This document is a military construction project data sheet for the National Guard Vehicle Maintenance Shop in Jackson, KY. The project is being undertaken by the Army National Guard (ARNG) and is programmed for fiscal year 2026 at an estimated total cost of $14.4 million. The project will construct a new 27,910 square foot vehicle maintenance facility to replace the existing flood-damaged shop. The new facility will include maintenance bays, administrative and logistical spaces, vehicle storage, and parking. Design is scheduled to begin in October 2023 and be completed by October 2025, with construction planned from May 2026 through March 2028.
The project is 100% federally funded, as it replaces a National Guard vehicle maintenance facility that was destroyed by multiple catastrophic flood events. The existing site conditions have driven the decision to pursue a new facility on an alternative site outside of the flood plain. The new facility will provide modern, sustainable maintenance capabilities to support the Kentucky National Guard's engineering units and their large construction equipment, which have been forced to travel long distances to access maintenance at overburdened remote locations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
9. COST ESTIMATES
ITEM U/M QUANTITY UNIT COST COST
($000)
Primary Facility Totals: - - 9369 21409 Maintenance Shop SF 22,496 315.00 ( 7086 ) 21470 Bulk POL Storage SF 275 350.00 ( 96 ) 44150 Flammable Materials Facility SF 544 280.00 ( 152 ) 44224 Enclosed Unheated Storage SF 1,265 230.00 ( 291 ) 85210 Rigid Pavement for MEP SY 2,344 120.00 ( 281 ) 44224 Unheated Storage SF 3,000 205.00 ( 615 ) 81122 Electrical Power, Photovoltaic LS - - ( 350 ) 44228 Controlled Waste Facility 85210 SF 330 312.12 ( 103 ) 89220 Energy Management Control System LS - - ( 160 ) 00005 Sustainability / Energy Measures LS - - ( 187 ) 00005 Information Systems LS - - ( 48 ) Supporting Facility Totals: - - 3933 14915 Anti-Terrorism/Force Protection LS - - ( 52 ) 21407 Demolition SF 13,096 36.41 ( 477 ) 69030 Detached Facility Sign EA 1 10,000.00 ( 10 ) 84330 Exterior Fire Protection LS - - ( 144 ) 81230 Exterior Lighting LS - - ( 180 ) 69010 Flagpoles EA 2 7,500.00 ( 15 ) 85215 Flexible Paving SY 865 60.00 ( 52 ) 13260 Information Systems LS - - ( 100 ) 14970 Loading Dock LS - - ( 80 ) 14970 Loading Ramp LS - - ( 60 ) 93310 Offset Disposal LS - - ( 400 ) 00000 Refuse Collection Facility 13260 LS - - ( 42 ) 85225 Rigid Pavement for Operations SY 9,666 85.00 ( 822 ) 87210 Security Fencing LF 1,210 62.00 ( 75 ) 85220 Sidewalks SY 403 100.00 ( 40 ) 93220 Site Improvement LS - - ( 484 ) 87110 Stormwater Drainage LS - - ( 288 )
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION 4. PROJECT TITLE
NATIONAL GUARD VEHICLE MAINTENANCE SHOPJACKSON,KY
5. PROGRAM ELEMENT 6. CATEGORY CODE 7. PROJECT NUMBER 8. PROJECT COST ($000)
0505896A 21407 210029 14,400
DD Form 1391, JUL 99 PREVIOUS EDITION IS OBSOLETE Page 1 of 9
81242 Utilities: Electric LS - - ( 130 ) 83210 Utilities: Waste Water/ Sewer LS - - ( 144 ) 84210 Utilities: Water LS - - ( 144 ) 82410 Utilities:Gas LS - - ( 144 ) 14955 Wash Platform LS - - ( 50 ) 00000 Refuse Collection Facility LS - - ( 0 )
TOTAL CONSTRUCTION COST - - 13302
Contingencies (5.0%) - - ( 665 ) Supervision, Inspection and Overhead (3.0%) - - ( 419 ) Commissioning (0.6%) - - ( 56 )
TOTAL PROJECT COST - - 14442
TOTAL PROJECT COST (ROUNDED) 14,400
Equipment Funded Other Appr (Non-Add) ( 2144)
10. DESCRIPTION OF PROPOSED CONSTRUCTION
A specially designed National Guard Vehicle Maintenance Shop of permanent construction. The National Guard Vehicle Maintenance Shop includes the following items that are integral to the facility; CHP Shelter, Bulk POL Storage, Falmmable Material Facility, Enclosed Unheated Storage, Rigid Pavement for MEP, Unheated Storage, Electircal Power, Photovotaic, Comtrolled Waste Facility, Energy Management Control System, Sustainability/Energy Mesures. Comprehensive interior design services are requested. This facility will be designed to meet Industry Standards as well as all local, State, and Federal building codes and as per Public Law 42 U.S. Code 4154. Construction will include all utility services, information systems, fire detection and alarm systems, roads, walks, curbs, gutters, storm drainage, parking areas and site improvements. [List the special work involved when supporting facility Costs in one or more categories are exceptionally high] Facilities will be designed to a minimum life of 50 years in accordance with DoD's Unified Facilities Code (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance as per ASA(IE&E) Sustainable Design and Development Policy updated 2017. Access for individuals with disabilities will be provided. Antiterrorism measures in accordance with the DoD Minimum Antiterrorism for building standards will be provided. This project will comply with the Army 1 SQFT for 1 SQFT disposal policy through the disposal of the original field maintenance shop and supporting facilities, as we;ll
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
NATIONAL GUARD VEHICLE MAINTENANCE SHOP 210029
DD Form 1391, JUL 99 Page 2 of 9 as a significant portion of 21B31-3101 to total more than 27,910 SQFT disposal.
MISSION: Current A/C TONNAGE: 26
0 SF27,910 SF Adequate: 27,910 SF 11. REQUIREMENT: Substandard:
2,593 m2 0 m2 2,593 m2
1. PROJECT: To construct a new 27,910 Vehicle Maintenance Shop, that supports the maintenenacet, repair, traing, administrative and logistical requirements for KYARNG. The facility will be built upon land owned by the state (Commonwealth of Kentucky). (Current Mission).
2. REQUIREMENT: After the historic 1978 flood severely damaged the Jackson Armory, a replacement Readiness Center was constructed and built. The Commonwealth of Kentucky retained and re-purposed the old armory for sustaining KYARNG equipment as an organizational maintenance shop due to limited available buildable areas capable of accommodating motor vehicle storage and egress requirements. A 1,000-year flood decimated this same facility in 2021. The Commonwealth restored the facility, and then a second 1,000-year flood (Hurrican Ian's land fall) hit the site 15 months later with catastrophic effect. The flooding devastated the current facility beyond feasibility of repair. The existing site conditions drove the decision to pursue repair by replacement on a new site outside a flood plain.
3. CURRENT SITUATION: This project is critical to the state of KY due to the current situation of the Jackson Field Maintenance legacy shop facility was damaged beyond reasonable repair by the July 2022 flood which devastated significant portions of eastern Kentucky.
The vintage 1984 Jackson Shop was converted from Organizational to Field Maintenance in title only and supported its assigned large engineer equipment with legacy maintenance methodology. The old Jackson Drill Hall floor served as the shop maintenance bay, and significant portions of vehicle maintenance was performed outdoors.
At present, KYARNG maintenance technicians assigned to this shop are split between the Hazard RC (40mi away) and Richmond Bluegrass Army Depot FMS (80mi away) performing sustainment on the assigned engineer, heavy construction equipment. This is untenable for two key reasons: 1) heavy construction traffic has increased significantly along narrow, two-lane eastern Kentucky roads. This extra traffic endangers military and civilian operators 5 days per week plus (at least) one weekend per month. And 2) the current operating conditions have cost an extra annual $100,000 O&M bill on the KYARNG G4 for tr
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 3 of 9 avel expenses for maintainers to work away from the Jackson FMS.
The site for this project is in the possession of the state of KY.
Currently, the state of KY has begun the environmental assessment on this project.
The facility where the current operations are being conducted was constructed in 1984.
Site Site FACNO RPUID Cat Built ISR-I F Q C Local Code UID Code Year Year Rating Rating Rating Name
4. IMPACT IF NOT PROVIDED: No maintenance facility exists in southeastern Kentucky. Rejection of this project places heavy construction equipment into weekly vehicle convoys traveling 75 and 100 miles to the closest, overburdened maintenance shops located in either London, Richmond, or Ashland, Kentucky.
This jeopardizes civilian and military vehicle operators, as well as risks readiness of assigned units by placing their equipment even further away from their home station locations.
Further, the unit's equipment readiness will degrade to the point where its unable to respond to the US Army and Commonwealth of Kentucky's missions. The assigned engineering units have proven ready by deploying repeatedly since 9/11 with all manner of combat and domestic support, and status quo impacts their capabiltiy significantly.
5. ADDITIONAL: This project has all physical security measures included in its program and will be coordinated with the installation physical security management team throughout design to ensure all required antiterrorism protection measures are included. Alternative methods of meeting this requirement have been explored during project development. Construction of a new facility or conversion of an existing warehouse represent the only feasible options to meet the requirement. This need for this project was urgent and unforeseen, hence the Deputy Assistant Secretary of the Army (Installations and Housing) cannot certify the need for unilateral/joint use of this facility following construction. The KYARNG intent is to exclude use of this facility by other components since this mission will mirror that of the location it’s replacing. Sustainable principles will be integrated into the design, development, and construction of the project in accordance with Executive Order 13123 and other applicable laws and Executive Orders.
6. PHYSICAL SECURITY: This project has been coordinated with the installation ph
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 4 of 9 ysical security plan, and no physical security measures are required.
7. ANTITERRORISM/FORCE PROTECTION: All required anti-terrorism/force protection measures are included.
8. ECONOMIC ANALYSIS: Alternative methods of meeting this requirement have been explored during project development. This project is the only feasible option to meet the requirement.
9. JOINT USE CERTIFICATION: The Deputy Assistant Secretary of the Army (Installation and Housing) certifies that this project has been considered for joint use potential. Mission requirements, operational considerations, and location are incompatible with use by other components.
HALDANE B. LAMBERTONDate Major General The Adjutant General
AT/FP POC: LTC KELLY SMITH/(502) 607-1404 CFMO: Mr. STEVEN KING/(502) 607-1481
12. SUPPLEMENTAL DATA
a. Estimated design data:
(1) Status:
(a) Date Design Started....................................Oct/2023
(b) Percent Complete as of January 2025..........................0%
(c) Date Design 35% Complete...............................Jun/2024
(d) Date Design Complete...................................Oct/2025
(e) Parametric Cost Estimating Used to Develop Cost..............No
(f) Type of Design Contract....................Design - Bid - Build
(2) Basis:
(a) Standard or Definitive Design................................No
(b) Where Design Was Most Recently Used.........................N/A
(3) Total Cost (c)=(a)+(b) or (d)+(e):.........................($000)
(a) Production of Plans and Specifications
(b) All Other Design Costs
(c) Total
(d) Contract
(e) In-house
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 5 of 9
12. SUPPLEMENTAL DATA (CONT)
(4) Construction Award.......................................Mar/2026
(5) Construction Start.......................................May/2026
(6) Construction Completion..................................Mar/2028
(7) Estimated Percent Complete as of 01 Jan 2025 [Budget Year]....70%
(8) Estimated Percent Complete as of 01 Oct 2025 [Program Year]...70%
Energy and Life Cycle Costs : An energy study and life cycle cost analysis will be documented during the final design.
b. Equipment associated with this project which will be provided from other appropriations:
Fiscal Year Appropriated or
Requested Equipment
Nomenclature Procuring
Appropriation Cost ($000)
FFE OMNG 2027 720
ISC Equipment OPA 2027 200
ESS (214L) OPA 2027 1,072
Other Special Equipment 2 OMNG 2027 152
Total: 2144
Point of Contact: CFMO KY, 502-607-1481
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 6 of 9
Detailed Requirement Statements
1. GENERAL: Tis project is programmed to provide the full requirement of scope at
This project is exempt from providing the minimum 25% funding state match because the scope constructs a National Guard Vehicle Maintenance Shop (category code 21407). These projects are supported 100% federally.
2. ANALYSIS OF DEFICIENCY: An entire modern Field Maintenance Shop must be constructed on a new site to replace the severely damaged facility.
The requirement includes, but is not limited to, modern maintenance bays, administrative and logistical spaces, locker and restroom spaces, military vehicle storage, and privately-owned vehicle parking.
3. ANALYSIS OF CRITERIA AND EXCEPTIONS FOR NEW CONSTRUCTION: The Real Property Development Plan reflects no adequate ARNG facilities in the area to accommodate this mission. No facilities can be expanded or converted to perform this sustainment mission.
EXCEPTIONS TO CRITERIA:
4. STATEMENT OF PROGRAM RELATED EQUIPMENT: Kitchen/Break Area equipment, Furniture, ESS (CIDS) ISC (Data & Telcom) will be requested in FY24 in the amount of $650,000.
5. DISPOSITION OF PRESENT ACCOMMODATIONS: Facilities will be demolished.
Demolition funding is programmed within the scope of this project.
Site Code
Cat Code
Cost ($000)FACNO Title SF Disposition
21B30 B3050 21407 National Guard Vehicle 13096 Demolish 400 21A95 TR7M2 17996 MOUT TNG (SM) 13884 Disposal 0 21A95 WK148 75052 REC SHELTER 3200 Disposal 0
6. CONTRIBUTIONS TO READINESS: a. How will readiness be enhanced by construction of this project? This project modern sustainment capability for remote eastern Kentucky units for the first time. The new Jackson FMS will eliminate outdoor maintenance performed on large engineer construction equipment. This will significantly improve readiness, morale, and productivity of all part & full time personnel from the shop and supported units.
b. How will readiness be impaired by deferring this project to a futur
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 7 of 9 e program year? The units assigned the Jackson Field Maintenance Shop before the July 2022 storm will suffer. These units' equipment will go to remote shop locations in order to receive higher level maintenance.
The G4 will pay $100,000/yr annually to pay per diem and travel costs associated with supporting Jackson FMS 6's full time technicians work being performed away from their assigned location.
c. Why does this project contribute more than another project? The assigned units are early responders to all manner of disaster locally and regionally. The engineers have deployed nationally and OCONUS to provide their specially construction and combat skill sets. Their lack of readiness jeopardizes Soldiers and citizens' lives and welfare.
7. CLEAN AIR ACT: Applicable permitting and other procedural requirements mandated by State, Interstate, and local air pollution control agencies will be complied with for this project. Copies of all Federally required permits and/or registration applications and responses will be forwarded to the US Army Center for Health Promotion and Preventive Medicine, ATTN: MCHB-TS-EAP, Aberdeen Proving Ground, MD 21010-5422
8. TELECOMMUNICATIONS: Telecommunications services and equipment are required. Telecommunications equipment not specifically authorized by NGR 105-23 will be provided by other than ARNG federal funds.
9. ECONOMIC ANALYSIS: An economic analysis has been conducted and is on file in the Construction and Facilities Management Office. A screening of available properties has been conducted as part of the economic analysis. The analysis results indicate no KYARNG facility within eastern Kentucky offers the opportunity to accommodate mission requirements.
10. ANTITERRORISM/FORCE PROTECTION: a. A risk analysis for this project has not been conducted.
b. A threat analysis for this project has not been conducted.
c. The building is to comply with standard design requirements per UFC 4-010-01 for Antiterrorism/Force Protection measures.
All required physical security and Antiterrorism/Force Protection measures are included.
This project is to be constructed within a perimeter.
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 8 of 9
e. This project conventional standoff as per UFC 4-010-01 dated 12 Dec 2018.
This project will be three stories of construction.
11. TRAFFIC ANALYSIS: None
12. SPECIAL PROGRAM REQUIREMENTS: None
13. RPMA DISCUSSION This project is programmed to provide the full requirement of a NG Vehicle Maintenance Shop possessing a scope of 17,296 SQFT. The KYARNG anticipates no further requirement for construction after this project's completion for this location.
1. COMPONENT
FY 2026 MILITARY CONSTRUCTION PROJECT DATA
2. DATE
ARNG 28 Jun 23
3. INSTALLATION AND LOCATION
JACKSON,KY
4. PROJECT TITLE 5. PROJECT NUMBER
DD Form 1391, JUL 99 Page 9 of 9
5. FREQUENCY AND TYPE UTILIZATION
Maintenance operations full time 5 days/week and 1 weekend/month for IDT Units.
6. OTHER ACTIVE/GUARD/RESERVE INSTALLATIONS WITHIN 15 MILE RADIUS
7. PROJECTS REQUESTED IN THIS PROGRAM
(DESIGN STATUS)
CATEGORY
CODE SCOPE
COST ($000)
PROJECT TITLE START COMPLETE
21407 NATIONAL GUARD VEHICLE
MAINTENANCE SHOP
27,910 SF
2,593 m2
14,400 01/10/23 01/10/25
8. STATE RESERVE FORCES FACILITIES BOARD RECOMMENDATION
07 Mar 2023Facilities identified in item 7 have been examined by Joint
Service Reserve Component Facility Board (JSRCFB) for possible joint use/expansion. The Board recommends unilateral construction.
(Date)
9. LAND ACQUISITION REQUIRED
None 0 (Number of Acres)
10. PROJECTS PLANNED IN NEXT FOUR YEARS
COST
($000)
CATEGORY
CODE
PROJECT TITLE SCOPE
None.
SRM BACKLOG ($000): $ 16000
28 Jun 202311. PERSONNEL STRENGTH AS OF:
PERMANENT GUARD/RESERVE
TOTAL OFFICER ENLISTED CIVILIAN TOTAL OFFICER ENLISTED
AUTHORIZED 0 0 0 0 0 0 0
ACTUAL 0 0 0 0 0 0 0
Percentage: 0%
12. RESERVE UNIT DATA
STRENGTH
UNIT DESIGNATIONUIC TPSN MTOE/TDA AUTHORIZED ACTUAL
W8A252 FMS 06 (HQ ARNG ELMT,
JFHQ-KY)
0 0
Totals 0 0
1. COMPONENT 2. DATEFY 2026 GUARD AND RESERVE
MILITARY CONSTRUCTION 28 Jun 23ARNG
3. INSTALLATION AND LOCATION 4. AREA CONSTR
COST INDEX
JACKSON, KY 0.96
DD Form 1390S/1, JUL 99 PREVIOUS EDITION IS OBSOLETE Page 1 of 2
13. MAJOR EQUIPMENT AND AIRCRAFT
TYPE Supported by Shop Assigned to Shop
SEMF Wheeled Vehicles 82 9 SEMF Trailers 67 5 SEMF Tracked Vehicles 9 2 SEMF Equipment > 30 FT 28 4 SEMF Fuel Truck 1 0
SEMF HET 0 0
Totals 187 20
14. OUTSTANDING POLLUTION AND SAFETY DEFICIENCIES
($000) Air Pollution 0 Water Pollution 0 Safety and Occupational Health 0
1. COMPONENT 2. DATEFY 2026 GUARD AND RESERVE
MILITARY CONSTRUCTION 28 Jun 23ARNG
3. INSTALLATION AND LOCATION 4. AREA CONSTR
COST INDEX
JACKSON, KY 0.96
DD Form 1390S/1, JUL 99 Page 2 of 2
Project Number : 210029 Project Title : NATIONAL GUARD VEHICLE MAINTENANCE SHOP Site Code : 21B32
Project Validation
The Reserve manpower potential to meet and maintain authorized strengths of all Reserve units in the area in which this facility is to be located has been reviewed in accordance with DOD Directive 1225.7. It has been determined, in coordination with all other Services having Reserve units in the area, that the number of units of the Reserve components of the Armed Forces presently located in the area and those which have been allocated to the area for future activation, is not and will not be larger than the number that reasonably can be expected to be maintained at authorized strength.
The proposed project is in compliance with the following acts, executive orders, laws, and rules:
NATIONAL ENVIRONMENTAL POLICY ACT: Project has been analyzed for potential environmental impact in accordance with Environmental Analysis of Army Actions (32 CFR Part 651).
SUSTAINABILITY: The design and execution of this project, where appropriate, will comply with Executive Orders (EOs) 13423 and 13514 with respect to reduction/elimination of hazardous materials and incorporation of sustainability and green building principles.
COASTAL ZONE PLAN: In accordance with the provisions of Section 102(2)(c) of the National Environmental Policy Act of 1969, the project has been reviewed, and it is determined to be in compliance with the States Coastal Zone Plan.
ENDANGERED SPECIES ACT: Project must include a review of threatened and endangered species in accordance with Section 7 of the Endangered Species Act (ESA), 50 CFR 402.
FALLOUT PROTECTION: In accordance with Section 601 of Public Law 89-568, as amended, the design of this project has been prepared to maximize fallout protection. Fallout shelters have been excluded from any structure only for the following reason: (1) Adequate protection areas are available to fulfill a stations requirements.
FLOOD HAZARD: Project has been evaluated for flood hazards in compliance with Executive Order 11988, and the facility is not sited in an area known to be subjected to flooding.
DESIGN ACCESSIBILITY FOR PHYSICALLY HANDICAPPED PERSONNEL: In accordance with 42 U.S.
Code 4154, provisions for the physically handicapped personnel will be provided for, where appropriate, in the design of the facility.
VENDING FACILITIES FOR THE BLIND: Project has been evaluated for the provision of vending facilities to be operated by blind persons in compliance with DHEW Rule, 45 CFR-1369, and the State Licensing Board has not sanctioned operation of a blind vending concession at the proposed location.
NATIONAL HISTORIC PRESERVATION ACT OF 1966: This action has the potential to cause adverse effects to historic properties and tribal resources. The State ARNG will consult with the State Historic Preservation Officer (SHPO) and North American Tribes under NHPA prior to project initiation to determine the presence/absence of historic properties that might be adversely affected.
ENVIRONMENTAL CONDITION OF PROPERTY (ECOP): ECOP analysis is required for this project per the requirements of AR 200-1 (Chapter 15-6) and applicable ASTM standards.
AT/FP POC: LTC KELLY SMITH
AT/FP Phone: 502-607-1404-null HALDANE B. LAMBERTON
Major General The Adjutant General Date:
Project Summary Information
Project Number 210029 Sponsoring Agency KY
Project Title NATIONAL GUARD VEHICLE MAINTENANCE SHOP
Unit of Measure English State Facility Review Board:
Preparation Date 28-JUN-23 Recommendation Modernization
Last Revision Date 28-JUN-23 Date of Recommendation 07-MAR-23
Site Summary Information
Site Identifier 21B32
Site Name JACKSON OMS 6
Address
Street 672 ARMORY DR
City and Zip JACKSON, 41339-9232
Pattern of Facility Usage
Maintenance operations full time 5 days/week and 1 weekend/month for IDT Units.
Reservist Weekends/Month 1 Winter Design Temperature 0
Avarage Annual Snowfall 10
Projects Requested In this Program
Cat Code Project Title Scope (SF) Cost ($000) Design StartDesign End
21407 NATIONAL GUARD VEHICLE
MAINTENANCE SHOP
27910 14400 01-OCT-23 01-OCT-25 2011
Additional Projects Planned in Next Four Years
PROJNO Cat Code Project Title Scope (SF) Cost ($000) FY
No future projects identified.
Nearest Five Military Installations
Component DoD Activity Location Distance
No Nearest Military Activities Identified.
Unit Summary Information
Reserve Strength Full-Time Strength
UIC Officers WOF Enlisted Officers Enlisted Civ
W8A252 0 0 0 0 0 0
Totals 0 0 0 0 0 0
Real Property Configuration
Category Description Existing SF Requested SF
214L ARNG - Surface Equipment Maintenance Facility 10456 14134
442 ARNG - Warehouse 208 0
INFO ARNG - Information Systems Worksheet 0 5488
Basic Project Data - Actual/ English Project Number: 210029 Project Title: NATIONAL GUARD VEHICLE MAINTENANCE SHOP Date: Jun 28, 2023 Page: 1 / 3
Basic Information Report (Units)
General Information
Field Value Field Value
UIC W8A252 Last Updated 12-JUN-23
Unit Name FMS 06 (HQ ARNG ELMT, JFHQ-KY)
Parent UIC W8A2AA MTOE/TDA Markup Status DATA IN
Unit Type MAINT SHOP Source ASIP
SRC Status M
DRC ARNG
Field Agency KY Unit Level
FACID 21B30 Facility City, State JACKSON, KY
Strength Count Ind C Strength Count Ind (Project) C
AMSA/SEMF Unit Info
Shop and Workbay Criteria
Field Value Field Value
Maintenance Shop Type FMS
Field Mechanics 13 Calibration Specialists 0
Sustainment Level Mechanics 0 Canvas repair Technicians 0
General Supervisor 0 Stock Control Admin and Sprt 0
Supervisors 1 Electronics Worksers 0
Production Controllers 1 Radiation Calibration Spec 0
Inspctn and Library Sect Tech 0 Missile Repair Specialists 0
Automation Clerks 1 Welding Technicians 0
Instrument Repair Tech 0 Machinists 0
Small Arms Repair Tech 0 Metal Worksers 0
Injector Test Specialists 0 Glass Repair Specialists 0
Fuel Ingnition Spec 0 Painters 0
Radiator Repair Spec 0 Carpenters 0
Comm/ Elec Technicians 0 BII Specialists 0
Communication Security Tech 0 Missile Calibration Spec 0
Other Maintenance Support Personnel 0
Parking Totals
Type Equipment Supported Assigned Hand Rcpt
Wheeled 82 9 0
Tracked 9 2 0
Trailers 67 5 0
Equipment 30 Ft 28 4 0
Fuel Truck 1 0 0
HET 0 0 0
Supported Unit Criteria
Field Value Field Value
Combat Vehicles (incl M2/M3s) 0 M1 Battle Tank Maint Req 0
M2/M3 Bradley 0 Total Supported Troops 246
Missile Systems 0 Highest Level of Unit HQCompany or below
Basic Project Data - Actual/ English Project Number: 210029 Project Title: NATIONAL GUARD VEHICLE MAINTENANCE SHOP
Page: 2 / 3
Units Supported
UIC Unit Name Type RelationshipAuth Strength Vehicles
WY0EA1 DET 1 (CO HORIZONTAL
CONSTRU)
Maintenance Shop 72 0
WY0EAA (CO ENG CONSTRUCTION C) Maintenance Shop 80 148
WY0NAA (CO SAPPER COMPANY (RE) Maintenance Shop 93 39
Strength Info
Reserve Personnel
Type PersonnelOfficers WOF Enlisted Total
Required 0 0 0 0
Authorized 0 0 0 0
Assigned 0 0 0 0
TAPDB-R 0 0 0 0
ASIP
FY-Type Officers WOF Enlisted Total DA Civ Oth Civ
2023-DWS 0 0 0 0 0 0
2023-FTS 0 0 0 0 10 0
2024-DWS 0 0 0 0 0 0
2024-FTS 0 0 0 0 10 0
2025-DWS 0 0 0 0 0 0
2025-FTS 0 0 0 0 10 0
2026-DWS 0 0 0 0 0 0
2026-FTS 0 0 0 0 10 0
2027-DWS 0 0 0 0 0 0
2027-FTS 0 0 0 0 10 0
2028-DWS 0 0 0 0 0 0
2028-FTS 0 0 0 0 10 0
2029-DWS 0 0 0 0 0 0
2029-FTS 0 0 0 0 10 0
Full-Time Personnel
Type PersonnelOfficers Enlisted Civilian
Authorized 0 0 0
Assigned 0 0 0
Basic Project Data - Actual/ English Project Number: 210029 Project Title: NATIONAL GUARD VEHICLE MAINTENANCE SHOP
Page: 3 / 3
Functional Space Details - Actual/ English
Project Number : 210029
Date : Jun 28, 2023
DD 1391 Cost Worksheet Memos Report 214L - ARNG - Surface Equipment Maintenance Facility
Primary Facilities
Unheated Storage Author Memo
Justification: Site conditions prevent construction of new standalone facility. This scope converts some of the existing warehouse space into unheated storage.
Proponent: KYARNG Recommendation Date: 29-Sep-22 Documentation Reference:
Reviewer Memo Feedback/Recommendation:
Proponent:
Recommendation Date:
Documentation Reference:
Supporting Facilities
Demolition Author Memo
Justification: Demolition of a portion of existing warehouse and old FMS associated with project within 2yrs of MILCON execution Proponent: ARNG Recommendation Date: 29-Sep-22 Documentation Reference:
Reviewer Memo Feedback/Recommendation:
Proponent:
Recommendation Date:
Documentation Reference:
Project Number : 210029
Regulatory Report Environmental Analysis Environmental Analysis Memo(s)
1. Environmental Documentation: This project is being assessed. A copy of the draft FNSI is expected to be published on 12/15/22. Preliminary assessment is included in the Environmental Documentation Paragraph above. Final environmental findings are expected no later than 02/1/23.
2. Summary of Environmental Consequences:
Environmental Impact Select no assessment at this time.
Environmental Officer CFMO Mr. CHRIS HETTINGER, Environmental Program Manager, KYARNG
Mr. STEVEN KING, CFMO, KYARNG
NEPA
NEPA Document Type NEPA Timeline (DD/MM/YYYY) NEPA Document Type: REC Scheduled NEPA Start Date: 01/10/2022 Performed By: In-House Scheduled NEPA Completion Date: TBD Cost to Prepare Documentation ($000): 5 Actual NEPA Start Date: TBD Actual NEPA Completion Date: TBD
NEPA Point of Contact Mr. CHRIS HETTINGER, 502-607-1860
Additional NEPA Information Do the following items pertain to this Scheduled Actual project? Start Date Comp Date Start Date Comp Date
NHPA Sect 106 Consultation: TBD TBD TBD TBD TBD
NHPA Agreement Document: TBD TBD TBD TBD TBD
ESA Section 7 Consultation: TBD TBD TBD TBD TBD
Wetlands Permitting: TBD TBD TBD TBD TBD
UXO: TBD TBD TBD TBD TBD
NEPA Memo(s)
1. Remarks/Explanation:
Historic Properties Protection of Historic Properties Memo(s)
1. Protection of Historic Properties:
2. Detailed Statement of Review Findings:
3. State Historic Preservation Officer (SHPO) Concurrence:
Project Number: 210029 Project Title: NATIONAL GUARD VEHICLE MAINTENANCE SHOP
4. State Historic Preservation Officer (SHPO) Non-Concurrence:
5. Request to Advisory Council on Historic Preservation (ACHP):
6. Memorandum of Agreement:
Flood Hazards and Wetlands Flood Hazards and Wetlands Memo(s)
1. Evaluation of Flood Hazards:
Flood Hazards or Wetlands Assessment This project is not sited in a floodplain or wetlands.
Accessibility Accessibility Standards Memo(s)
1. Hazards to Individuals with Disabilities:
2. Accessibility Standards:
Accessibility and Usability This project will not be designed for accessibility and usability by those with disabilities as the facility will be used and operated solely by military personnel without disabilities.
Commercial Activities Commercial Activities Memo(s)
1. Commercial Activities Analysis Conclusions: There will be no commercial activities performed at this location.
2. Executive Summary of the Commercial Activities Analysis: There will be no commercial activities performed at this location.
Energy and Utility Reqs Energy and Utility Requirements Memo(s)
1. Summary of Energy Requirements: New facilities will comply with LEED Silver standards and include the latest, most efficient facility systems that can be feasibly and reasonably incorporated.
2. Summary of Utility Support:
3. User Discretionary Block:
Project Number: 210029 Project Title: NATIONAL GUARD VEHICLE MAINTENANCE SHOP
File details come from the government source that posted it. Updated .