This is a Utility Relocation Schedule (URS) document prepared by Frontier Communications for Hillsborough County's CR-584 (Waters Avenue) at Florida Mining Blvd. Intersection Improvements project, with plans dated April 5, 2024 and CIP Number 69600318. The document outlines Frontier's facility relocation, adjustment, installation, and protection activities required for the county road construction project. Frontier Communications estimates 60 calendar days for preliminary work and material procurement prior to county project construction, with 16 estimated calendar days for construction items during the county project. The project involves the relocation and removal of existing Frontier facilities including various conduit sizes, fiber optic cables (600-BT, 900-BT, 48-BFO, 144-BFO), handholes, and vaults across multiple stations along the project corridor from Sta. 187+40 to Sta. 192+50. Frontier working days are limited to normal business hours, Monday through Friday, 7:30 a.m. to 5:00 p.m., excluding holidays, with all relocation activities contingent upon receipt of approved permits and the utility work schedule. The road contractor is required to provide 48-hour notice prior to construction commencement and must maintain communication with Frontier's representative, Albert Rivas, throughout the project duration.
The work schedule was signed and approved on October 8, 2025, by Manny Santos as Project Manager and Sandra Gonzalez, P.E., as Section Manager for Hillsborough County, with final approval dated October 9, 2025. Frontier Communications designated Kraivuth Choeykrajang as the UAO Project Representative and Paul Lineberry as the UAO Field Representative, both listed as authorized contacts for project coordination. Key special conditions include Frontier's requirement for a copy of the Critical Path Method (CPM) schedule upon approval by Hillsborough County, prohibition of work during adverse weather conditions per OSHA regulations, and Frontier's right to maintain access throughout the project duration to monitor and maintain facilities for service continuity. The document confirms that no changes were made to the standard form document, and all parties acknowledge their understanding and acceptance of the specified work schedule and coordination requirements.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hillsborough County County Road: 584 Plans Dated: 4/5/2024
CIP Number: 69600318 Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection Improvements
Utility Agency/Owner (UAO): Frontier Communications
NON-CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
CONSTRUCTION ITEMS
ESTIMATED
*CALENDAR DAYS
Total Preliminary 60 Prior to County Project Construction 52
Total Material Procurement 60 During County Project Construction 16
Total Right-of-Way Acquisition As-Built Information _____________
Total Other * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.
Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.
Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.
The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.
During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: Paul Lineberry Telephone Number: 813-838-8867
UAO Project Representative: Kraivuth Choeykrajang Telephone Number: 813-877-7480
UAO Field Representative: Paul Lineberry Telephone Number: 813-838-8867
This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.
You MUST signify by selecting or checking which of the following applies:
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough
County:
(Signature) (Signature) (Signature)
Kraivuth Choeykrajang
(Printed Name) (Printed Name) (Printed Name)
Engr, Network III
(Title) (Title) (Title)
(Date) (Date) (Date)
Final Approval by Hillsborough County:
(Signature) (Date)
Sandra Gonzalez, P.E. Section Manager (Printed Name) (Title)
(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)
10/01/2025
Lynn Decker
Engineer of Record
10/7/2025
GonzalezSa Typewritten Text Manny Santos
GonzalezSa Typewritten Text Project Manager
GonzalezSa Typewritten Text 10/08/2025
GonzalezSa Typewritten Text 10/09/2025
Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection
Special Conditions and Constraints
1: Frontier Relocation Activities will not commence until receipt of Approved UWS which created based on Hillsborough
County road plans dated on this UWS form, and Approved Permits.
2: Frontier Inspector will be available for the pre-construction meeting in the field and be the point of contact for Frontier
Construction for the Road Contractor for the duration of the project.
3: Frontier Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays).
Frontier will arrange any works after hour with an advance notice through Frontier field representative.
4: Frontier facilities that are to remain in place will be located and protected during construction.
5: The Road Contractor is to notify Frontier Albert Rivas at 813-431-2909, 48 hours prior to start of construction.
6: Frontier is to have access throughout the duration of the project to monitor and maintain Frontier facilities for the ability to provide service.
7: Extreme caution is to be used when excavating near or around Frontier facilities and the road contractor is to contact
Frontier 48 hours (Mon-Fri) prior to monitoring / adjustments during construction.
8: Frontier requests a copy of the CPM upon approval by Hillsborough County.
9: Per OSHA Regulations, Frontier will prohibit work to be performed when adverse weather conditions that would jeopardize the safety of Frontier's crews.
Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection
C. Disposition of Facilities (List All Existing & Proposed) on Project
TYPE / SIZE /
MATERIAL / OFFSET
TO BASELINE FROM
STA TO STA
DESCRIPTION
OF
UTILITY WORK
DEPENDENT
ACTIVITIES
M.O.T.
PHASE
NUMBER
CONSECUTIVE
CALENDAR
DAYS
Prior During
Sta. 187+40 to Sta. 192+50, LT
All Frontier existing facilities unless otherwise noted.
To Remain None N/A 0 0
Sta. 189+47, 69’ LT to Sta. 189+60, 132’ LT to
Sta. 189+43, 131’ LT
600-BT
To Be Removed where Accessible, Placed Out of Service
Installation and Activation of Proposed Facilities
N/A 4 0
Sta. 189+47, 69’ LT to Sta. 189+57, 91’ LT to Sta. 189+43, 131’ LT
900-BT
To Be Removed where Accessible, Placed Out of Service
Installation and Activation of Proposed Facilities
N/A 4 0
Sta. 189+51, 112 to Sta. 189+51, 127’ LT
48-BFO
To be adjusted
Staking of S-5 prior to county constructon
N/A 2 0
Sta. 189+60, 111’ LT Handhole
To be Removed Installation and Activation of
Proposed Facilities N/A 2 0
Sta. 189+60, 111’ LT to Sta. 189+54, 157’ LT
144-BFO
To Be Removed where Accessible, Placed Out of Service
Installation and Activation of Proposed Facilities
Phase II 0 4
Sta. 189+60, 109’ to Sta. 189+83, 111’ LT, 48-BFO, 900-BT &
144-BFO, cables exit
H/H to the east
To Be Removed where Accessible, Placed Out of Service
Staking and Construction of 18” RCP from S-4 to S-3, Installation and Activation of Proposed Facilities Phase II 0 4
Sta. 189+83, 110’ to Sta. 190+10, 111’ LT, Conduit w/48-BFO, 900-BT & 144-BFO
To Be Placed Out of Service and Grout Filled
Staking and Construction of 18” RCP from S-4 to S-3, Installation and Activation of Proposed Facilities Phase III 0 4
Sta. 190+10, 110’ LT to Sta. 190+82, 78’ LT, 900-BT, cable continues south before heading east
To Be Removed where Accessible, Placed Out of Service
Installation and Activation of Proposed Facilities
N/A 3 0
Sta. 190+10, 110’ LT to Sta. 190+30, 72’ LT, 48-BFO & 144-BFO, cables continue south to 3’ x 5’ H/H Vault
To Be Removed where Accessible, Placed Out of Service
Installation and Activation of Proposed Facilities
N/A 3 0
Sta. 190+10, 157’ LT to Sta. 190+30, 72’ LT
2-4” Vacant Conduits
To Be Removed where Accessible, Placed Out of Service
Construction of 30” RCP from S-3 to S-2 and from S-2 to S-1
Phase III 0 3
Sta. 190+30, 72’ LT, 3 x 5’ H/H Vault
To Be Removed Installation and Activation of
Proposed Facilities N/A 3 0
Sta. 190+30, 72’ LT to Sta. 190+83, 65’ LT, Adjust existing cables to new H/H location
Adjust/Splice existing cables to proposed H/H
Installation and Activation of Proposed Facilities
N/A 3 0
Sta. 191+56 26’ LT / MH lid MH lid to be adjusted to grade
To be coordinated with the contractor for the final elevation surface Phase III 0 1
Project Name: CR-584 (Waters Avenue) at Florida Mining Blvd., Intersection
Proposed Facilities:
Sta. 189+47, 69’ LT to Sta. 189+43, 131’ LT
Place 2-4” Conduits w/BT & BFO cable by DB/Open Trench @ 36” Min. DOC to X-Box, Cut-over of existing facilities
Approved UWS, Permits and Material Acquisition
N/A 3 0
Sta. 189+47, 98’ LT H/H
Place H/H and splice proposed 48- BFO with existing 48-BFO cable
Approved UWS, Permits and Material Acquisition
N/A 3 0
Sta. 189+43, 131’ LT to Sta. 189+54, 157’ LT
Place 2-4” Conduits w/144-BFO, 48-BFO and 900-BT by DB/Open
Trench @ 36” Min. DOC from X-Box to Proposed H/H
Approved UWS, Permits and Material Acquisition
N/A 4 0
Sta. 189+54, 157’ LT to Sta. 190+10, 157’ LT
Place 2-4” Conduits w/144-BFO, 48- BFO and 900-BT by DB @ 48” Min.
DOC
Approved UWS, Permits and Material Acquisition
N/A 5 0
Sta. 189+54, 157’ LT H/H
Place H/H and splice existing 144- BFO with proposed BFO cable
Approved UWS, Permits and Material Acquisition
N/A 3 0
Sta. 190+10, 157’ LT to Sta. 190+83, 65’ LT
Place 2-4” Conduits w/144-BFO, 48- BFO and 900-BT by DB/Open Trench @ 36” Min. DOC from
Proposed H/H to Proposed H/H
Approved UWS, Permits and Material Acquisition
N/A 5 0
Sta. 190+83, 65’ LT Place Handhole and splice proposed cables with existing cables
Approved UWS, Permits and Material Acquisition
N/A 5 0
| 2025-10-08T15:28:31-0400 | |
| Manuel Santos |
| 2025-10-09T08:50:41-0400 | |
| Sandra González |
File details come from the government source that posted it. Updated .