Submittal Register Form Summary
This is a Submittal Register form (dated January 1996) designed as a template for federal construction contracts to track and manage contractor submittals throughout project execution. The form provides a comprehensive checklist of required submissions organized by construction phase and submittal category.
The form requires contractors to submit preconstruction submittals (SD-01) including schedules of prices, contact personnel lists, construction schedules, equipment delivery schedules, accident prevention plans, activity hazard analyses, crane work plans and certifications, traffic control plans, environmental protection plans, preconstruction surveys, storm water permits, and notices of intent. Product data submittals (SD-03) include backflow preventers and supporting documentation. Test reports (SD-06) encompass monthly exposure reports, accident reports, regulatory citation documentation, crane reports, and backflow preventer tests. Certificates and compliance documents (SD-07) required include confined space entry permits, quality control plan certifications, certificates of compliance, backflow tester certifications, and third-party certifications for barge-mounted mobile cranes. Closeout submittals (SD-11) require interim DD Form 1354 documentation, transfer and acceptance of military real property, submittal registers, and complete submittal packages. The form contains columns for tracking submission dates, approval authority review dates, material needed dates, other reviewer coordination, and remarks for each submittal item, with specification section references included for each requirement.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
Crane Reports
SD-07 CERTIFICATES
Confined Space Entry Permit
Approving AuthorityContractor Schedule Dates
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
Contractor Action
DESCRIPTION
ITEM SUBMITTED
(Enter Contractor Name Here)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
SD-01 PRECONSTRUCTION SUBMITTALS
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
Third Party Certification of Barge-
Mounted Movile Cranes
SD-11 CLOSEOUT SUBMITTALS
Qaulity Control Plan (QC Plan)
Certificate of Compliance
Backflow Tester Certification (If Applicable)
Backflow Preventer Tests (If Applicable)
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicab
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
Backflow Preventers Certificate (If Applicable)