25-Attachment C - URS - Tampa Electric Signed.pdf

PDF 1 MB Posted

Attached to
CR 584 (Waters Ave) at Florida Mining Blvd. Intersection Improvements
Solicitation number
IFB-26-00287
Issued by
Hillsborough County, Florida

About this file

This is a Utility Relocation Schedule (URS) document from Tampa Electric Company (TECO) submitted to Hillsborough County for the CR 584 (Waters Ave) at Florida Mining Blvd intersection improvements project. The document outlines the utility work requirements and coordination procedures for relocating TECO's 13.2 KV overhead electric facilities within the project limits. The project involves installing new poles and associated electrical infrastructure while removing existing facilities once new installations are energized and joint users have vacated the existing poles. Material procurement during county project construction is estimated at 14 calendar days. TECO requires a minimum of 30 calendar days advance notice to schedule any work related to the project, including line cover installation, outages, pole holding, and facility monitoring. The utility work schedule includes multiple phases of installation and removal activities for overhead electric lines, poles, and span guys, with work dependent upon completion of proposed pole installations and receipt of executed utility work schedules and notices to proceed.

Key operational constraints include that TECO line crews will not work in adverse weather conditions and normal work schedules are Monday through Friday from 8 a.m. to 5 p.m., excluding TECO-observed holidays. TECO's line crew availability may be limited due to emergency response requirements. The relocation schedule is contingent upon FDOT beginning construction within 12 months of the TECO representative's signature date; failure to commence construction within this timeframe will void the schedule and require resubmission based on current field conditions. TECO's project management contact is CSADMIN@TECOENERGY.COM, with field representatives Jason T. Payne (813-765-2494) and Robbie Nieman (813-635-6993) designated as primary contacts. An emergency number (877-588-1010) is provided for nights, weekends, and TECO holidays.

View the file

Other files

File Type Posted
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
36-IFB-26-00287 Plans - ROADWAY.pdf PDF
23-Attachment C - URS - NC - Spectrum No Conflict.pdf PDF
15-Attachment A - Construction Sign 2026.pdf PDF
8-Insurance Certificate.doc.doc DOC document
26-Attachment C - URS - TCA- URS-Signed.pdf PDF
34-Performance Bond.pdf PDF
42-Agreement - Construction - Stand Alone.pdf PDF
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
45-IFB-26-00287 Contract Terms and Conditions.pdf PDF
27-Attachment C - URS - TECO Peoples Gas-Signed.pdf PDF
19-Attachment C - URS - CrownCastle-Signed.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
38-IFB-26-00287 Plans - Waters-FL Mining SS UTV1.pdf PDF
41-IFB-26-00287 Supplemental Specifications.pdf PDF
4-Application for Payment.pdf.pdf PDF
24-Attachment C - URS - NC - Summit No Conflict Letter.pdf PDF
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
16-Attachment B - GEO - Rpt Rev1 SS.pdf PDF
35-Payment Bond.pdf PDF
39-IFB-26-00287 Plans - Waters-FL Mining SS UTV2.pdf PDF
31-Attachment D - Permits - Waters Ave. at Florida Mining Blvd.exemption.pdf PDF
30-Attachment D - Permits - SWFWMD Permit Withdrawn.pdf PDF
32-Attachment E - Drainage-Memo.pdf PDF
18-Attachment C - URS - COTW Signed.pdf PDF
44-SBE Goal Participation SBE-1 Form Tutorial (SBE Division v3).mp4 MP4 file
7-Change Order Form.pdf.pdf PDF
40-IFB-26-00287 Project Map.pdf PDF
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
29-Attachment C - URS - Utility Certification Letter 10.8.25.pdf PDF
37-IFB-26-00287 Plans - SIGNALIZATION.pdf PDF
3-Allowance Authorization Release Form.pdf.pdf PDF
21-Attachment C - URS - FTR Signed.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
33-Bid Bond.doc DOC document
20-Attachment C - URS - FIBERLIGHT -Signed.pdf PDF
28-Attachment C - URS - UNITI FIBER Signed.pdf PDF
17-Attachment C - URS - CenturyLink Signed.pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
22-Attachment C - URS - MCI-Signed.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
43-IFB-26-00287 Insurance Requirements.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 584 Plans Dated: 05/02/2025

CIP Number: 69600.318 Project Name: CR 584 (WATERS AVE) AT FLORIDA MINING BLVD

Utility Agency/Owner (UAO): TAMPA ELECTRIC COMPANY

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary Prior to County Project Construction 0

Total Material Procurement During County Project Construction 14

Total Right-of-Way Acquisition As-Built Information _____________

Total Other * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Call 811 Sunshine

UAO Project Representative: Jason T. Payne Telephone Number: 813-765-2494

UAO Field Representative: Robbie Nieman Telephone Number: 813-635-6993

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature)

Jason T. Payne

Lynn M. Decker, P.E.

(Printed Name) (Printed Name) (Printed Name)

Right of Way Liaison

E.O.R.

(Title) (Title) (Title)

9/4/2025

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Section Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

10/7/2025

GonzalezSa Typewritten Text Manny Santos

GonzalezSa Typewritten Text Project Manager

GonzalezSa Typewritten Text 10/08/2025

GonzalezSa Typewritten Text 10/09/2025

Special Conditions and Constraints

SPECIAL NOTATIONS

1. TEC (TAMPA ELECTRIC COMPANY) REQUIRES A MINIMUM OF 30 CALENDAR DAYS TO SCHEDULE ANY TEC WORK RELATED TO THIS PROJECT, INCLUDING BUT NOT LIMITED TO "DURING CONSTRUCTION" WORK IDENTIFIED IN THIS RELOCATION SCHEDULE, REQUESTS FOR THE

INSTALLATION OF LINE COVER, REQUESTS FOR OVERHEAD/UNDERGROUND ELECTRIC OUTAGE(S), REQUESTS FOR TEC POLE HOLDING, AND/OR REQUESTS TO MONITOR ANY TEC FACILITIES WITH SAID REQUESTS BEING INITIATED BY HILLSBOROUGH COUNTY, THE

HILLSBOROUGH COUNTY CONTRACTOR AND/OR THEIR SUBCONTRACTOR. THIS NOTICE INCLUDES POLE REMOVAL ONCE A JOINT USER HAS

VACATED THE FACILITY AND PROPERLY NOTICIFIED TEC FIELD REPRESENTATIVE TO ALLOW SCHEDULING OF ACTIVITY TO OCCUR.

2. FOR SAFETY REASONS, TEC LINE CREWS SHALL NOT WORK IN ADVERSE WEATHER CONDITIONS.

3. THE TEC LINE CREW AVAILABILITY SHALL BE AFFECTED AND/OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS.

THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY OF THE EMERGENCY.

4. TEC AND/OR TEC'S SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TEC

OBSERVED HOLIDAY'S WHICH INCLUDE NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE

FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE DAY AND CHRISTMAS DAY.

5. TEC CAN NOT REMOVE ANY TEC POLES THAT HAVE EXISTING JOINT USERS STILL ATTACHED. SUBSEQUENTLY, ALL JOINT USERS SUCH AS

FRONTIER, SPECTRUM, TRAFFIC, ETC. MUST BE REMOVED BEFORE TEC CAN REMOVE THE POLE ITSELF.

6. IF A NEW TEC ELECTRIC SERVICE MUST BE ESTABLISHED, PLEASE EMAIL ONE SOURCE AT CEREPS@TECOENERGY.COM OR 813-635-1500 AND

REQUEST THE "PROCEDURE FOR ESTABLISHING A NEW ELECTRIC SERVICE". ALSO INCLUDED IN THIS SAME TEC DOCUMENT IS THE

PROCEDURE FOR THE REMOVAL OF AN EXISTING TEC ELECTRIC SERVICE.

7. THIS RELOCATION SCHEDULE WILL BE CONSIDERED VOID SHOULD THE FDOT NOT BEGIN CONSTRUCTION WITHIN 12 MONTHS FROM

SIGNATURE DATE OF TEC REPRESENTATIVE. IF SCHEDULE SHOULD BECOME VOID, TEC WILL THEN REQUIRE THE LATEST SET OF PLANS THAT

REFLECT CURRENT FIELD CONDITIONS AT THAT TIME FOR REVIEW AND RE-WRITE OF SCHEDULE IF DEEMED NECESSARY BY TEC.

EMERGENCY NUMBER FOR NIGHTS, WEEKENDS & TECO HOLIDAYS - 877-588-1010

PROJECT MANAGEMENT: CSADMIN@TECOENERGY.COM

13KV DISTRIBUTION FACILITIES CONTACT: ROBBIE NEIMAN 813-635-6993

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

13.2 KV OE

187+47’ LT 61’ TO

189+ 14’ LT 61’

INSTALL ONCE PROPOSED POLE(S) ARE

INSTALLED

I - 1

POLE

189+ 14’ LT 61’

INSTALL ONCE EXECUTED UWS & NTP IS

RECEIVED

I - 2

13.2 KV OE

189+ 14’ LT 61’ TO

191+18’ LT 61’

13.2 KV OE (SPAN

GUY)

189+42’ RT 49’ TO

189+47’ LT 89’

POLE / (2) DOWN

GUYS

189+47’ LT 89’ /

189+47’ LT 68’

INSTALL ONCE EXECUTED UWS & NTP IS

RECEIVED

I - 2

13.2 KV OE (SPAN

GUY)

189+47’ LT 89’ TO

12+98’ LT 40’

13.2 KV OE

187+47’ LT 61’ TO

189+ 24’ LT 61’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

I - 1

POLE

189+ 24’ LT 61’

REMOVE ONCE JOINT USER HAS

VACATED POLE AND NOTIFIED

TEC

I - 1

13.2 KV OE

189+ 24’ LT 61’ TO

191+18’ LT 61’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

I - 1

13.2 KV OE (SPAN

GUY)

189+42’ RT 49’ TO

189+47’ LT 74’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

I - 1

POLE

189+47’ LT 74’

REMOVE ONCE JOINT USER HAS

VACATED POLE AND NOTIFIED

TEC

I - 1

13.2 KV OE (SPAN

GUY)

189+47’ LT 74’ TO

12+98’ LT 40’

REMOVE ONCE NEW FACILITES HAVE

BEEN INSTALLED AND

ENERGIZED

2025-10-08T15:14:27-0400
Manuel Santos
2025-10-09T08:58:08-0400
Sandra González