Utility Relocation Work Schedule
This document is a Utility Relocation and Adjustment Schedule (URS) prepared by CenturyLink (Level 3) for Hillsborough County, Florida, detailing utility work coordination for the CR 584 (Waters Ave) at Florida Mining Boulevard Intersection Improvements project (CIP Number 69600318). The project involves the relocation and adjustment of existing fiber optic cable (FOC) in HDPE conduits to accommodate roadway construction activities. CenturyLink's work is divided into two phases: Phase 1 requires three calendar days of preliminary work prior to county project construction for vertical adjustment of eight 1.25-inch and twelve 1.5-inch HDPE conduits with FOC to gain clearance for spread footer placement of mast arm structures between stations 189+92 and 190+45; Phase 2 requires one calendar day of work during construction for holding and adjusting two 2-inch HDPE conduits with FOC during drainage structure placement between stations 190+14 and 190+73. The utility work is dependent upon roadway contractor activities and must be coordinated with proper staking and notification procedures. Work must be performed during normal business hours (8:00 a.m. to 5:00 p.m., Monday through Friday), with 48 hours' notice required for scheduled work and 72 hours' advance notice for work outside normal business hours.
The project representative and authorized utility agent is Matt Anthony, reachable at 239-822-4986 during business hours with an emergency contact number of 800-228-8485 for nights, weekends, and holidays. CenturyLink's work will be performed by its National master contractor in close coordination with the roadway contractor. The utility schedule was signed and accepted by Hillsborough County on October 9, 2025, with final approval by Section Manager Sandra Gonzalez, P.E., on the same date. The document specifies that CenturyLink shall obtain a utility permit, comply with Hillsborough County Utility Agreement Management requirements, provide as-built information, and locate facilities within 48 hours of notice to their representative. No changes were made to the standard form document in this execution.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hillsborough County County Road: CR 584 Plans Dated:5/2/2025 CIP Number: 69600318 Project Name: Waters Ave at Florida Mining Blvd Intersection Improvements Utility Agency/Owner (UAO): LUMEN (LEVEL 3)
NON-CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
Total Preliminary 0 Prior to County Project Construction 3 Total Material Procurement During County Project Construction 1 Total Right-of-Way Acquisition As-Built Information _____________ Total Other * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.
Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.
Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.
The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.
During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Matt Anthony Telephone Number: 239-822-4986 UAO Project Representative: MATT ANTHONY Telephone Number: 239-822-4986 UAO Field Representative: MATT ANTHONY Telephone Number: 239-822-4986 This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.
You MUST signify by selecting or checking which of the following applies:
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough
County:
(Signature) (Signature) (Signature)
MATT ANTHONY
(Printed Name) (Printed Name) (Printed Name) Network Implementation
Program Manager
(Title) (Title) (Title) 5/2/2025
(Date) (Date) (Date)
Final Approval by Hillsborough County:
(Signature) (Date)
Sandra Gonzalez, P.E. Section Manager (Printed Name) (Title)
(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)
Lynn M. Decker
Project Manager
8/28/2025
GonzalezSa Typewritten Text Manny Santos
GonzalezSa Typewritten Text Project Manager
GonzalezSa Typewritten Text 10/08/2025
GonzalezSa Typewritten Text 10/09/2025
Special Conditions and Constraints
1. Existing facilities include HDPE's Conduits with Buried FOC.
2. The Contractor is to contact Matt Anthony Level 3 Employee at 239-822-4986, 48 Hrs. prior to the start of construction.
3. Locate & Protect and Adjust (A Level 3 employee or representative will be present), & Adjustment (Raise or lower the cable(s) with a vertical or horizontal position where needed or possible) activities to be provided by CenturyLink National master contractor who will work closely with the Roadway Contractor.
4. Level 3 and Contractor’s normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
5. Any work during normal business hours not scheduled needs 48 hours notice.
6. Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.
7. Level 3 requests for the Road Contractor to provide Staking prior to activities as listed in Section C.
8. Emergency number for nights, weekends and Level 3 Florida holidays is (800) 228-8485.
C. Disposition of Facilities (List All Existing & Proposed) on Project
TYPE / SIZE /
MATERIAL / OFFSET
TO BASELINE FROM
STA TO STA
DESCRIPTION
OF
UTILITY WORK
DEPENDENT
ACTIVITIES
M.O.T.
PHASE
NUMBER
CONSECUTIVE
CALENDAR
DAYS
Prior During (8)1.25” & (12)1.5”
HDPE WFOC
189+92 47’ RT
190+45 47’ RT
VERTICALLY ADJUST EXISTING
FACILITIES TO GAIN CLEARANCE
OF SPREAD FOOTER
PLACEMENT OF SPEADFOOTER
FOR MAST ARM
PHASE 1
3 0
(2)2” HDPE W/FOC
190+14 59’ LT
190+73 57’ LT
HOLD GUARD AND ADJUST AS
NEEDED DURING PLACEMENT
PLACEMENT OF DRAINAGE
STRUCTURE S-1
PHASE 2 0 1
| 2025-10-08T15:25:36-0400 | |
| Manuel Santos |
| 2025-10-09T08:56:59-0400 | |
| Sandra González |