This is a Utility Relocation Schedule (URS) document executed between Hillsborough County and the City of Tampa Water Department regarding intersection improvements at County Road 584 (Waters Avenue) at Florida Mining Boulevard. The project, identified by CIP Number 69600318 with plans dated May 2, 2025, involves the relocation, adjustment, and protection of water utility facilities within the project corridor. The utility work includes four primary tasks: removal of a 12-inch gate valve at Station 10+92.82, installation of a 12-inch gate valve at Station 11+22.25, removal of an 8-inch gate valve at Station 190+17.94, and installation of an 8-inch gate valve at Station 190+64.82. All utility work is scheduled to occur during county project construction with zero preliminary calendar days and zero calendar days of concurrent activity. The document was signed by the City of Tampa Water Department's authorized representative Randall C. Liuzzo on May 21, 2025, with county acceptance and final approval completed by Sandra Gonzalez, P.E., Section Manager on October 9, 2025.

The schedule establishes specific operational requirements and constraints for project execution. The City of Tampa requires receipt of the county-approved contractor's construction schedule via email to WaterUtilityCoordination@TampaGOV.net and mandates 1.5 weeks' advance written notification prior to work affecting water meter boxes, valve boxes, and related appurtenances. Material for valve box adjustments is available at 3901 East 26th Avenue, Tampa, Florida 33605, with delivery coordination required. The City identified blackout dates when water shutdowns and work cannot be performed: November 23 through December 7, 2024, and December 15, 2024 through January 5, 2025. All City of Tampa water appurtenances must be maintained in operational condition post-resurfacing and cannot be paved over or left in a state that would impede maintenance access. Emergency contact for the City of Tampa Water Department's 24-hour operations is (813) 274-7400.

View the file

Other files

File Type Posted
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
36-IFB-26-00287 Plans - ROADWAY.pdf PDF
23-Attachment C - URS - NC - Spectrum No Conflict.pdf PDF
15-Attachment A - Construction Sign 2026.pdf PDF
8-Insurance Certificate.doc.doc DOC document
26-Attachment C - URS - TCA- URS-Signed.pdf PDF
34-Performance Bond.pdf PDF
25-Attachment C - URS - Tampa Electric Signed.pdf PDF
42-Agreement - Construction - Stand Alone.pdf PDF
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
45-IFB-26-00287 Contract Terms and Conditions.pdf PDF
27-Attachment C - URS - TECO Peoples Gas-Signed.pdf PDF
19-Attachment C - URS - CrownCastle-Signed.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
38-IFB-26-00287 Plans - Waters-FL Mining SS UTV1.pdf PDF
41-IFB-26-00287 Supplemental Specifications.pdf PDF
4-Application for Payment.pdf.pdf PDF
24-Attachment C - URS - NC - Summit No Conflict Letter.pdf PDF
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
16-Attachment B - GEO - Rpt Rev1 SS.pdf PDF
35-Payment Bond.pdf PDF
37-IFB-26-00287 Plans - SIGNALIZATION.pdf PDF
3-Allowance Authorization Release Form.pdf.pdf PDF
21-Attachment C - URS - FTR Signed.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
33-Bid Bond.doc DOC document
20-Attachment C - URS - FIBERLIGHT -Signed.pdf PDF
28-Attachment C - URS - UNITI FIBER Signed.pdf PDF
17-Attachment C - URS - CenturyLink Signed.pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
22-Attachment C - URS - MCI-Signed.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
43-IFB-26-00287 Insurance Requirements.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
39-IFB-26-00287 Plans - Waters-FL Mining SS UTV2.pdf PDF
31-Attachment D - Permits - Waters Ave. at Florida Mining Blvd.exemption.pdf PDF
30-Attachment D - Permits - SWFWMD Permit Withdrawn.pdf PDF
32-Attachment E - Drainage-Memo.pdf PDF
44-SBE Goal Participation SBE-1 Form Tutorial (SBE Division v3).mp4 MP4 file
7-Change Order Form.pdf.pdf PDF
40-IFB-26-00287 Project Map.pdf PDF
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
29-Attachment C - URS - Utility Certification Letter 10.8.25.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 584 Plans Dated: 05/02/2025

CIP Number: 69600318 Project Name: CR 584 (WATERS AVENUE) AT FLORIDA MINING BLVD.

INTERSECTION IMPROVEMENTS

Utility Agency/Owner (UAO): City of Tampa Water Department

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary 0 Prior to County Project Construction 6

Total Material Procurement 0 During County Project Construction 0

Total Right-of-Way Acquisition 0 As-Built Information _____________

Total Other 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: _ Telephone Number: -

UAO Project Representative: Randall C Liuzzo Telephone Number: (813) 274-8756

UAO Field Representative: Randall C Liuzzo Telephone Number: (813) 274-8756

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough County:

(Signature) (Signature) (Signature)

Randall C Liuzzo

(Printed Name) (Printed Name) (Printed Name)

Engineer II

(Title) (Title) (Title)

5/21/2025

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Sandra Gonzalez, P.E. Section Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule) ldecker Stamp ldecker Typewritten Text Lynn M. Decker ldecker Typewritten Text Project Manager ldecker Typewritten Text 8/28/2025

GonzalezSa Typewritten Text Manny Santos

GonzalezSa Typewritten Text Project Manager

GonzalezSa Typewritten Text 10/08/2025

GonzalezSa Typewritten Text 10/09/2025

Special Conditions and Constraints

1. City of Tampa Water must receive (via e-mail to WaterUtilityCoordination@TampaGOV.net) a Hillsborough County approved contractor proposed construction project schedule dated on or after the Hillsborough County official approval/acceptance.

2. In the event of a general water emergency, contact the City of Tampa Water Department's 24-hour emergency number

(813) 274-7400 and WaterDistributionScheduling@TampaGov.net

3. Adjustments to valve boxes, required due to resurfaced roadway adjacent to those boxes, will be made as follows:

a) Material Lead Time: The City of Tampa will need 1.5 weeks (8 working days) notification PRIOR to work at the location of the water meter boxes, valve boxes, tops, and or risers. Such notification may occur during the project construction meetings, but all requests must be presented in writing for record keeping purposes. E-mail to WaterUtilityCoordination@TampaGOV.net is preferred.

b) If there is a case where any of the items listed above is damaged and material is requested, (see Material Lead Time above) the City can provide the required items at:

3901 E. 26th Ave, Tampa Florida 33605 ** Delivery can be coordinated, but a specific DATE must be provided. **

c) All material acquisition requests for the City originating from the County contractor will be directed to the City of Tampa Water Department Field contact. When different, the UAO Project Rep will be carbon copied (CC) on all project related correspondence.

d) After resurfacing operations have been completed, Hillsborough County or its Contractor will ensure all Water valve boxes, meter box lids, hydrants, and all other City of Tampa maintained appurtenances are left in a condition allowing easy operation and access for maintenance. City of Tampa appurtenances will not be paved over, unadjusted, or left in any state where maintenance would be considered unduly difficult or hampered.

4. "Stations" and "offsets" provided in Section C will be understood to be referenced from the project Hillsborough County surveyed construction baseline (Baseline of Construction), as identified in the associated dated HC project plans.

5. City of Tampa Black-out Dates: Wherever applicable, dates the City of Tampa cannot perform water shutdowns and work is limited

[11/23/2024 to 12/07/2024] AND [12/15/2024 to 01/05/2025]

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE / MATERIAL /

OFFSET

TO BASELINE FROM STA

TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

1) 12” Gate Valve

STA 10+92.82 RT 25.52

Remove 12” Gate Valve NA NA 1 0

2) 12” Gate Valve

STA 11+22.25 RT 35.64

Install 12” Gate Valve NA NA 2 0

3) 8” Gate Valve

STA 190+17.94 LT 76.83

Remove 8” Gate Valve NA NA 1 0

4) 8” Gate Valve

STA 190+64.82 LT 76.64

Install 8” Gate Valve NA NA 2 0

2025-05-21T15:07:27-0400
Randall C Liuzzo
2025-10-08T15:26:26-0400
Manuel Santos
2025-10-09T08:56:00-0400
Sandra González