHALL BE REMOVED FROM THE
ROADS BY SHOVELING OR SWEEPING THEN TRANSPORTING TO A
SEDIMENT CONTROL DISPOSAL AREA. STREET WASHING SHALL BE
ALLOWED ONLY AFTER SEDIMENT IS REMOVED IN THIS MANNER.
6. THE CONTRACTOR SHALL CONDUCT OPERATIONS AND MAINTAIN
THE PROJECT SITE AS TO MINIMIZE THE CREATION AND DISPERSION
OF DUST. DUST CONTROL SHALL BE USED THROUGHOUT THE WORK
AT THE SITE AS PER THE STANDADRDS AND SPECIFICAITONS FOR
SOIL EROSION AND SEDIMENT CONTROL.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 15 EXTERIOR
ORIGINAL DRAWING
SCANS
A-001
621-23-106
JANUARY 31,
NJH
15 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
BLK
LEFT SIDE ELEVATION - BLDG. 15
REAR ELEVATION - BLDG. 15FRONT ELEVATION - BLDG. 15
RIGHT SIDE ELEVATION - BLDG. 15
~36' +/-
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
FRONT ELEVATION - BLDG. 15
BLDG 15 EXTERIOR
FRONT DETAILS
621-23-106
NJH
JANUARY 31,
A-002
NTS
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. REMOVE AND REPLACE DAMAGED AND ROTTEN WOOD JOISTS (APPROXIMATELY 40 LF OF THE BUILDING). REPLACEMENT MATERIALS SHALL REST ON SILL
PLATES AND BE CONNECTED TO RIM JOISTS.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
14. REMOVE AND REPLACE HANDRAIL. PAINT COLOR TO BE SELECTED BY COR.
F1
A-021
ROOF DRAIN LOCATIONS - RD 6"
SEE DETAIL C1 ON SHEET A-021
REVISION 1 3.3.23
C2
A-021
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
BLK
LEFT SIDE ELEVATION - BLDG. 15
NTS
BLDG 15 EXTERIOR LEFT
DETAILS
A-003
621-23-106
JANUARY 31,
NJH
15 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. REMOVE AND REPLACE DAMAGED AND ROTTEN WOOD JOISTS (APPROXIMATELY 40 LF OF THE BUILDING). REPLACEMENT MATERIALS SHALL REST ON SILL
PLATES AND BE CONNECTED TO RIM JOISTS.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
14. REMOVE AND REPLACE HANDRAIL. PAINT COLOR TO BE SELECTED BY COR.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 15 EXTERIOR
REAR DETAILS
A-004
621-23-106
JANUARY 31,
NJH
15 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
KEY NOTES
1. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION IN A NUMBER OF LOCATIONS, INCLUDING EXTERIOR AND INTERIOR SIDE OF WALL IN SPOT AREAS, IN ORDER TO ADDRESS WATER INFILTRATION (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN
KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED.
2. TUCKPOINT AND REPAIR DAMAGE TO CHIMNEY (120 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED. REPAIR/REPLACE CRICKET AND FLASHING AS NEEDED.
3. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS, WINDOWS AND OTHER AREAS TO PREPARE SURFACE. PRIME AND APPLY TWO COATS OF
PAINT.
4. REMOVE WOOD SIDING AND ANY DAMAGED, ROTTEN WOOD ADJACENT, SUCH AS WINDOW, DOOR, AND HOUSE TRIM. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REPAIR/REPLACE DECK SUBSTRUCTURE ON PORCH OF SECOND STORY (APPROXIMATELY 550 SF). REMOVE ADHERED EPDM ROOFING SYSTEM ON SECOND STORY PORCH (APPROXIMATELY 550 SF) AND REPLACE WITH TPO. REPLACE TPO/AHHERED MODIFIED BITUMEN ROOFING SYSTEM ON ROOF.
6. REPAIR/REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 100 LF).
7. REPAIR/REPLACE WOOD GUARDRAIL AND ANY DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF). CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
8. REMOVE EXISTING METAL GUTTERS, INCLUDING SPLASHGUARDS, AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). ADD GUTTER GUARDS TO PROTECT FROM FALLING LEAVES. DIVERT WATER AWAY FROM FOUNDATION USING AN UNDERGROUND SYSTEM FOR 25 FEET.
9. REMOVE EXISTING IRON HANDRAIL AND REPLACE (APPROXIMATELY 30 LF).
10. REMOVE ROTTEN WOOD FROM JOIST AND REPAIR/REPLACE (APPROXIMATELY 40 LF OF THE BUILDING).
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL EXTERIOR SIGNAGE IN ACCORDANCE WITH VA STANDARDS.
REAR ELEVATION - BLDG. 15 KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN
PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF). REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS
OF PAINT.
8. REMOVE AND REPLACE DAMAGED AND ROTTEN WOOD JOISTS (APPROXIMATELY 40 LF OF THE BUILDING). REPLACEMENT MATERIALS SHALL REST ON SILL PLATES AND
BE CONNECTED TO RIM JOISTS.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
14. REMOVE AND REPLACE HANDRAIL. PAINT COLOR TO BE SELECTED BY COR.
REVISION 1 3.3.23
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
BLDG 15 EXTERIOR
RIGHT DETAILS
621-23-106
NJH
JANUARY 31,
A-005
NTS
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
RIGHT SIDE ELEVATION - BLDG. 15
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. REMOVE AND REPLACE DAMAGED AND ROTTEN WOOD JOISTS (APPROXIMATELY 40 LF OF THE BUILDING). REPLACEMENT MATERIALS SHALL REST ON SILL
PLATES AND BE CONNECTED TO RIM JOISTS.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 45 EXTERIOR
ORGINAL DRAWING
SCANS
A-006
621-23-106
NJH
45 N/A
ATION MAP
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
LEFT SIDE ELEVATION - BLDG 45
FRONT ELEVATION - BLDG. 45 REAR ELEVATION - BLDG. 45
RIGHT SIDE ELEVATION - BLDG. 45
JANUARY 31,
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
BLDG 45 EXTERIOR
FRONT DETAILS
621-23-106
NJH
JANUARY 31,
A-007
NTS
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
F1
A-021
ROOF DRAIN LOCATIONS - RD 6"
SEE DETAIL C1 ON SHEET A-021
FRONT ELEVATION - BLDG. 45
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. DELETED.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 45 EXTERIOR LEFT
DETAILS
A-008
621-23-106
JANUARY 31,
NJH
45 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
LEFT SIDE ELEVATION - BLDG 45
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. DELETED.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 45 EXTERIOR
REAR DETAILS
A-009
621-23-106
JANUARY 31,
NJH
45 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
REAR ELEVATION - BLDG. 45
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN
PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF). REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS
OF PAINT.
8. DELETED.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
14. REMOVE AND REPLACE HANDRAIL. PAINT COLOR TO BE SELECTED BY COR.
REVISION 1 3.3.23
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
BLDG 45 EXTERIOR RIGHT
DETAILS
621-23-106
NJH
JANUARY 31,
A-010
NTS
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
ATION MAPRIGHT SIDE ELEVATION - BLDG. 45
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF). REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING.
PRIME AND APPLY TWO COATS OF PAINT.
8. DELETED COMMENT.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON
COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
A-011
621-23-106
NJH
46 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
BLDG 46 EXTERIOR
ORIGINAL DRAWING
SCANS
LEFT SIDE ELEVATION - BLDG. 46 RIGHT SIDE ELEVATION - BLDG. 46
FRONT ELEVATION - BLDG. 46 REAR ELEVATION - BLDG. 46
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 46 EXTERIOR
FRONT DETAILS
A-012
621-23-106
JANUARY 31,
NJH
46 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
F1
A-021
ROOF DRAIN LOCATIONS - RD 6"
SEE DETAIL C1 ON SHEET A-021
FRONT ELEVATION - BLDG. 46
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. DELETED.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
NTS
BLDG 46 EXTERIOR LEFT
DETAILS
A-013
621-23-106
JANUARY 31,
NJH
46 N/A
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
LEFT SIDE ELEVATION - BLDG. 46
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING DECKING ON SECOND STORY BALCONY/PORCH. REPLACE DECKING WITH 3/4" TREATED PLYWOOD AND REROOF WITH TPO (APPROXIMATELY 550 SF). REMOVE BUILT UP ROOFING SYSTEM ON TOP FLAT ROOF AND REPLACE WITH TPO.
6. REPLACE WOOD GUARDRAIL, COLUMNS, AND COLUMN BASES ON SECOND STORY EXTERIOR BALCONY (APPROXIMATELY 180 LF AND 100 LF RESPECTIVELY).
REPLACEMENTS SHALL MATCH EXISTING. PRIME AND APPLY TWO COATS OF PAINT.
7. REPLACE WOOD GUARDRAIL AND ALL DAMAGED, ROTTEN, UNMATCHED WOOD ON COLUMNS AND COLUMN BASES ON FRONT PORCH (APPROXIMATELY 150 LF).
REPAIRS AND REPLACEMENTS SHALL MATCH EXISTING. CLEAN AND REMOVE PAINT FROM WOOD THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND
APPLY TWO COATS OF PAINT.
8. DELETED.
9. REMOVE EXISTING METAL GUTTERS AND REPLACE WITH COPPER GUTTERS (APPROXIMATELY 1,500 LF OF THE BUILDING). INSTALL GUTTER GUARDS. GUTTER GUARDS SHALL BE COMPATIBLE WITH COPPER GUTTERS. REMOVE SPLASHGUARDS. CONNECT DOWNSPOUTS TO 6" DIA. SCH. 80 PVC, MINIMUM LENGTH 25 FEET DEPENDING ON SLOPE. DAYLIGHT AND BEVEL OUTLET END TO MATCH GRADE. PATCH AND REPAIR PAVEMENT AS NECESSARY.
10. PREPARE, PRIME AND PAINT ( MINIMUM TWO COATS) ALL SURFACES, INCLUDING MASONRY, FRONT PORCH CEILING, DOORS, TRIM, EAVES AND EAVE JOISTS.
11. PROVIDE FINAL SMOOTH GRADE, MULCH, AND SEED ALL GRASSED AREAS DISTURBED BY WORK, INCLUDING INSTALLATION OF DRAINAGE, UPON COMPLETION.
12. REINSTALL SALVAGED EXTERIOR SIGNAGE AS DIRECTED BY THE COR.
13. CLEAN ALL WINDOWS.
Drawn:
Project Title:
Checked: Approved:
Project No.
Drawing No.
Date
Building:
Scale:
JAMES H. QUILLEN
MOUNTAIN HOME VAMC
Drawing Title:
Revisions DateApprovals Date
MOUNTAIN HOME
Floor:
BLDG 46 EXTERIOR REAR
DETAILS
621-23-106
NJH
JANUARY 31,
A-014
NTS
RESTORE EXTERIORS
FOR QUARTERS
BUILDINGS
N/A
REAR ELEVATION - BLDG. 46
KEY NOTES
1. PRESSURE WASH ROOF. CLEAN AND REMOVE PAINT FROM BRICK MASONRY FOUNDATION WALLS AND ALL OTHER AREAS TO RECEIVE PAINT.
2. TUCKPOINT AND REPAIR DAMAGE TO BRICK FOUNDATION AT ALL VISIBLE LOCATIONS AND AT ALL INTERIOR LOCATIONS WHERE WATER INFILTRATION HAS OCCURED (APPROXIMATELY 1,200 SF TUCKPOINTING OF THE BUILDING). PATCH AS REQUIRED TO MATCH ADJACENT CONSTRUCTION IN KIND WHERE ALL CONSTRUCTION IS TO REMAIN - FIELD VERIFY EXTENT REQUIRED. EXISTING REFRIGERANT LINES SHALL BE REMOVED AND REINSTALLED AS NECESSARY.
3. TUCKPOINT AND REPAIR DAMAGE TO FRONT BRICK STEPS AND CHIMNEY (150 SF TUCKPOINTING) - FIELD VERIFY EXTENT REQUIRED.
4. REMOVE AND REPLACE, WITH LIKE MATERIALS, ALL WOOD SIDING AND ALL DAMAGED, ROTTEN WOOD INCLUDING FRAMING AND TRIM AT WINDOWS & DOORS, AND HOUSE TRIM. REMOVE AND REINSTALL EXISTING SURFACE MOUNTED ELECTRICAL CIRCUITS INSIDE WALL CAVITY. REMOVE EXTERIOR SIGNAGE AND SECURE/PROTECT FOR REINSTALLATION. INSTALL MOISTURE BARRIER AND NEW WOOD (CYPRESS) SIDING. CLEAN AND REMOVE PAINT FROM WOOD, METAL, AND MASONRY THAT IS TO REMAIN IN PREPARATION FOR PAINTING. PRIME AND APPLY TWO COATS OF PAINT.
5. REMOVE BUILT UP ROOFING SYSTEM AND UNDERLYING…
This is the start of the file's text. The full file is on GovTribe.