240149_Submittal_Register.xlsx
XLSX spreadsheet 49 KB Posted
- Solicitation number
- FA813725R0016
About this file
The file is a Submittal Register for the WWYK240149 Renovation Project at Tinker Air Force Base, detailing 270+ specific submittal requirements across multiple specification sections. The project involves renovating the Northeast area of Building 3, including HVAC system modifications, lighting fixture relocations, electrical updates, fire alarm device installations, fire protection sprinkler work, flooring replacements, and conference room modifications.
The submittal register comprehensively outlines preconstruction submittals, shop drawings, product data, test reports, certificates, samples, operation and maintenance data, and closeout documents required from the contractor. Key submission categories include entry access lists, health and safety plans, environmental documentation, construction schedules, quality control plans, design submittals, fire protection system documentation, fire alarm system details, and as-built drawings. Submissions are categorized by specification section and must be submitted at specific project stages, with many requiring government review and approval before proceeding with work.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register_General Requ
| TITLE: | WWYK240149 | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | RENOVATE NE AREA OF SOUTH PROJECT | |||||||||||||||||
| LOCATION: | B3 | |||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks | |
| 1 | 00 70 00 | 01 | Preconstruction Submittals | Entry Access List | 1.6 | G | |||||||||||||||
| 2 | 00 70 00 | 01 | Preconstruction Submittals | Key Issue Receipt | 1.3.12.1 | ||||||||||||||||
| 3 | 00 70 00 | 06 | Test Reports | Pre-Construction Testing Record | 1.3.11 | G | |||||||||||||||
| 4 | 00 70 00 | 07 | Certificates | Welding, Cutting and Brazing Permit | 1.4 | G | |||||||||||||||
| 5 | 00 70 00 | 07 | Certificates | Framed Instructions | 1.8 | ||||||||||||||||
| 6 | 00 70 00 | 11 | Closeout Submittals | Key Return Receipt | 1.3.12.1 | ||||||||||||||||
| 7 | 00 71 00 | 01 | Preconstruction Submittals | Health and Safety Plan | 1.3 | G | |||||||||||||||
| 8 | 00 71 00 | 01 | Preconstruction Submittals | Internal Combustion Engines Plan | 1.3.5 | G | |||||||||||||||
| 9 | 00 71 00 | 01 | Preconstruction Submittals | Entry Authority List | 1.5.2 | ||||||||||||||||
| 10 | 00 71 00 | 01 | Preconstruction Submittals | Vehicle Entry Authority List | 1.5.2 | G | |||||||||||||||
| 11 | 00 71 00 | 01 | Preconstruction Submittals | Equipment and Material Storage | 1.5 | G | |||||||||||||||
| 12 | 00 71 00 | 01 | Preconstruction Submittals | Contractor Offices and Plants | 1.5 | G | |||||||||||||||
| 13 | 00 71 00 | 01 | Preconstruction Submittals | Designated Waste and Disposal Areas | 1.5 | G | |||||||||||||||
| 14 | 00 71 00 | 01 | Preconstruction Submittals | Construction Phasing Plan | 1.5 | G | |||||||||||||||
| 15 | 00 71 00 | 01 | Preconstruction Submittals | Airfield Construction Waiver | 1.5 | G | Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing. | ||||||||||||||
| 16 | 00 71 00 | 01 | Preconstruction Submittals | FAA Form 7460-1 | 1.5.3 | G | |||||||||||||||
| 17 | 00 71 00 | 07 | Certificates | Safety Meetings | 1.3 | ||||||||||||||||
| 18 | 00 71 00 | 07 | Certificates | FOD Awareness and Prevention Training | 1.4 | ||||||||||||||||
| 19 | 00 72 00 | 01 | Preconstruction Submittals | Restoration Plan | 1.3.2 | G | |||||||||||||||
| 20 | 00 72 00 | 01 | Preconstruction Submittals | Storm Water Pollution Prevention Plan | 1.3.3.2 | G | |||||||||||||||
| 21 | 00 72 00 | 01 | Preconstruction Submittals | Water System Construction Permit | 1.3.3.6 | G | |||||||||||||||
| 22 | 00 72 00 | 01 | Preconstruction Submittals | AF Form 3952 Chemical/Hazardous Material Request/Authorization | 1.4 | G | |||||||||||||||
| 23 | 00 72 00 | 01 | Preconstruction Submittals | Spray Painting Plan | 1.9 | G | |||||||||||||||
| 24 | 00 72 00 | 01 | Preconstruction Submittals | Environmental Management System Awareness Training | 1.1 | ||||||||||||||||
| 25 | 00 72 00 | 03 | Product Data | New Boiler Information Form | 1.3.8.2 | G | |||||||||||||||
| 26 | 00 72 00 | 03 | Product Data | Affirmative Procurement Documentation or Green Statement | 1.3.10 | G | Provide only one. Reference specification for additional information | ||||||||||||||
| 27 | 00 72 00 | 06 | Test Reports | AF Form 487 Generator Operating Log (Inspection and Testing) | 1.3.8.1 | G | |||||||||||||||
| 28 | 00 72 00 | 07 | Cerificates | Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate | 1.3.4.1 | ||||||||||||||||
| 29 | 00 72 00 | 07 | Cerificates | Monthly Hazardous Material Usage Report | 1.4 | G | Provide 1st week of each month during construction | ||||||||||||||
| 30 | 00 72 00 | 07 | Cerificates | Refrigerant Technical Certifications | 1.5 | G | |||||||||||||||
| 31 | 00 72 00 | 07 | Cerificates | Refrigerant Installation | 1.5 | G | |||||||||||||||
| 32 | 00 72 00 | 08 | Manufacturer's Instructions | Safety Data Sheets/Material Safety Data Sheets | 1.4 | ||||||||||||||||
| 33 | 00 72 00 | 11 | Closeout Submittals | Notice of Termination | |||||||||||||||||
| (ODEQ Form 640-572) | 1.3.3.2 | G | |||||||||||||||||||
| 34 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Documentation of Training/ Experience | C.2 |
C.13 35 00 72 00 - Attch 2 01 Preconstruction Submittals Employee Physicals C.2 C.13
| 36 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Regulatory Agency Notification | C.3 | ||
| 37 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Security Documentation | C.4 | ||
| 38 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Communications | C.5 | ||
| 39 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Step-by-Step Abatement Procedures | C.6 | G | |
| 40 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Glovebag Procedures | C.7 | G | |
| 41 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Negative Pressure Enclosure Construction Procedures | C.8 | G | |
| 42 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Respirator Protection Program | C.9 | ||
| 43 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Encapsulation Procedures | C.11 | G | |
| 44 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Landfill Qualifications | C.14 | ||
| 45 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Work Schedule | C.16 | ||
| 46 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Emergency Plans and Fire Prevention Plans | C.17 | G | |
| 47 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Written Hazardous Communication Program | C.18 | ||
| 48 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Rental Equipment | C.19 | ||
| 49 | 00 72 00 - Attch 2 | 07 | Cerificates | Manufacturer’s Certifications | C.10 | ||
| 50 | 00 72 00 - Attch 2 | 07 | Cerificates | Laboratory and Monitoring Qualifications/Certifications | C.12 | ||
| 51 | 00 72 00 - Attch 2 | 07 | Cerificates | Asbestos Waste Transporter Certification of Insurance | C.13 | ||
| 52 | 00 72 00 - Attch 2 | 08 | Manufacturer's Instructions | Safety Data Sheets/Material Safety Data Sheets | C.15 | ||
| 53 | 00 72 00 - Attch 2 | 11 | Closeout Submittals | Waste Disposal Receipt | M.1(1) | G | |
| 54 | 00 72 00 - Attch 2 | 11 | Closeout Submittals | Air Sampling Results | M.1(2) | G | |
| 55 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Documentation of Training/ Experience | C.1 | ||
| 56 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Employee Physicals | C.2 | ||
| 57 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Security Documentation | C.3 | ||
| 58 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Step-by-Step Abatement Procedures Plan | C.4 | G | |
| 59 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Full Containment Construction Procedures/Drawings | C.5 | G | |
| 60 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Respirator Protection Program | C.6 | ||
| 61 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Work Schedule | C.11 | G | |
| 62 | 00 72 00 - Attch 3 | 03 | Product Data | Materials List | C.10 | ||
| 63 | 00 72 00 - Attch 3 | 07 | Cerificates | Manufacturer’s Certifications | C.7 | ||
| 64 | 00 72 00 - Attch 3 | 07 | Cerificates | Laboratory and Monitoring Qualifications | C.8 | ||
| 65 | 00 72 00 - Attch 3 | 07 | Cerificates | Lead Based Paint Waste Transporter’s Qualifications | C.9 | ||
| 66 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Waste Disposal Receipt | M.1.1 | G | |
| 67 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Air Sampling Results | M.1.2 | G | |
| 68 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Verification of Decontamination of Rental Equipment | M.1.3 | ||
| 69 | 00 72 00 - Attch 3a | 01 | Preconstruction Submittals | Removal Procedures | B.1 | G | |
| 70 | 00 72 00 - Attch 3a | 03 | Product Data | List of Material | B.2 | ||
| 71 | 00 72 00 - Attch 3a | 08 | Manufacturer's Instructions | Material Data Sheets | B.3 | ||
| 72 | 00 72 00 - Attch 5 | 01 | Preconstruction Submittals | Construction Debris Analysis Plan | 1.2.3 | G | |
| 73 | 00 72 00 - Attch 5 | 07 | Certificates | Monthly Debris Management Report | 2 | G | Provide 1st week of each month during construction |
| 74 | 00 72 00 - Attch 11 | 01 | Preconstruction Submittals | Tree Planting/Removal Permit | 1.1 | G | |
| 75 | 00 72 00 - Attch 11 | 01 | Preconstruction Submittals | Tree Protection Plan | 2.1 | G | |
| 76 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | Provide within 10 days of NTP. |
| 77 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Design Schedule | 1.2 | G | Provide within 10 days of NTP. |
| 78 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | Provide 1st week of each month during construction, or as directed by CO | |
| 79 | 01 32 16.00 20 | 07 | Certificates | 3-Week Look Ahead Schedule | 1.6 | Provide weekly with the Contract Progress Report | |
| 80 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.8 | G | |
| 81 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Design Quality Control Plan | 1.5.1 | G | |
| 82 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Initial Design Conference | 1.5.2.2 | ||
| 83 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Preconstruction Conference | 1.5.2.3 | ||
| 84 | 01 33 16.00 10 | 01 | Preconstruction Submittals | DCM Procedures | 3.5.1 | G | |
| 85 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Submittal Register | 3.8.4 | G | |
| 86 | 01 33 16.00 10 | 05 | Design Data | Design and Code Checklists | 1.7.1 | C | |
| 87 | 01 33 16.00 10 | 05 | Design Data | Interim Design Submittals | 3.2.1 | R | |
| 88 | 01 33 16.00 10 | 05 | Design Data | Interior And Exterior Building Finishes Scheme | 3.6.5.1.1 | G | |
| 89 | 01 33 16.00 10 | 05 | Design Data | Conference Documentation | 3.7.3 | ||
| 90 | 01 33 16.00 10 | 05 | Design Data | Final Design Submittals | 3.8 | R | |
| 91 | 01 33 16.00 10 | 05 | Design Data | Design Complete Documents | 3.9 | C | |
| 92 | 01 33 16.00 10 | 11 | Closeout Submittals | DD Form 1354 | 3.8.5 | A | |
| 93 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Quality Control (QC) Plan | 3.2 | G | |
| 94 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Additional Requirements for Design Quality Control (DQC) Plan | 3.2.2 | G | |
| 95 | 01 45 00.00 10 | 05 | Design Data | Discipline-Specific Checklists | 3.2.2 | ||
| 96 | 01 45 00.00 10 | 05 | Design Data | Design Quality Control | 3.9.1 | ||
| 97 | 01 45 00.00 10 | 06 | Test Reports | QC Documentation | 3.9 | Provide weekly with the Contract Progress Report | |
| 98 | 01 50 00 | 01 | Preconstruction Submittals | Request for Contractor Staging Area | 1.1 | G | |
| 99 | 01 50 00 | 01 | Preconstruction Submittals | Photographic Record | 1.3 | ||
| 100 | 01 78 00 | 03 | Product Data | Warranty Letter | 1.7.1 | ||
| 101 | 01 78 00 | 03 | Product Data | Warranty Tags | 1.7.3 | ||
| 102 | 01 78 00 | 03 | Product Data | Spare Parts Data | 1.5 | ||
| 103 | 01 78 00 | 08 | Manufacturer's Instructions | Instructions | 1.7.1 | ||
| 104 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.4 | G | Provide (2) electronic sets (optical media) and (1) hard copy |
| 105 | 01 78 00 | 11 | Closeout Submittals | Working As-Built Drawings | 3.1 | G | Provide (2) electronic sets (optical media) and (2) hard copies |
| 106 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.3 | G | Provide (2) electronic sets (optical media) and (1) hard copy |
| 107 | 01 78 00 | 11 | Closeout Submittals | Certification of EPA Designated Items | 2.3 | G | |
| 108 | 01 78 00 | 11 | Closeout Submittals | Certification Of USDA Designated Items | 2.4 | G | |
| 109 | 01 78 00 | 11 | Closeout Submittals | DD FORM 1354 | 3.6 | G | |
| 110 | 01 78 00 | 11 | Closeout Submittals | Checklist for DD FORM 1354 | 3.6 | G | |
| 111 | 01 78 23 | 10 | Operation and Maintenance Data | Operation and Maintenance Data | 1.2 | G | Provide 30 days prior to scheduled Training |
| 112 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.3 | G | |
| 113 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | Provide 30 days prior to scheduled Final Inspection |
| 114 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | Provide 14 days prior to scheduled Training |
| 115 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | Provide 14 days prior to scheduled Training |
| 116 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | |
| 117 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | |
| 118 | SOW | 07 | Certificates | Contract Progress Report(s) | 2.4 | G | Provide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal) |
| 119 | SOW | 01 | Preconstruction Submittals | B3001 Visitor Badge Issue Receipt | 1.3.7 | ||
| 120 | SOW | 11 | Closeout Submittals | B3001 Visitor Badge Return Receipt | 1.3.7 | ||
| 121 | 07 84 00 | 2 | Shop Drawings | Firestopping System | 2.1 | G | |
| 122 | 07 84 00 | 3 | Product Data | Firestopping Materials | 2.2 | G | |
| 123 | 07 84 00 | 6 | Test Reports | Inspection | 3.3 | G | |
| 124 | 07 84 00 | 7 | Certificates | Inspector Qualifications | 1.5.2 | G | |
| 125 | 07 84 00 | 7 | Certificates | Firestopping Materials | 2.2 | G | |
| 126 | 07 84 00 | 7 | Certificates | Installer Qualifications | 1.5.1 | G | |
| 127 | 07 92 00 | 3 | Product Data | Sealants | 2.1 | ||
| 128 | 07 92 00 | 3 | Product Data | Primers | 2.2 | ||
| 129 | 07 92 00 | 3 | Product Data | Backstops | 2.3 | G | |
| 130 | 08 11 13 | 2 | Shop Drawings | Doors | 2.1 | G | |
| 131 | 08 11 13 | 2 | Shop Drawings | Doors | 2.1 | G | |
| 132 | 08 11 13 | 2 | Shop Drawings | Frames | 2.4 | G | |
| 133 | 08 11 13 | 2 | Shop Drawings | Frames | 2.4 | G | |
| 134 | 08 11 13 | 2 | Shop Drawings | Accessories | 2.3 | ||
| 135 | 08 11 13 | 3 | Product Data | Doors | 2.1 | G | |
| 136 | 08 11 13 | 3 | Product Data | Frames | 2.4 | G | |
| 137 | 08 11 13 | 3 | Product Data | Accessories | 2.3 | ||
| 138 | 08 31 00 | 2 | Shop Drawings | Access Doors And Panels | 1.3 | G | |
| 139 | 08 31 00 | 3 | Product Data | Access Doors And Panels | 1.3 | G | |
| 140 | 08 31 00 | 3 | Product Data | Accessories | 2.2.7 | G | |
| 141 | 08 31 00 | 3 | Product Data | Recycled Content | 2.1 | S | |
| 142 | 08 31 00 | 6 | Test Reports | Fire-rating(s) of Assemblies | 1.3.1 | G | |
| 143 | 08 71 00 | 2 | Shop Drawings | Manufacturer's Detail Drawings | 1.3 | G | |
| 144 | 08 71 00 | 2 | Shop Drawings | Verification of Existing Conditions | 1.3 | G | |
| 145 | 08 71 00 | 2 | Shop Drawings | Hardware Schedule | 1.5 | G | |
| 146 | 08 71 00 | 2 | Shop Drawings | Keying System | 2.3.6 | G | |
| 147 | 08 71 00 | 3 | Product Data | Hardware Items | 2.3 | G | |
| 148 | 08 71 00 | 8 | Manufacturer's Instructions | Installation | 3.1 | ||
| 149 | 08 71 00 | 10 | Operation and Maintenance Data | Hardware Schedule | 1.5 | G | |
| 150 | 09 22 00 | 2 | Shop Drawings | Metal Support Systems | 2.1 | G | |
| 151 | 09 22 00 | 3 | Product Data | Metal Support Systems | 2.1 | ||
| 152 | 09 24 23 | 2 | Shop Drawings | Lath | 3.4 | ||
| 153 | 09 24 23 | 3 | Product Data | Proportions and Mixing | 3.7 | ||
| 154 | 09 24 23 | 4 | Samples | Colored Stucco Finish Coat | 2.2 | ||
| 155 | 09 24 23 | 4 | Samples | Sample Panel | 1.3 | G | |
| 156 | 09 29 00 | 3 | Product Data | Accessories | 2.1.5 | ||
| 157 | 09 29 00 | 3 | Product Data | Gypsum Board | 2.1.1 | ||
| 158 | 09 29 00 | 8 | Manufacturer's Instructions | Safety Data Sheets | 2.1 | ||
| 159 | 09 29 00 | 10 | Operation and Maintenance Data | Manufacturer Maintenance Instructions | 2.1 | ||
| 160 | 09 51 00 | 3 | Product Data | Acoustical Performance | 2.1.1 | G | |
| 161 | 09 51 00 | 4 | Samples | Acoustical Units | 2.2 | G | |
| 162 | 09 65 00 | 3 | Product Data | Adhesives | 2.3 | ||
| 163 | 09 65 00 | 3 | Product Data | Vinyl Composition Tile | 2.1 | ||
| 164 | 09 65 00 | 3 | Product Data | Wall Base | 2.2 | ||
| 165 | 09 65 00 | 4 | Samples | Resilient Flooring and Accessories | 2.6 | G | |
| 166 | 09 65 00 | 6 | Test Reports | Moisture, Alkalinity and Bond Tests | 3.3 | G | |
| 167 | 09 65 00 | 8 | Manufacturer's Instructions | Installation | 3.1 | G | |
| 168 | 09 65 00 | 10 | Operation and Maintenance Data | Resilient Flooring and Accessories | 2.6 | G | |
| 169 | 09 90 00 | 2 | Shop Drawings | Piping Identification | 3.8 | ||
| 170 | 09 90 00 | 3 | Product Data | Coating | 2.1 | G | |
| 171 | 09 90 00 | 3 | Product Data | Product Data Sheets | 2.1 | ||
| 172 | 09 90 00 | 4 | Samples | Color | 2.2 | G | |
| 173 | 09 90 00 | 8 | Manufacturer's Instructions | Application Instructions | 3.2.1 | ||
| 174 | 09 90 00 | 8 | Manufacturer's Instructions | Mixing | 2.1 | ||
| 175 | 09 90 00 | 8 | Manufacturer's Instructions | Manufacturer's Safety Data Sheets | 1.7.1 | ||
| 176 | 09 90 00 | 10 | Operation and Maintenance Data | Coatings | 2.1 | G | |
| 177 | 10 14 00.20 | 2 | Shop Drawings | Detail Drawings | 1.3.2 | G | |
| 178 | 10 14 00.20 | 3 | Product Data | Room Identification Signage System | 2.1 | G | |
| 179 | 10 14 00.20 | 4 | Samples | Interior Signage | 1.3.1 | G | |
| 180 | 10 14 00.20 | 4 | Samples | Room Identification Signage System | 2.1 | G | |
| 181 | 10 14 00.20 | 10 | Operation and Maintenance Data | Approved Manufacturer's Instructions | 3.1 | G | |
| 182 | 10 14 00.20 | 10 | Operation and Maintenance Data | Protection and Cleaning | 3.1.2 | G | |
| 183 | 10 26 00 | 2 | Shop Drawings | Corner Guards | 2.2 | G | |
| 184 | 10 26 00 | 3 | Product Data | Corner Guards | 2.2 | G | |
| 185 | 21 13 13 | 1 | Preconstruction Submittals | Qualified Fire Protection Engineer (QFPE) | 1.2.3 | G | |
| 186 | 21 13 13 | 1 | Preconstruction Submittals | Sprinkler System Designer | 1.4.2.1 | G | |
| 187 | 21 13 13 | 1 | Preconstruction Submittals | Sprinkler System Installer | 1.4.2.2 | G | |
| 188 | 21 13 13 | 2 | Shop Drawings | Shop Drawing | 1.2.1.1 | G | |
| 189 | 21 13 13 | 3 | Product Data | Pipe | 1.4.1.1 | G | |
| 190 | 21 13 13 | 3 | Product Data | Fittings | 2.2.1.2 | G | |
| 195 | 21 13 13 | 3 | Product Data | Sprinklers | 2.7 | G | |
| 196 | 21 13 13 | 3 | Product Data | Pipe Hangers and Supports | 2.2.3 | G | |
| 197 | 21 13 13 | 3 | Product Data | Sprinkler Alarm Switch | 2.4.1 | G | |
| 203 | 21 13 13 | 3 | Product Data | Seismic Bracing | |||
| 204 | 21 13 13 | 3 | Product Data | Nameplates | 2.4.5 | G | |
| 208 | 21 13 13 | 6 | Test Reports | Test Procedures | 3.6.1 | G | |
| 209 | 21 13 13 | 6 | Test Reports | NFPA 13 Contractor's Material and Test Certificate for Aboveground Piping. | 3.6.1 | G | |
| 211 | 21 13 13 | 7 | Certificates | Verification of Compliant Installation | 3.6.2.1 | G | |
| 212 | 21 13 13 | 7 | Certificates | Request for Government Final Test | 3.6.2.2 | G | |
| 213 | 21 13 13 | 10 | Operation and Maintenance Data | Operating and Maintenance (O&M) Instructions | 3.8 | G | |
| 214 | 21 13 13 | 10 | Operation and Maintenance Data | Spare Parts | 1.6 | G | |
| 215 | 21 13 13 | 11 | Closeout Submittals | As-built drawings | 3.8 | ||
| 216 | 23 00 00 | 02 | Shop Drawings | Detail Drawings | 1.4.5 | G | |
| 217 | 23 00 00 | 03 | Product Data | Metallic Flexible Duct | 2.9.1.1 | G | |
| 218 | 23 00 00 | 03 | Product Data | Insulated Nonmetallic Flexible Duct Runouts | 2.9.1.2 | G | |
| 219 | 23 00 00 | 03 | Product Data | Duct Connectors | 2.9.1.3 | G | |
| 220 | 23 00 00 | 03 | Product Data | Duct Access Doors | 2.9.2 | G | |
| 221 | 23 00 00 | 03 | Product Data | Fire Dampers | 2.9.3 | G | |
| 222 | 23 00 00 | 03 | Product Data | Manual Balancing Dampers | 2.9.4 | G | |
| 223 | 23 00 00 | 03 | Product Data | Sound Attenuation Equipment | 2.9.8 | G | |
| 224 | 23 00 00 | 03 | Product Data | Diffusers | 2.9.9.1 | G | |
| 225 | 23 00 00 | 03 | Product Data | Registers and Grilles | 2.9.9.2 | G | |
| 226 | 23 03 00 | 03 | Product Data | Certification | 1.2 | G | |
| 227 | 23 05 93 | 01 | Preconstruction Submittals | Records of Existing Conditions | 1.4 | G | |
| 228 | 23 05 93 | 02 | Shop Drawings | TAB Schematic Drawings and Report Forms | 1.4 | G | |
| 229 | 23 05 93 | 03 | Product Data | Equipment and Performance Data | 1.4 | G | |
| 230 | 23 05 93 | 03 | Product Data | TAB Related HVAC Submittals | 1.4 | G | |
| 231 | 23 05 93 | 06 | Test Reports | Completed Pre-Final DALT Report | 3.3.5 | G | |
| 232 | 23 05 93 | 06 | Test Reports | Certified Final DALT Report | 3.3.8 | G | |
| 233 | 23 05 93 | 07 | Certificates | Independent TAB Agency and Personnel Qualifications | 1.5.1 | G | |
| 234 | 23 05 93 | 07 | Certificates | DALT and TAB Submittal and Work Schedule | 1.5.1 | G | |
| 235 | 23 05 93 | 07 | Certificates | TAB Pre-Final Engineering Report | 1.5.1 | G | |
| 236 | 28 31 76 | 1 | Preconstruction Submittals | Qualified Fire Protection Engineer (QFPE) | 1.3.2 | G | |
| 237 | 28 31 76 | 1 | Preconstruction Submittals | Fire alarm system designer | 1.9.2.1 | G | |
| 238 | 28 31 76 | 1 | Preconstruction Submittals | Supervisor | 1.9.2.2 | G | |
| 239 | 28 31 76 | 1 | Preconstruction Submittals | Technician | 1.9.2.3 | G | |
| 240 | 28 31 76 | 1 | Preconstruction Submittals | Installer | 1.9.2.4 | G | |
| 241 | 28 31 76 | 1 | Preconstruction Submittals | Fire Alarm System Site-Specific Software Acknowledgement | 1.7 | G | |
| 242 | 28 31 76 | 2 | Shop Drawings | Nameplates | 1.9.1.3 | G | |
| 243 | 28 31 76 | 2 | Shop Drawings | Instructions | 2.2.4 | G | |
| 244 | 28 31 76 | 2 | Shop Drawings | Wiring Diagrams | 1.9.1.4 | G | |
| 245 | 28 31 76 | 2 | Shop Drawings | System Layout | 1.9.1.5 | G | |
| 246 | 28 31 76 | 2 | Shop Drawings | Notification Appliances | 1.9.1.6 | G | |
| 247 | 28 31 76 | 2 | Shop Drawings | Initiating devices | 1.9.1.7 | G | |
| 248 | 28 31 76 | 2 | Shop Drawings | Amplifiers | 1.9.1.8 | G | |
| 249 | 28 31 76 | 2 | Shop Drawings | Battery Power | 1.9.1.9 | G | |
| 250 | 28 31 76 | 2 | Shop Drawings | Voltage Drop Calculations | 1.9.1.10 | G | |
| 251 | 28 31 76 | 3 | Product Data | LCD Annunciator | 2.6.1 | G | |
| 252 | 28 31 76 | 3 | Product Data | Manual Stations | 2.7 | G | |
| 253 | 28 31 76 | 3 | Product Data | Notification Appliances | 1.9.1.6 | G | |
| 254 | 28 31 76 | 3 | Product Data | Supplemental Notification Appliance Circuit Panels | 2.14.1.1 | G | |
| 255 | 28 31 76 | 3 | Product Data | Auxiliary Power Supply Panels | 2.14.1.1 | G | |
| 256 | 28 31 76 | 3 | Product Data | Surge Protective Devices | 2.15 | G | |
| 257 | 28 31 76 | 3 | Product Data | Alarm Wiring | 2.15 | G | |
| 258 | 28 31 76 | 3 | Product Data | Back Boxes and Conduit | 3.3.4 | G | |
| 259 | 28 31 76 | 3 | Product Data | Ceiling Bridges | 3.2.9 | G | |
| 260 | 28 31 76 | 6 | Test Reports | Test Procedures | 3.6.1 | G | |
| 261 | 28 31 76 | 7 | Certificates | Verification of Compliant Installation | 3.6.2.1 | G | |
| 262 | 28 31 76 | 7 | Certificates | Request for Government Final Test | 3.6.2.2 | G | |
| 263 | 28 31 76 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Instructions | 3.8 | G | |
| 264 | 28 31 76 | 10 | Operation and Maintenance Data | Instruction of Government Employees | 3.9 | G | |
| 265 | 29 31 76 | 11 | Closeout Submittals | NFPA 72 System Record of Completion | G | ||
| 266 | 28 31 76 | 11 | Closeout Submittals | As-Built Drawings | 1.9.1.13 | G | |
| 267 | 28 31 76 | 11 | Closeout Submittals | Spare Parts | 1.11.1 | G | |
| 268 | SOW | 06 | Test Reports | Pre-TAB | 4.8 et al | G | |
| 269 | SOW | 06 | Test Reports | Final TAB | 4.9 et al | G | |
| 270 | |||||||
| 271 | |||||||
| 272 | |||||||
| 273 | |||||||
| 274 | |||||||
| 275 | |||||||
| 276 | |||||||
| 277 | |||||||
| 278 | |||||||
| 279 | |||||||
| 280 | |||||||
| 281 | |||||||
| 282 | |||||||
| 283 | |||||||
| 284 | |||||||
| 285 | |||||||
| 286 | |||||||
| 287 | |||||||
| 288 |