36C24824R0016 0004.pdf
PDF 123 KB Posted
- Attached to
- Y1DA--FY24: NRM (PROJ: 673-23-104) DB Install Fall Protection Anchorage and Guardrails for Bldg 1 and 2
- Solicitation number
- 36C24824R0016
About this file
This document contains an amendment to a federal solicitation and related opportunity details. The amendment provides answers to contractor questions, confirms the proposal due date of February 14, 2024, and adds FAR clause 52.232-18 regarding availability of funds. The related opportunity is a design-build project set aside for Service-Disabled Veteran Owned Small Businesses to install fall protection anchorage and guardrails for two buildings at the James A. Haley VA Medical Center in Tampa, Florida. The estimated value is between $2-5 million. Proposals are due November 22, 2023 and the pre-bid site visit occurred on November 15, 2023.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODECODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 2
0004 673-23-104
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
Tampa FL 33637
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
Tampa FL 33637
To all Offerors/Bidders
36C24824R0016
11-03-2023
X
X X
X
Project Title: DB Install Fall Protection Anchorage and Guardrails for bldgs. 1 and 2 Project #: 673-23-104
The Purpose of this amendment is to provide answers to RFI, add 52.232-18 "Availability of Funds" clause to the RFP.
Phase 2 proposals are due Feb 14, 2024 at 2:00PM EST.
All other terms and conditions remain the same.
POC: David Hernandez, email: david.hernandez1@va.gov
Contracting Specialist David Hernandez
RFI ANSWERS.
Please review the responses below:
1. Will the VA clarify if a counterweight system can be used in lieu of a through mounted system? A counterweight system would eliminate the need for additional work in the areas below the SOW(welding/abatement/etc.)
RFI Answer: This counterweight system will not satisfy the requirement as the through mounted system and the VA will not accept the counterweight system.
2. Will a horizontal lifeline system be required in addition to a guard rail were indicated in the SOW? The horizontal lifeline system is designed separately from the swing stage tie backs. The last rounds of RFIs requested that we install (3) separate systems; a horizontal lifeline, swing stage tie backs and railings. There appears to be some redundancies and overlaps in this request.
RFI Answer: There is no horizontal lifeline system needed. The guard rails are for fall protection. There is no need to have another system performing this requirement.
Adding FAR 52.232-18 “Availability Of Funds”. (Apr 1984) Clause to the RFP.
Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
(End of clause)