This is a Utility Relocation Schedule (URS) document submitted by TECO Peoples Gas, a utility agency/owner, to Hillsborough County for the CR 584 (Waters Ave) at Florida Mining Blvd intersection improvements project (CIP Number: 69600318). The project involves the relocation, adjustment, and protection of existing gas facilities along the roadway corridor. TECO Peoples Gas has identified specific utility work items including lowering a 6-inch carbon steel gas main during Phase I (15 calendar days prior to construction and 4 days during construction), monitoring a 4-inch carbon steel gas main during Phase II (3 calendar days during construction), and adjusting a 4-inch gas valve during sidewalk construction in Phase II (2 calendar days). The utility work is dependent on roadway contractor activities, with estimated material procurement requiring 90 calendar days and other preliminary work requiring 30 calendar days. The document was authorized by Jenna Jackson, Gas Design Project Manager, on May 13, 2025, and received final approval from Hillsborough County Section Manager Sandra Gonzalez on October 9, 2025.

TECO Peoples Gas has established special conditions and constraints for this project, including a 24-hour emergency number (1-877-832-6747) and limitations on crew availability due to emergency response obligations. Normal work hours are Monday through Friday, 8 a.m. to 5 p.m., excluding observed holidays; any work outside these hours must be scheduled 48 hours in advance with crew verification required on the actual workday. The utility requires a copy of the approved contractor's Critical Path Method (CPM) schedule within 5 days of approval and may choose to grout fill and retire gas mains under paved areas as an alternative to removal. TECO Peoples Gas representatives include Jenna Jackson (UAO Project Representative, 813-917-9446) and Javy Vazquez (UAO Field Representative, 813-426-6115), who must be notified in writing prior to starting, stopping, resuming, or completing work. The utility must be notified within 48 hours of any facility location requests and is required to provide as-built information and obtain a utility permit in compliance with Hillsborough County Utility Agreement Management requirements.

View the file

Other files

File Type Posted
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
36-IFB-26-00287 Plans - ROADWAY.pdf PDF
23-Attachment C - URS - NC - Spectrum No Conflict.pdf PDF
15-Attachment A - Construction Sign 2026.pdf PDF
8-Insurance Certificate.doc.doc DOC document
26-Attachment C - URS - TCA- URS-Signed.pdf PDF
34-Performance Bond.pdf PDF
25-Attachment C - URS - Tampa Electric Signed.pdf PDF
42-Agreement - Construction - Stand Alone.pdf PDF
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
45-IFB-26-00287 Contract Terms and Conditions.pdf PDF
19-Attachment C - URS - CrownCastle-Signed.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
38-IFB-26-00287 Plans - Waters-FL Mining SS UTV1.pdf PDF
41-IFB-26-00287 Supplemental Specifications.pdf PDF
4-Application for Payment.pdf.pdf PDF
24-Attachment C - URS - NC - Summit No Conflict Letter.pdf PDF
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
16-Attachment B - GEO - Rpt Rev1 SS.pdf PDF
35-Payment Bond.pdf PDF
37-IFB-26-00287 Plans - SIGNALIZATION.pdf PDF
3-Allowance Authorization Release Form.pdf.pdf PDF
21-Attachment C - URS - FTR Signed.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
33-Bid Bond.doc DOC document
20-Attachment C - URS - FIBERLIGHT -Signed.pdf PDF
28-Attachment C - URS - UNITI FIBER Signed.pdf PDF
17-Attachment C - URS - CenturyLink Signed.pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
22-Attachment C - URS - MCI-Signed.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
43-IFB-26-00287 Insurance Requirements.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
39-IFB-26-00287 Plans - Waters-FL Mining SS UTV2.pdf PDF
31-Attachment D - Permits - Waters Ave. at Florida Mining Blvd.exemption.pdf PDF
30-Attachment D - Permits - SWFWMD Permit Withdrawn.pdf PDF
32-Attachment E - Drainage-Memo.pdf PDF
18-Attachment C - URS - COTW Signed.pdf PDF
44-SBE Goal Participation SBE-1 Form Tutorial (SBE Division v3).mp4 MP4 file
7-Change Order Form.pdf.pdf PDF
40-IFB-26-00287 Project Map.pdf PDF
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
29-Attachment C - URS - Utility Certification Letter 10.8.25.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: CR 584 Plans Dated: 5/2/25 CIP Number: 69600318 Project Name: CR 584 (Waters Ave) at Florida Mining Blvd Utility Agency/Owner (UAO): TECO Peoples Gas

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary Prior to County Project Construction 15 Total Material Procurement 90 During County Project Construction 5 Total Right-of-Way Acquisition As-Built Information _____________ Total Other 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Javy Vazquez Telephone Number: 813-426-6115 UAO Project Representative: Jenna Jackson Telephone Number: 813-917-9446 UAO Field Representative: Javy Vazquez Telephone Number: 813-426-6115 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature) Jenna Jackson

(Printed Name) (Printed Name) (Printed Name) Gas Design Project Manager Utility Coordinator

(Title) (Title) (Title) 5/13/25

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Sandra Gonzalez, P.E. Section Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

Lynn M. Decker

Project Manager

8/28/2025

GonzalezSa Typewritten Text Manny Santos

GonzalezSa Typewritten Text 10/09/2025

GonzalezSa Typewritten Text 10/09/2025

Special Conditions and Constraints

1. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877 TECO PGS (1-877-832-6747).

2. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY AND

LOCATION OF THE EMERGENCY.

3. TECO PEOPLES GAS EMPLOYEES AND SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAY'S (NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, CHRISTMAS EVE DAY AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE REQUESTED FROM THE FDOT, THEIR CONTRACTOR OR SUBCONTRACTOR OUTSIDE OF THESE NORMAL WORKING HOURS MUST BE SCHEDULED 48 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD PREVIOUSLY BEEN

REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED

WEEKEND OR HOLIDAY.

4. A COPY OF THE APPROVED CONTRACTOR’S CPM (CRITICAL PATH METHOD) IS REQUESTED WITHIN 5 DAYS

OF APPROVAL.

5. TECO/PEOPLES GAS MAY GROUT FILL AND RETIRE GAS MAINS THAT ARE UNDER PAVED ROADWAYS AND

DRIVEWAYS AS AN ALTERNATIVE TO REMOVING.

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During 6” CS GM from

190+01.00, 53.5’ RT to

190+21.00, 53.5’ RT

Lower in place, 24” below proposed spread footer foundation

Permitting, staking Phase I 15

4” CS GM from

11+19.00, 33.6’ LT

To remain, provide construction watch during the installation of proposed S-5

Construction of S-5 Phase II 3

4” CS gas valve from

189+24.00, 51.5’ RT

To adjust, final sidewalk grade established by roadway contractor

Construction of sidewalk Phase II 2

2025-10-09T07:42:54-0400
Manuel Santos
2025-10-09T08:43:03-0400
Sandra González