This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Department of Veterans Affairs Network Contracting Office 8 (NCO 8) in Tampa, FL, with the solicitation number 36C24825Q1093. The amendment includes a Questions and Answers section providing technical details for a chiller installation project.
The Q&A section specifies critical infrastructure requirements, including 200' of hose for chilled and condenser water connections with 20" and 16" diameter flanged connections respectively, and 200' of power cable for electrical connections. The electrical specifications include 480V voltage and 1800 AMPS available at the disconnect. The project requires one chiller to handle both buildings, with valves available at the water connections. The amendment's primary purpose is to address vendor questions and provide clarification on the technical specifications for the chiller installation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24825Q1093 0006_1.docx | DOCX document | |
| 36C24825Q1093 0006.pdf | ||
| 36C24825Q1093 0005.pdf | ||
| 36C24825Q1093 0005_1.docx | DOCX document | |
| S02 36C24825Q1093 rev c.pdf | ||
| 36C24825Q1093 0004.pdf | ||
| 36C24825Q1093 0004_1.docx | DOCX document | |
| 36C24825Q1093 0003_1.docx | DOCX document | |
| 36C24825Q1093 0002_1.docx | DOCX document | |
| 36C24825Q1093 0002.pdf | ||
| S02 36C24825Q1093 rev b.pdf | ||
| S06 36C24825Q1093 0001.pdf | ||
| 36C24825Q1093 0001_1.docx | DOCX document | |
| 36C24825Q1093_2.docx | DOCX document | |
| S02 36C24825Q1093.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
0003 09-18-2025
NONE
36C248
Department of Veterans Affairs
Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy Suite 525
Tampa FL 33637
36C248
Department of Veterans Affairs
Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy
Tampa FL 33637
To all Offerors/Bidders
36C24825Q1093
X
X X
See CONTINUATION Page
The purpose of this amendment is to address the vendors questions regarding this requirement. Please see the next page for additional details.
Marcus Lewis
VA-VHA-RPOE-2025-0041
Questions and Answers
1. What is the length of hose required to reach the chilled water and condenser water connections at the building?
Answer: 200’ of hose to reach both the chilled/condenser water connections.
2. What type of connections are provided? (Flanged or Victaulic)
Answer: Flanged connections
3. What is the diameter of the water connections?
Answer: 20” chilled water, 16” condenser water
4. Are there valves available at these connections?
Answer: Yes
5. What is the length of power cable to reach the electrical panel/disconnect at the building?
Answer: 200’
6. What is the Voltage available at the panel? (208/480/4160)
Answer: 480
7. How many AMPS are available at the disconnect? (Temp Chiller requires 1,200-1,600 AMPS)
Answer: 1800
8. Is the requirement for one chiller to handle both buildings or is a chiller required for each building?
Answer: One chiller for both buildings