This is a Utility Relocation Schedule (URS) document prepared by Frontier Communications for Hillsborough County's CR-584 (Waters Avenue) at Florida Mining Blvd. Intersection Improvements project, with plans dated April 5, 2024 and CIP Number 69600318. The document outlines Frontier's facility relocation, adjustment, installation, and protection activities required for the county road construction project. Frontier Communications estimates 60 calendar days for preliminary work and material procurement prior to county project construction, with 16 estimated calendar days for construction items during the county project. The project involves the relocation and removal of existing Frontier facilities including various conduit sizes, fiber optic cables (600-BT, 900-BT, 48-BFO, 144-BFO), handholes, and vaults across multiple stations along the project corridor from Sta. 187+40 to Sta. 192+50. Frontier working days are limited to normal business hours, Monday through Friday, 7:30 a.m. to 5:00 p.m., excluding holidays, with all relocation activities contingent upon receipt of approved permits and the utility work schedule. The road contractor is required to provide 48-hour notice prior to construction commencement and must maintain communication with Frontier's representative, Albert Rivas, throughout the project duration.

The work schedule was signed and approved on October 8, 2025, by Manny Santos as Project Manager and Sandra Gonzalez, P.E., as Section Manager for Hillsborough County, with final approval dated October 9, 2025. Frontier Communications designated Kraivuth Choeykrajang as the UAO Project Representative and Paul Lineberry as the UAO Field Representative, both listed as authorized contacts for project coordination. Key special conditions include Frontier's requirement for a copy of the Critical Path Method (CPM) schedule upon approval by Hillsborough County, prohibition of work during adverse weather conditions per OSHA regulations, and Frontier's right to maintain access throughout the project duration to monitor and maintain facilities for service continuity. The document confirms that no changes were made to the standard form document, and all parties acknowledge their understanding and acceptance of the specified work schedule and coordination requirements.

View the file

Other files

File Type Posted
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
36-IFB-26-00287 Plans - ROADWAY.pdf PDF
23-Attachment C - URS - NC - Spectrum No Conflict.pdf PDF
15-Attachment A - Construction Sign 2026.pdf PDF
8-Insurance Certificate.doc.doc DOC document
26-Attachment C - URS - TCA- URS-Signed.pdf PDF
34-Performance Bond.pdf PDF
25-Attachment C - URS - Tampa Electric Signed.pdf PDF
42-Agreement - Construction - Stand Alone.pdf PDF
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
45-IFB-26-00287 Contract Terms and Conditions.pdf PDF
27-Attachment C - URS - TECO Peoples Gas-Signed.pdf PDF
19-Attachment C - URS - CrownCastle-Signed.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
38-IFB-26-00287 Plans - Waters-FL Mining SS UTV1.pdf PDF
41-IFB-26-00287 Supplemental Specifications.pdf PDF
4-Application for Payment.pdf.pdf PDF
24-Attachment C - URS - NC - Summit No Conflict Letter.pdf PDF
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
16-Attachment B - GEO - Rpt Rev1 SS.pdf PDF
35-Payment Bond.pdf PDF
37-IFB-26-00287 Plans - SIGNALIZATION.pdf PDF
3-Allowance Authorization Release Form.pdf.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
33-Bid Bond.doc DOC document
20-Attachment C - URS - FIBERLIGHT -Signed.pdf PDF
28-Attachment C - URS - UNITI FIBER Signed.pdf PDF
17-Attachment C - URS - CenturyLink Signed.pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
22-Attachment C - URS - MCI-Signed.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
43-IFB-26-00287 Insurance Requirements.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
39-IFB-26-00287 Plans - Waters-FL Mining SS UTV2.pdf PDF
31-Attachment D - Permits - Waters Ave. at Florida Mining Blvd.exemption.pdf PDF
30-Attachment D - Permits - SWFWMD Permit Withdrawn.pdf PDF
32-Attachment E - Drainage-Memo.pdf PDF
18-Attachment C - URS - COTW Signed.pdf PDF
44-SBE Goal Participation SBE-1 Form Tutorial (SBE Division v3).mp4 MP4 file
7-Change Order Form.pdf.pdf PDF
40-IFB-26-00287 Project Map.pdf PDF
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
29-Attachment C - URS - Utility Certification Letter 10.8.25.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: 584 Plans Dated: 4/5/2024

CIP Number: 69600318 Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection Improvements

Utility Agency/Owner (UAO): Frontier Communications

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary 60 Prior to County Project Construction 52

Total Material Procurement 60 During County Project Construction 16

Total Right-of-Way Acquisition As-Built Information _____________

Total Other * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Paul Lineberry Telephone Number: 813-838-8867

UAO Project Representative: Kraivuth Choeykrajang Telephone Number: 813-877-7480

UAO Field Representative: Paul Lineberry Telephone Number: 813-838-8867

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature)

Kraivuth Choeykrajang

(Printed Name) (Printed Name) (Printed Name)

Engr, Network III

(Title) (Title) (Title)

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Sandra Gonzalez, P.E. Section Manager (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

10/01/2025

Lynn Decker

Engineer of Record

10/7/2025

GonzalezSa Typewritten Text Manny Santos

GonzalezSa Typewritten Text Project Manager

GonzalezSa Typewritten Text 10/08/2025

GonzalezSa Typewritten Text 10/09/2025

Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection

Special Conditions and Constraints

1: Frontier Relocation Activities will not commence until receipt of Approved UWS which created based on Hillsborough

County road plans dated on this UWS form, and Approved Permits.

2: Frontier Inspector will be available for the pre-construction meeting in the field and be the point of contact for Frontier

Construction for the Road Contractor for the duration of the project.

3: Frontier Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays).

Frontier will arrange any works after hour with an advance notice through Frontier field representative.

4: Frontier facilities that are to remain in place will be located and protected during construction.

5: The Road Contractor is to notify Frontier Albert Rivas at 813-431-2909, 48 hours prior to start of construction.

6: Frontier is to have access throughout the duration of the project to monitor and maintain Frontier facilities for the ability to provide service.

7: Extreme caution is to be used when excavating near or around Frontier facilities and the road contractor is to contact

Frontier 48 hours (Mon-Fri) prior to monitoring / adjustments during construction.

8: Frontier requests a copy of the CPM upon approval by Hillsborough County.

9: Per OSHA Regulations, Frontier will prohibit work to be performed when adverse weather conditions that would jeopardize the safety of Frontier's crews.

Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During

Sta. 187+40 to Sta. 192+50, LT

All Frontier existing facilities unless otherwise noted.

To Remain None N/A 0 0

Sta. 189+47, 69’ LT to Sta. 189+60, 132’ LT to

Sta. 189+43, 131’ LT

600-BT

To Be Removed where Accessible, Placed Out of Service

Installation and Activation of Proposed Facilities

N/A 4 0

Sta. 189+47, 69’ LT to Sta. 189+57, 91’ LT to Sta. 189+43, 131’ LT

900-BT

To Be Removed where Accessible, Placed Out of Service

Installation and Activation of Proposed Facilities

N/A 4 0

Sta. 189+51, 112 to Sta. 189+51, 127’ LT

48-BFO

To be adjusted

Staking of S-5 prior to county constructon

N/A 2 0

Sta. 189+60, 111’ LT Handhole

To be Removed Installation and Activation of

Proposed Facilities N/A 2 0

Sta. 189+60, 111’ LT to Sta. 189+54, 157’ LT

144-BFO

To Be Removed where Accessible, Placed Out of Service

Installation and Activation of Proposed Facilities

Phase II 0 4

Sta. 189+60, 109’ to Sta. 189+83, 111’ LT, 48-BFO, 900-BT &

144-BFO, cables exit

H/H to the east

To Be Removed where Accessible, Placed Out of Service

Staking and Construction of 18” RCP from S-4 to S-3, Installation and Activation of Proposed Facilities Phase II 0 4

Sta. 189+83, 110’ to Sta. 190+10, 111’ LT, Conduit w/48-BFO, 900-BT & 144-BFO

To Be Placed Out of Service and Grout Filled

Staking and Construction of 18” RCP from S-4 to S-3, Installation and Activation of Proposed Facilities Phase III 0 4

Sta. 190+10, 110’ LT to Sta. 190+82, 78’ LT, 900-BT, cable continues south before heading east

To Be Removed where Accessible, Placed Out of Service

Installation and Activation of Proposed Facilities

N/A 3 0

Sta. 190+10, 110’ LT to Sta. 190+30, 72’ LT, 48-BFO & 144-BFO, cables continue south to 3’ x 5’ H/H Vault

To Be Removed where Accessible, Placed Out of Service

Installation and Activation of Proposed Facilities

N/A 3 0

Sta. 190+10, 157’ LT to Sta. 190+30, 72’ LT

2-4” Vacant Conduits

To Be Removed where Accessible, Placed Out of Service

Construction of 30” RCP from S-3 to S-2 and from S-2 to S-1

Phase III 0 3

Sta. 190+30, 72’ LT, 3 x 5’ H/H Vault

To Be Removed Installation and Activation of

Proposed Facilities N/A 3 0

Sta. 190+30, 72’ LT to Sta. 190+83, 65’ LT, Adjust existing cables to new H/H location

Adjust/Splice existing cables to proposed H/H

Installation and Activation of Proposed Facilities

N/A 3 0

Sta. 191+56 26’ LT / MH lid MH lid to be adjusted to grade

To be coordinated with the contractor for the final elevation surface Phase III 0 1

Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection

Proposed Facilities:

Sta. 189+47, 69’ LT to Sta. 189+43, 131’ LT

Place 2-4” Conduits w/BT & BFO cable by DB/Open Trench @ 36” Min. DOC to X-Box, Cut-over of existing facilities

Approved UWS, Permits and Material Acquisition

N/A 3 0

Sta. 189+47, 98’ LT H/H

Place H/H and splice proposed 48- BFO with existing 48-BFO cable

Approved UWS, Permits and Material Acquisition

N/A 3 0

Sta. 189+43, 131’ LT to Sta. 189+54, 157’ LT

Place 2-4” Conduits w/144-BFO, 48-BFO and 900-BT by DB/Open

Trench @ 36” Min. DOC from X-Box to Proposed H/H

Approved UWS, Permits and Material Acquisition

N/A 4 0

Sta. 189+54, 157’ LT to Sta. 190+10, 157’ LT

Place 2-4” Conduits w/144-BFO, 48- BFO and 900-BT by DB @ 48” Min.

DOC

Approved UWS, Permits and Material Acquisition

N/A 5 0

Sta. 189+54, 157’ LT H/H

Place H/H and splice existing 144- BFO with proposed BFO cable

Approved UWS, Permits and Material Acquisition

N/A 3 0

Sta. 190+10, 157’ LT to Sta. 190+83, 65’ LT

Place 2-4” Conduits w/144-BFO, 48- BFO and 900-BT by DB/Open Trench @ 36” Min. DOC from

Proposed H/H to Proposed H/H

Approved UWS, Permits and Material Acquisition

N/A 5 0

Sta. 190+83, 65’ LT Place Handhole and splice proposed cables with existing cables

Approved UWS, Permits and Material Acquisition

N/A 5 0

2025-10-08T15:28:31-0400
Manuel Santos
2025-10-09T08:50:41-0400
Sandra González