511/26386. KMM; Olympia Readiness Ctr - Addition
Solicitation number
RFP 171 260000002318 3
Issued by
Michigan

About this file

This is a DD Form 1390S/1 and DD Form 1391 military construction project request submitted by the Army National Guard (ARNG) for the State of Michigan regarding a National Guard Readiness Center Addition/Alteration at Detroit Olympia, Detroit, MI. The project encompasses a specially designed permanent National Guard Readiness Center featuring a 36,531 square-foot addition, a 13,976 square-foot alteration, and a 7,150 square-foot unheated vehicle storage shed addition. The facility will include a backup/emergency generator, organizational vehicle parking, comprehensive interior design services, utility systems (gas, electric, water, and wastewater), information systems, fire detection and alarm systems, stormwater drainage, security fencing, exterior security lighting, photovoltaic systems, and anti-terrorism/force protection measures. The project follows a Design-Bid-Build acquisition strategy with design estimated at 35 percent completion by October 2026, 65 percent by March 2028, and full design completion by September 2028. Construction contract award is scheduled for October 2030, with construction commencing in October 2030 and completion targeted for October 2028, based on an area construction cost index of 1.05 for the Detroit facility.

The total project cost is $45,334,000, with the federal government funding $34,000,000 and Michigan providing a state share of $11,334,000. The cost estimate includes primary facility construction totaling $35,143,000 and supporting facility improvements totaling $6,525,000, with additional allocations for contingencies (5 percent), supervision and inspection (3 percent), commissioning (0.6 percent), and design services. The project includes comprehensive sustainability and energy efficiency measures, with an energy study and life cycle cost analysis to be documented during the 35 percent design phase. The facility will comply with DoD's Unified Facilities Code, all local, state, and federal building codes, ADA accessibility requirements, and anti-terrorism standards. The project is not located in a 100-year floodplain and will comply with the Army's one square-foot for one square-foot disposal policy through disposal of 4,681 square feet. Supporting equipment includes 468 authorized and actual personnel, 214 wheeled vehicles, 128 trailers, 34 pieces of equipment exceeding 30 feet, and 9 fuel trucks.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD Form 1390S/1, JUL 99 PREVIOUS EDITION IS OBSOLETE Page 1 of 2

1. COMPONENT

ARNG

FY 2029 GUARD AND RESERVE

MILITARY CONSTRUCTION

2. DATE

28 Apr 26

3. INSTALLATION AND LOCATION

Detroit Olympia, Detroit, MI

4. AREA CONSTR COST INDEX

1.05

Reservists 3 weekends/month

7. PROJECTS REQUESTED IN THIS PROGRAM (DESIGN STATUS)

CATEGORY

CODE

PROJECT TITLE SCOPE COST ($000) START COMPLETE

17180

National Guard Readiness Center Addition/ Alteration

SF 34,000 /2026 /202

, m2

8. STATE RESERVE FORCES FACILITIES BOARD RECOMMENDATION

Facilities identified in item 7 have been examined by Joint Service Reserve Component Facility Board (JSRCFB) for possible joint use/expansion. The Board recommends unilateral construction.

21 AUG 2025

(Date)

9. LAND ACQUISITION REQUIRED

None

(Number of Acres)

10. PROJECTS PLANNED IN NEXT FOUR YEARS

CATEGORY

CODE

PROJECT TITLE SCOPE COST ($000)

N/A NONE

A SITE SURVEY HAS BEEN COMPLETED AND THE SITE IS SUITABLE FOR CONSTRUCTION OF THE

PROPOSED PROJECT AT THE ESTIMATED COST INDICATED.

DD Form 1390S/1, JUL 99 PREVIOUS EDITION IS OBSOLETE Page 2 of 2

ARNG

FY 2029 GUARD AND RESERVE

MILITARY CONSTRUCTION

2. DATE

28 Apr 26

3. INSTALLATION AND LOCATION

Detroit Olympia, Detroit, MI

4. AREA CONSTR COST INDEX

1.05

11. PERSONNEL STRENGTH AS OF: 27/04/26

ENLISTED

12. RESERVE UNIT DATA

STRENGTH

UIC UNIT DESIGNATION TPSN MTOE/TDA AUTHORIZED ACTUAL

Totals 468 468

13. MAJOR EQUIPMENT AND AIRCRAFT

TYPE ACTUAL

Wheeled Vehicles 214

Trailers 128

Tracked Vehicles 0

Equipment > 30 FT (includes HEMTT PLS Trailers) 34

Fuel Truck 9

HET 0

Totals 385

14. OUTSTANDING POLLUTION AND SAFETY DEFICIENCIES

Air Pollution 0 Water Pollution 0 Safety and Occupational Health 0

DD Form 1391, JUL 99 Page 1 of 10

ARNG FY 2029 MILITARY CONSTRUCTION PROJECT DATA

2. DATE

28 Apr 26

3. INSTALLATION AND LOCATION

Detroit Olympia, Detroit, MI

4. PROJECT TITLE

National Guard Readiness Center Addition/Alteration

5. PROGRAM ELEMENT 6. CATEGORY CODE 7. PROJECT NUMBER

260282

8. PROJECT COST ($000)

0505896A 17180 34,000

9. COST ESTIMATES

ITEM U/M QUANTITY UNIT COST COST ($000)

Primary Facility Totals: 35143

17180 Readiness Center Addition SF 36,531 662.83 ( 24214) 17180 Readiness Center Alteration SF 13,976 442.01 ( 6178) 44263 Unheated Encl/Shed-TP Vehicle Storage Addition SF 7,150 326.40 ( 2334)

81160 Backup/Emergency Generator EA 1 150,000.00 ( 150) 85210 Rigid Pavement for MEP SY 3,475 184.76 ( 642) 88042 Enhanced AT/FP (RC Only) LS - 2%- ( 311) 00005 Sustainability/Energy Measures LS - 2%- ( 314) 00000 Cybersecurity LS - ($250k/sys) ( 1000)

Supporting Facility Totals: 6525

85225 Rigid Concrete Paving SY 4,158 184.00 ( 765)

85215 Flexible Paving SY 15,450 150.00 ( 2318)

87210 Security Fencing LF 2,310 460.00 ( 1063)

85220 Curbing (Rigid) LF 2,798 180.00 ( 504)

85220 Sidewalks SY 609 180.00 ( 110)

81230 Exterior Security Lighting EA 1 90,000 ( 90)

69030 Detached Facility Sign EA 1 5,000 ( 5)

84330 Exterior Fire Protection LS 1 100,000 ( 100)

81122 Photovoltaic LS 1 150,000 ( 150)

81242 Utilities: Gas LS 1 90,000 ( 90)

82410 Utilities: Electric LS 1 90,000 ( 90)

84210 Utilities: Water LS 1 90,000 ( 90)

83210 Utilities: Wastewater/Sewer LS 1 90,000 ( 90)

87110 Stormwater Drainage LS 1 110,000 ( 110)

13260 Information Systems LS 1 240,000 ( 240)

93220 Site Improvement LS 1 550,000 ( 550)

14915 Anti-Terrorism/Force Protection LS 1 150,000 ( 150)

TOTAL CONSTRUCTION COST 41668

DD Form 1391, JUL 99 Page 2 of 3

ARNG FY 2029 MILITARY CONSTRUCTION PROJECT DATA

2. DATE

28 Apr 26

3. INSTALLATION AND LOCATION

Detroit Olympia, Detroit, MI

4. PROJECT TITLE

National Guard Readiness Center Addition/Alteration

5. PROJECT NUMBER

260282

9. COST ESTIMATES (Con�t)

Contingencies (5.0%) ( 2083)

Supervision, Inspection and Overhead (3.0%) ( 1312)

Commissioning (0.6%) ( 271)

Design Build (4.0%) ( 0)

Design During Construction ( 0)

TOTAL PROJECT COST 45334

State Share ( 11334)

TOTAL FEDERAL COST 34000

TOTAL FEDERAL COST (ROUNDED)

1-5M(50k)5-10M(100k)10-15m(200k)15-20m(500k)20M+(1M) 34,000

Equipment Funded Other Appr (Non-Add) ( 3790)

10. DESCRIPTION OF PROPOSED CONSTRUCTION

A specially designed National Guard Readiness Center of permanent construction.

The National Guard Readiness Center includes the following items that are integral to the facility: Backup/Emergency Generator, Organizational Vehicle Parking (Paved), Unheated Enclosed/Shed-TP vehicle storage addition.

Comprehensive interior design services are requested. This facility will be designed to meet Industry Standards as well as all local, State, and Federal building codes and as per 42 U.S. Code 4154. Construction will include all utility services, information systems, fire detection and alarm systems, roads, walks, curbs, gutters, storm drainage, parking areas and site improvements.

Facilities will be designed to a minimum life of 50 years in accordance with DoD's Unified Facilities Code (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance as per ASA(IE&E) Sustainable Design and Development Policy updated 2017. Access for individuals with disabilities will be provided. Antiterrorism measures in accordance with the DoD Minimum Antiterrorism for building standards will be provided. This project will comply with the Army 1 SQFT for 1 SQFT disposal policy through the disposal of 4 ,681 SQFT.

MISSION: Current A/C TONNAGE: 270

DD Form 1391, JUL 99 Page 3 of 3

ARNG FY 2029 MILITARY CONSTRUCTION PROJECT DATA

2. DATE

28 Apr 26

3. INSTALLATION AND LOCATION

Detroit Olympia, Detroit, MI

4. PROJECT TITLE

National Guard Readiness Center Addition/Alteration

5. PROJECT NUMBER

260282

IMPACT IF NOT PROVIDED: (Cont.)

10. Required assessments have been made for supporting facilities and the project is not in a 100-year floodplain in accordance with Executive Order 11988.

Date

12a. SUPPLEMENTAL DATA

OCT/2026

35% 65%

MAR/2028

Yes Yes

SEP/2028

OCT/2028

A. Estimated Execution Data:

(1) Acquisition Strategy: Design-Bid-Build

(2) Design Data:

(a) Design or Request for Proposal (RFP) Started:

(b) Percent of Design Completed as of DEC 2026

(c) Percent of Design Completed as of JAN 2028

(d) Design or RFP Complete.

(e) Total Design Cost ($000):

(f) Energy Study and/or Life Cycle Cost Analysis performed:

(g) Standard or Definitive Design Used?

(3) Construction Data:

(a) Contract Award:

(b) Construction Start:

(c) Construction Complete:

OCT/2030

Energy and Life Cycle Costs: An energy study and life cycle cost analysis will be documented during the conceptual (35%) design.

File details come from the government source that posted it. Updated .