This is a memorandum from the National Guard Bureau to the Construction and Facilities Management Officer of the Michigan Army National Guard (MIARNG) regarding initial design authority for a National Guard Readiness Center addition in Detroit, Michigan (Project Number 260282), programmed for the FY29 Military Construction (MCNG) program. The project authorizes the negotiation of an Architect-Engineer contract for design services using the Design-Bid-Build construction delivery method, with the State serving as the construction agent under state contracting procedures. The approved scope encompasses 57,657 square feet of addition and new construction including support structures. Design deliverables are required on a specific schedule: a Concept Design (30%) must be submitted to ARNG-IEI-C no later than December 15, 2026, and 35% design approval is required before submission of the Budget Estimate Submission to the Office of the Secretary of Defense, typically between February and March 2027. The memorandum references applicable regulations and provides guidance on design contract execution, federal reimbursement limitations for redesign efforts, and subsequent facility requirement submissions to the ARNG Requirement & Analysis system no later than two fiscal years prior to project completion.

The total estimated project cost is $45,334,000, comprised of $41,668,000 in construction costs, $2,083,000 for contingency, $1,312,000 for supervision, inspection, and overhead, and $271,000 for commissioning. The federal project cost is estimated at $34,000,000, with the State of Michigan contributing $11,334,100. Federal reimbursement for design services is limited to the amount specified in the approved Military Construction Cooperative Agreement (MCCA). The memorandum emphasizes that the state must coordinate with the ARNG-Construction Branch for authorization levels and that failure to meet design milestones or conform to ARNG design criteria may result in project removal from the Future Years Defense Program (FYDP) and consideration for placement on an Unfunded Priority List (UPL).

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL GUARD BUREAU

111 SOUTH GEORGE MASON DRIVE

ARLINGTON VA 22204-1373

ARNG-IEZ 22 May 2026

MEMORANDUM FOR Construction and Facilities Management Officer, MIARNG, 3411 N Martin Luther King Jr Blvd, Lansing, MI

SUBJECT: Initial Design Authority for National Guard Readiness Center, Detroit, MI, PN 260282, FY29, Army National Guard Military Construction

1. References.

a. NGR 415-5, Army National Guard (ARNG) Military Construction (MCNG) Program Development and Execution, 6 March 15

b. NG Pam 415-12, Army National Guard Facilities Allowances, 25 January 15

c. Under Secretary of Defense memorandum (New Military Construction Budget Estimate Requirements), 17 March 2020

d. Under Secretary of the Army memorandum (Policy Guidance for Programming Army Military Construction Projects), 12 March 2024

2. We have programmed this project for execution in the FY29 Military Construction Program and based cost estimates upon that construction year. The DD Forms 1390/91 dated 28 Apr 26 for the subject facility (Encl) has been reviewed and approved. These documents show an estimated construction cost of $41,668,000; with $2,083,000 for Contingency; $1,312,000 for Supervision, Inspection, and Overhead; and $271,000 for Commissioning for a total project cost of $45,334,000. The total estimated Federal project cost is $34,000,000. The State share for this project is $11,334,100. The total approved scope for this project is 57,657 square feet of addition and new construction to include support structures. The Construction Deliver Method has been identified as Design-Bid-Build. The Construction Agent is identified as being State w/ State Contracting Procedures.

3. You may negotiate an Architect-Engineer contract for the design of the subject project in accordance with the provisions of reference 1.a.

a. Coordinate with ARNG-Construction Branch (ARNG-IEI-C) for instructions on the level of design authorized and limit federal funding for design to the amount shown in the approved Military Construction Cooperative Agreement (MCCA).

ARNG-IEZ

SUBJECT: Initial Design Authority for National Guard Readiness Center, Detroit, MI, PN 260282, FY29, Army National Guard Military Construction (MCNG)

b. Submit the NGB Form 86-R/87-R for Title I/Type A-B Architect-Engineer Services to ARNG-IEI-C to process for approval and funding. Once you execute a design contract, you will not be federally reimbursed for any lost design or redesign efforts resulting from any future change in ARNG construction criteria or failure to conform to ARNG design criteria, which results in redesign efforts.

c. You are required to submit your Concept Design (30%) to IEI-C no later than 15 December three years prior to the programmed year (i.e., a FY29 project is due 15 December 2026).

(1). A project will be removed from the FYDP if it fails to meet 35% design approval before submission of the BES to OSD (typically between February and March) two years prior to the programmed year (i.e., a FY29 project is due February 2027).

(2). The project will receive a removal memo directing continued design as programmed and consideration for an Unfunded Priority List (UPL) candidate upon reaching 35% design.

4. Totals shown in Section 12.b of DD Form 1391 are for planning purposes only. You must submit your requirement in the ARNG Requirement & Analysis’ (ARNG-IES-P) Facility Management Building Tool (FMBT), no later than two fiscal years prior to project completion. Your validated requirement is subject to available funding in the year of need.

5. The point of contact is

FOR THE CHIEF, ARNG G-9, ARMY NATIONAL GUARD: