00 80 05.pdf

PDF 10 KB Posted

Attached to
TINKER AFB MAC BOA WWYK240149 RENOVATE NE AREA OF SOUTH PROJECT, B3
Solicitation number
FA813725R0016
Issued by

About this file

This document is a Special Provisions section (00 80 05) for working on or near the airfield at Tinker Air Force Base (AFB), detailing specific requirements and restrictions for contractors performing work in active airfield areas. The provisions cover critical operational guidelines including runway/taxiway closure procedures, safety protocols, access restrictions, and emergency procedures.

Key requirements include submitting written closure requests 45 calendar days in advance, maintaining strict safety standards (such as providing ear protection and preventing foreign object debris), obtaining approval for any structures over 12 feet tall within 1000 feet of a runway, and adhering to strict cleanliness and evacuation protocols. Contractors must coordinate closely with Base Operations, obtain clearance from the control tower for vehicle and personnel movements, and be prepared to immediately vacate work areas during aircraft emergencies. All contractor vehicles and equipment operating on landing areas must be identified with low-intensity amber flashing lights, and two-way radio communication with the control tower is mandatory for repeated runway crossings.

View the file

Other files

File Type Posted
240149_pre-bid_RFIs_responses_COR.pdf PDF
WWYK240149 MAC BOA Site Visit.pdf PDF
Solicitation - FA813725R0016.pdf PDF
Solicitation - FA813725R0016.pdf PDF
2020 TAFB Facility Standard.pdf PDF
240149_Drawings.pdf PDF
00 80 00.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 45 00.00 10.pdf PDF
01 42 00.pdf PDF
Headhouse-Widow-Elevation.pdf PDF
00003A-FP01.pdf PDF
240149_Submittal_Register.xlsx XLSX spreadsheet
240149 SOW att2 Design Narrative.pdf PDF
UMRL.pdf PDF
01 78 23.pdf PDF
240149_SOW.pdf PDF
Original AsBuilts.pdf PDF
00 71 00.pdf PDF
240149_Submittal_Register.pdf PDF
01 32 16.00 20.pdf PDF
090069 Sustain RAC Structural Failures In B3.pdf PDF
00 70 00.pdf PDF
940084A.pdf PDF
2023 TAFB Fire Protection Standard.pdf PDF
00 72 00.pdf PDF
970116 Repr Wooden Trusses.pdf PDF
240149 SOW att1 Draft RMDF.pdf PDF
2020 TAFB Mechanical Standard.pdf PDF
880371.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 50 00.pdf PDF
2024 TAFB Electrical Standards.pdf PDF
20200083 As Built Drawings.pdf PDF
01 78 00.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --