00 80 00.pdf

PDF 8 KB Posted

Attached to
TINKER AFB MAC BOA WWYK240149 RENOVATE NE AREA OF SOUTH PROJECT, B3
Solicitation number
FA813725R0016
Issued by

About this file

This document is a Special Provisions section (Section 00 80 00) for working on Tinker Air Force Base (TAFB), detailing specific requirements and guidelines for contractors operating on the base. Key provisions include strict airfield operations protocols, such as pre-coordinating all activities with the Contracting Officer and Chief, Airfield Management (CAM), maintaining a 12-foot height limit for construction vehicles, and requiring flight line driver training for personnel operating equipment within the movement area.

The document also outlines additional contractor responsibilities including dewatering excavated areas, using specified haul routes, implementing traffic control and barricades according to national standards, managing waste removal off-base, and potential negotiation of a winter recess between December 1 and March 1. Contractors must coordinate for airfield authorization passes, ensure minimal road lane closures during construction, and maintain close coordination with the Airfield Manager, with taxiing and towed aircraft always having right-of-way.

View the file

Other files

File Type Posted
240149_pre-bid_RFIs_responses_COR.pdf PDF
WWYK240149 MAC BOA Site Visit.pdf PDF
Solicitation - FA813725R0016.pdf PDF
Solicitation - FA813725R0016.pdf PDF
2020 TAFB Facility Standard.pdf PDF
240149_Drawings.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 45 00.00 10.pdf PDF
01 42 00.pdf PDF
Headhouse-Widow-Elevation.pdf PDF
00003A-FP01.pdf PDF
240149_Submittal_Register.xlsx XLSX spreadsheet
240149 SOW att2 Design Narrative.pdf PDF
UMRL.pdf PDF
01 78 23.pdf PDF
240149_SOW.pdf PDF
Original AsBuilts.pdf PDF
00 71 00.pdf PDF
240149_Submittal_Register.pdf PDF
01 32 16.00 20.pdf PDF
090069 Sustain RAC Structural Failures In B3.pdf PDF
00 70 00.pdf PDF
940084A.pdf PDF
2023 TAFB Fire Protection Standard.pdf PDF
00 72 00.pdf PDF
970116 Repr Wooden Trusses.pdf PDF
240149 SOW att1 Draft RMDF.pdf PDF
2020 TAFB Mechanical Standard.pdf PDF
880371.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
00 80 05.pdf PDF
01 50 00.pdf PDF
2024 TAFB Electrical Standards.pdf PDF
20200083 As Built Drawings.pdf PDF
01 78 00.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 00

SPECIAL PROVISIONS FOR WORKING ON TINKER AFB

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. The most current edition of the listed publications at the time of contract/delivery order award shall be used.

TINKER AIR FORCE BASE (TAFB)

TAFBI 13-204 (2021) Airfield Operations

1.2 DEWATERING EXCAVATED AREA

It shall be the Contractor's responsibility to protect the construction area from damage due to rainwater. The Contractor shall provide and maintain at the job site sufficient pumps to remove rainwater from the excavated area as soon as practicable.

1.3 HAUL ROUTES

The haul routes to be used by the Contractor shall be as directed on the project drawings or by the Contracting Officer.

1.4 AIRFIELD OPERATIONS

All contractor activities on the airfield shall be pre-coordinated with the Contracting Officer in conjunction with the Chief, Airfield Management (CAM) prior to the Contractor proceeding on the airdrome. The provisions of TAFBI 13-204 and Section 00 80 05 SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD shall be strictly adhered to.

All runways, taxiways and aprons shall remain open during this project, unless specified otherwise by the Contracting Officer. The height of construction vehicles and equipment shall be limited to 12 feet above the surface. Absolutely no equipment or personnel will be allowed on the aircraft movement area or within 200 feet of the runways without permission from the Tinker Control Tower.

All Contractor personnel who will be operating their equipment or vehicles within the movement area or on any aircraft-parking ramp shall receive flight line driver training and have portable radios capable of communicating with Tinker Ground Control for projects over seven days.

The CAM may authorize certain contractors and other personnel to drive on the airdrome for short specified periods without completing the flight line driving training. However, Airfield Management will brief contractors and project engineers (or other supervisors responsible for the work being accomplished) and will provide flight line orientation for contractor vehicle operators prior to allowing them to drive on the airdrome.

January 2022 Page 1 Section 00 80 00

Tinker AFB Tinker General Requirements

Prior to commencing work on this project, the Contractor shall coordinate with the Contracting Officer for any airfield authorization passes that may be required.

Taxiing and towed aircraft shall have the right-of-way at all times.

Close coordination will be maintained between the Contractor's on-site foreman and the Airfield Manager.

1.5 TRAFFIC CONTROL AND BARRICADES

1.5.1 Automobile Movement Areas

Construction areas affecting automobile movement areas shall be protected by an adequate number of barricades with working flashing lights, warning devices, construction signs, flagmen and personnel. The barricades and warning devices shall be in accordance with the "Manual on Uniform Traffic Control Devices for Streets and Highways" developed by the U.S. Department of Transportation as an approved national standard. All costs associated with providing the traffic control and barricades shall be considered incidentals and shall be borne by the Contractor at no additional cost to the Government.

1.5.2 Road Closures

On two lane roads, only one lane may be blocked at a time. On four lane roads, at least two lanes shall be kept open at all times and three at rush hour.

1.6 WASTE AREA

Unless otherwise specified in these specifications, all waste materials removed shall become property of the Contractor and shall be taken off base for disposal. Disposal site location shall be the responsibility of the Contractor.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 WINTER RECESS

A winter recess, between December 1 and March 1, can be negotiated per Delivery Order between the Contracting Officer and the Contractor. It shall be a no cost modification to the contract moving the Delivery Order completion date the amount of the recess time.

-- End of Section --