TINKER AFB MAC BOA WWYK240149 RENOVATE NE AREA OF SOUTH PROJECT, B3
Solicitation number
FA813725R0016
Issued by

About this file

The provided document is a Submittal Register for the WWYK240149 project to renovate the NE area of the South Project, Building 3 at Tinker Air Force Base. The comprehensive register details 269 individual submittal line items across multiple specification sections, including preconstruction submittals, product data, shop drawings, certificates, test reports, operation and maintenance data, and closeout submittals. Key submittal categories cover critical areas such as fire protection systems, fire alarm systems, HVAC, quality control, environmental management, safety plans, and training documentation.

The register requires contractors to submit numerous detailed documents throughout the project lifecycle, with many items marked as "Government" (G) review classification. Specific notable submittals include a Health and Safety Plan, Storm Water Pollution Prevention Plan, FAA Form 7460-1, Entry Access Lists, Construction Phasing Plan, Environmental Management System Awareness Training, Airfield Construction Waiver, and multiple certification and documentation requirements for fire protection, fire alarm systems, and facility renovation processes. The project involves repairing and replacing HVAC systems, lighting fixtures, electrical feeds, fire alarm devices, fire protection sprinklers, flooring, acoustical tiles, and conference room modifications in Building 3 at Tinker AFB.

View the file

Other files

File Type Posted
240149_pre-bid_RFIs_responses_COR.pdf PDF
WWYK240149 MAC BOA Site Visit.pdf PDF
Solicitation - FA813725R0016.pdf PDF
Solicitation - FA813725R0016.pdf PDF
2020 TAFB Facility Standard.pdf PDF
240149_Drawings.pdf PDF
00 80 00.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 45 00.00 10.pdf PDF
01 42 00.pdf PDF
Headhouse-Widow-Elevation.pdf PDF
00003A-FP01.pdf PDF
240149_Submittal_Register.xlsx XLSX spreadsheet
240149 SOW att2 Design Narrative.pdf PDF
UMRL.pdf PDF
01 78 23.pdf PDF
240149_SOW.pdf PDF
Original AsBuilts.pdf PDF
00 71 00.pdf PDF
01 32 16.00 20.pdf PDF
090069 Sustain RAC Structural Failures In B3.pdf PDF
00 70 00.pdf PDF
940084A.pdf PDF
2023 TAFB Fire Protection Standard.pdf PDF
00 72 00.pdf PDF
970116 Repr Wooden Trusses.pdf PDF
240149 SOW att1 Draft RMDF.pdf PDF
2020 TAFB Mechanical Standard.pdf PDF
880371.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
00 80 05.pdf PDF
01 50 00.pdf PDF
2024 TAFB Electrical Standards.pdf PDF
20200083 As Built Drawings.pdf PDF
01 78 00.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Trans mittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G

2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1

3 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G

4 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

5 00 70 00 07 Certificates Framed Instructions 1.8

6 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1

7 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

8 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G

9 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2

10 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G

11 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G

12 00 71 00 01 Preconstruction Submittals Contractor Offices and Plants 1.5 G

13 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G

14 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G

15 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G

Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.

16 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G

17 00 71 00 07 Certificates Safety Meetings 1.3

18 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

19 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G

20 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G

21 00 72 00 01 Preconstruction Submittals Water System Construction Permit 1.3.3.6 G

22 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G

23 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

24 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1

25 00 72 00 03 Product Data New Boiler Information Form 1.3.8.2 G

26 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information

27 00 72 00 06 Test Reports AF Form 487 Generator Operating Log (Inspection and Testing) 1.3.8.1 G

28 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1

29 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction

30 00 72 00 07 Cerificates Refrigerant Technical Certifications 1.5 G

31 00 72 00 07 Cerificates Refrigerant Installation 1.5 G

32 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4

33 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G

34 00 72 00 - Attch 2 01 Preconstruction Submittals Documentation of Training/ Experience C.2 C.13

35 00 72 00 - Attch 2 01 Preconstruction Submittals Employee Physicals C.2 C.13

36 00 72 00 - Attch 2 01 Preconstruction Submittals Regulatory Agency Notification C.3

37 00 72 00 - Attch 2 01 Preconstruction Submittals Security Documentation C.4

38 00 72 00 - Attch 2 01 Preconstruction Submittals Communications C.5

39 00 72 00 - Attch 2 01 Preconstruction Submittals Step-by-Step Abatement Procedures C.6 G

40 00 72 00 - Attch 2 01 Preconstruction Submittals Glovebag Procedures C.7 G

41 00 72 00 - Attch 2 01 Preconstruction Submittals Negative Pressure Enclosure Construction Procedures C.8 G

42 00 72 00 - Attch 2 01 Preconstruction Submittals Respirator Protection Program C.9

43 00 72 00 - Attch 2 01 Preconstruction Submittals Encapsulation Procedures C.11 G

44 00 72 00 - Attch 2 01 Preconstruction Submittals Landfill Qualifications C.14

45 00 72 00 - Attch 2 01 Preconstruction Submittals Work Schedule C.16

46 00 72 00 - Attch 2 01 Preconstruction Submittals Emergency Plans and Fire Prevention Plans C.17 G

47 00 72 00 - Attch 2 01 Preconstruction Submittals Written Hazardous Communication Program C.18

48 00 72 00 - Attch 2 01 Preconstruction Submittals Rental Equipment C.19

49 00 72 00 - Attch 2 07 Cerificates Manufacturer’s Certifications C.10

50 00 72 00 - Attch 2 07 Cerificates Laboratory and Monitoring Qualifications/Certifications C.12

51 00 72 00 - Attch 2 07 Cerificates Asbestos Waste Transporter Certification of Insurance C.13

52 00 72 00 - Attch 2 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets C.15

53 00 72 00 - Attch 2 11 Closeout Submittals Waste Disposal Receipt M.1(1) G

54 00 72 00 - Attch 2 11 Closeout Submittals Air Sampling Results M.1(2) G

55 00 72 00 - Attch 3 01 Preconstruction Submittals Documentation of Training/ Experience C.1

56 00 72 00 - Attch 3 01 Preconstruction Submittals Employee Physicals C.2

57 00 72 00 - Attch 3 01 Preconstruction Submittals Security Documentation C.3

58 00 72 00 - Attch 3 01 Preconstruction Submittals Step-by-Step Abatement Procedures Plan C.4 G

59 00 72 00 - Attch 3 01 Preconstruction Submittals Full Containment Construction Procedures/Drawings C.5 G

60 00 72 00 - Attch 3 01 Preconstruction Submittals Respirator Protection Program C.6

61 00 72 00 - Attch 3 01 Preconstruction Submittals Work Schedule C.11 G

62 00 72 00 - Attch 3 03 Product Data Materials List C.10

63 00 72 00 - Attch 3 07 Cerificates Manufacturer’s Certifications C.7

64 00 72 00 - Attch 3 07 Cerificates Laboratory and Monitoring Qualifications C.8

65 00 72 00 - Attch 3 07 Cerificates Lead Based Paint Waste Transporter’s Qualifications C.9

66 00 72 00 - Attch 3 11 Closeout Submittals Waste Disposal Receipt M.1.1 G

67 00 72 00 - Attch 3 11 Closeout Submittals Air Sampling Results M.1.2 G

TITLE: WWYK240149

SUBMITTAL REGISTER

JOB NAME: RENOVATE NE AREA OF SOUTH PROJECT

LOCATION: B3

CONTRACT NO:

CONTRACTOR:

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

Submittal Register_v3_03/07/22

Acti vity

Trans mittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

68 00 72 00 - Attch 3 11 Closeout Submittals Verification of Decontamination of Rental Equipment M.1.3

69 00 72 00 - Attch 3a 01 Preconstruction Submittals Removal Procedures B.1 G

70 00 72 00 - Attch 3a 03 Product Data List of Material B.2

71 00 72 00 - Attch 3a 08 Manufacturer's Instructions Material Data Sheets B.3

72 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

73 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

74 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Planting/Removal Permit 1.1 G

75 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Protection Plan 2.1 G

76 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

77 01 32 16.00 20 01 Preconstruction Submittals Baseline Design Schedule 1.2 G Provide within 10 days of NTP.

78 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

79 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report

80 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

81 01 33 16.00 10 01 Preconstruction Submittals Design Quality Control Plan 1.5.1 G

82 01 33 16.00 10 01 Preconstruction Submittals Initial Design Conference 1.5.2.2

83 01 33 16.00 10 01 Preconstruction Submittals Preconstruction Conference 1.5.2.3

84 01 33 16.00 10 01 Preconstruction Submittals DCM Procedures 3.5.1 G

85 01 33 16.00 10 01 Preconstruction Submittals Submittal Register 3.8.4 G

86 01 33 16.00 10 05 Design Data Design and Code Checklists 1.7.1 C

87 01 33 16.00 10 05 Design Data Interim Design Submittals 3.2.1 R

88 01 33 16.00 10 05 Design Data Interior And Exterior Building Finishes Scheme 3.6.5.1.1 G

89 01 33 16.00 10 05 Design Data Conference Documentation 3.7.3

90 01 33 16.00 10 05 Design Data Final Design Submittals 3.8 R

91 01 33 16.00 10 05 Design Data Design Complete Documents 3.9 C

92 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A

93 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

94 01 45 00.00 10 01 Preconstruction Submittals Additional Requirements for Design Quality Control (DQC) Plan 3.2.2 G

95 01 45 00.00 10 05 Design Data Discipline-Specific Checklists 3.2.2

96 01 45 00.00 10 05 Design Data Design Quality Control 3.9.1

97 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report

98 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

99 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

100 01 78 00 03 Product Data Warranty Letter 1.7.1

101 01 78 00 03 Product Data Warranty Tags 1.7.3

102 01 78 00 03 Product Data Spare Parts Data 1.5

103 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1

104 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G Provide (2) electronic sets (optical media) and

(1) hard copy

105 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

106 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

107 01 78 00 11 Closeout Submittals Certification of EPA Designated Items 2.3 G

108 01 78 00 11 Closeout Submittals Certification Of USDA Designated Items 2.4 G

109 01 78 00 11 Closeout Submittals DD FORM 1354 3.6 G

110 01 78 00 11 Closeout Submittals Checklist for DD FORM 1354 3.6 G

111 01 78 23 10 Operation and Maintenance Data Operation and Maintenance Data 1.2 G Provide 30 days prior to scheduled Training

112 01 78 23 10 Operation and Maintenance Data O&M Database 1.3 G

113 01 78 23 10 Operation and Maintenance Data Training Plan 3.1.1 G Provide 30 days prior to scheduled Final Inspection

114 01 78 23 10 Operation and Maintenance Data Training Content 3.1.2 G Provide 14 days prior to scheduled Training

115 01 78 23 10 Operation and Maintenance Data Training Outline 3.1.3 G Provide 14 days prior to scheduled Training

116 01 78 23 11 Closeout Submittals Training Video Recording 3.1.4 G

117 01 78 23 11 Closeout Submittals Validation of Training Completion 3.1.6 G

118 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal)

119 SOW 01 Preconstruction Submittals B3001 Visitor Badge Issue Receipt 1.3.7

120 SOW 11 Closeout Submittals B3001 Visitor Badge Return Receipt 1.3.7

121 07 84 00 2 Shop Drawings Firestopping System 2.1 G 122 07 84 00 3 Product Data Firestopping Materials 2.2 G 123 07 84 00 6 Test Reports Inspection 3.3 G 124 07 84 00 7 Certificates Inspector Qualifications 1.5.2 G 125 07 84 00 7 Certificates Firestopping Materials 2.2 G 126 07 84 00 7 Certificates Installer Qualifications 1.5.1 G 177 10 14 00.20 2 Shop Drawings Detail Drawings 1.3.2 G 178 10 14 00.20 3 Product Data Room Identification Signage System 2.1 G 179 10 14 00.20 4 Samples Interior Signage 1.3.1 G 180 10 14 00.20 4 Samples Room Identification Signage System 2.1 G

181 10 14 00.20 10 Operation and Maintenance Data Approved Manufacturer's Instructions 3.1 G

182 10 14 00.20 10 Operation and Maintenance Data Protection and Cleaning 3.1.2 G

185 21 13 13 1 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) 1.2.3 G 186 21 13 13 1 Preconstruction Submittals Sprinkler System Designer 1.4.2.1 G 187 21 13 13 1 Preconstruction Submittals Sprinkler System Installer 1.4.2.2 G 188 21 13 13 2 Shop Drawings Shop Drawing 1.2.1.1 G 189 21 13 13 3 Product Data Pipe 1.4.1.1 G 190 21 13 13 3 Product Data Fittings 2.2.1.2 G 195 21 13 13 3 Product Data Sprinklers 2.7 G 196 21 13 13 3 Product Data Pipe Hangers and Supports 2.2.3 G 197 21 13 13 3 Product Data Sprinkler Alarm Switch 2.4.1 G 203 21 13 13 3 Product Data Seismic Bracing 204 21 13 13 3 Product Data Nameplates 2.4.5 G 208 21 13 13 6 Test Reports Test Procedures 3.6.1 G

209 21 13 13 6 Test Reports NFPA 13 Contractor's Material and Test Certificate for Aboveground Piping. 3.6.1 G

211 21 13 13 7 Certificates Verification of Compliant Installation 3.6.2.1 G 212 21 13 13 7 Certificates Request for Government Final Test 3.6.2.2 G

213 21 13 13 10 Operation and Maintenance Data Operating and Maintenance (O&M) Instructions 3.8 G

214 21 13 13 10 Operation and Maintenance Data Spare Parts 1.6 G

215 21 13 13 11 Closeout Submittals As-built drawings 3.8

216 23 00 00 02 Shop Drawings Detail Drawings 1.4.5 G

Acti vity

Trans mittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES APPROVING AUTHORITY

217 23 00 00 03 Product Data Metallic Flexible Duct 2.9.1.1 G

218 23 00 00 03 Product Data Insulated Nonmetallic Flexible Duct Runouts 2.9.1.2 G

219 23 00 00 03 Product Data Duct Connectors 2.9.1.3 G

220 23 00 00 03 Product Data Duct Access Doors 2.9.2 G

221 23 00 00 03 Product Data Fire Dampers 2.9.3 G

222 23 00 00 03 Product Data Manual Balancing Dampers 2.9.4 G

223 23 00 00 03 Product Data Sound Attenuation Equipment 2.9.8 G

224 23 00 00 03 Product Data Diffusers 2.9.9.1 G

225 23 00 00 03 Product Data Registers and Grilles 2.9.9.2 G

226 23 03 00 03 Product Data Certification 1.2 G

227 23 05 93 01 Preconstruction Submittals Records of Existing Conditions 1.4 G

228 23 05 93 02 Shop Drawings TAB Schematic Drawings and Report Forms 1.4 G

229 23 05 93 03 Product Data Equipment and Performance Data 1.4 G

230 23 05 93 03 Product Data TAB Related HVAC Submittals 1.4 G

231 23 05 93 06 Test Reports Completed Pre-Final DALT Report 3.3.5 G

232 23 05 93 06 Test Reports Certified Final DALT Report 3.3.8 G

233 23 05 93 07 Certificates Independent TAB Agency and Personnel Qualifications 1.5.1 G

234 23 05 93 07 Certificates DALT and TAB Submittal and Work Schedule 1.5.1 G

235 23 05 93 07 Certificates TAB Pre-Final Engineering Report 1.5.1 G 236 28 31 76 1 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) 1.3.2 G 237 28 31 76 1 Preconstruction Submittals Fire alarm system designer 1.9.2.1 G 238 28 31 76 1 Preconstruction Submittals Supervisor 1.9.2.2 G 239 28 31 76 1 Preconstruction Submittals Technician 1.9.2.3 G 240 28 31 76 1 Preconstruction Submittals Installer 1.9.2.4 G

241 28 31 76 1 Preconstruction Submittals Fire Alarm System Site-Specific Software Acknowledgement 1.7 G

242 28 31 76 2 Shop Drawings Nameplates 1.9.1.3 G 243 28 31 76 2 Shop Drawings Instructions 2.2.4 G 244 28 31 76 2 Shop Drawings Wiring Diagrams 1.9.1.4 G 245 28 31 76 2 Shop Drawings System Layout 1.9.1.5 G 246 28 31 76 2 Shop Drawings Notification Appliances 1.9.1.6 G 247 28 31 76 2 Shop Drawings Initiating devices 1.9.1.7 G 248 28 31 76 2 Shop Drawings Amplifiers 1.9.1.8 G 249 28 31 76 2 Shop Drawings Battery Power 1.9.1.9 G 250 28 31 76 2 Shop Drawings Voltage Drop Calculations 1.9.1.10 G 251 28 31 76 3 Product Data LCD Annunciator 2.6.1 G 252 28 31 76 3 Product Data Manual Stations 2.7 G 253 28 31 76 3 Product Data Notification Appliances 1.9.1.6 G 254 28 31 76 3 Product Data Supplemental Notification Appliance Circuit Panels 2.14.1.1 G 255 28 31 76 3 Product Data Auxiliary Power Supply Panels 2.14.1.1 G 256 28 31 76 3 Product Data Surge Protective Devices 2.15 G 257 28 31 76 3 Product Data Alarm Wiring 2.15 G 258 28 31 76 3 Product Data Back Boxes and Conduit 3.3.4 G 259 28 31 76 3 Product Data Ceiling Bridges 3.2.9 G 260 28 31 76 6 Test Reports Test Procedures 3.6.1 G 261 28 31 76 7 Certificates Verification of Compliant Installation 3.6.2.1 G 262 28 31 76 7 Certificates Request for Government Final Test 3.6.2.2 G

263 28 31 76 10 Operation and Maintenance Data Operation and Maintenance (O&M) Instructions 3.8 G

264 28 31 76 10 Operation and Maintenance Data Instruction of Government Employees 3.9 G

265 29 31 76 11 Closeout Submittals NFPA 72 System Record of Completion G 266 28 31 76 11 Closeout Submittals As-Built Drawings 1.9.1.13 G 267 28 31 76 11 Closeout Submittals Spare Parts 1.11.1 G 268 SOW 06 Test Reports Pre-TAB 4.8 et al G 269 SOW 06 Test Reports Final TAB 4.9 et al G