24-45_Matrix_Access_System_Upgrade_BC.pdf

PDF 338 KB Posted

Attached to
Upgrade Existing Credential & Security Access System + Maintenance
Solicitation number
25-021-ITB
Issued by
Kenton County, Elkton City, Kentucky

About this file

The document is a project proposal for the Matrix Access System Upgrade at CVG Airport Authority, detailing a comprehensive security system modernization initiative. The project aims to replace legacy access control panels and components dating back to the 1990s, upgrading the entire system by replacing outdated copper line connections with network drops, and upgrading magstripe card readers to more secure iClass/magstripe combo card readers. The project is scheduled for implementation from 2024 Q4 through 2026 Q3, with key milestones including appropriations in 2024 Q4, solicitation in 2025 Q1, award and Notice to Proceed (NTP) in 2025 Q2, and project completion and closeout in 2026 Q2-Q3.

The total project cost is estimated at $604,114, with major expense categories including $493,114 for construction/installation, $50,000 for CVG provided data pulls, $50,000 for contingency, $10,000 for force labor, and $1,000 for miscellaneous expenses. The project will be funded through CAPEX and is justified by the current system's vulnerability to failures, difficulty in service restoration during outages, and reliance on outdated swipe card technology that poses potential security risks. The recommended approach involves engaging with the Matrix provider to upgrade control boards and access points, with the primary objective of enhancing security access standards, increasing system reliability, and aligning with industry best practices.

View the file

Other files

File Type Posted
Upgrade_Existing_Credential_&_Security_Access_System_+_Maintenance_(Addendum_#3_Revision).pdf PDF
Building_Numbers_04.24.2025.pdf PDF
IDF.MDF_Location_Data_with_Totals.xlsx XLSX spreadsheet
25-021-ITB_Terminal_Dwgs_-_All_Levels_Marked_Up.pdf PDF
25-021-ITB_Access_System_Upgrade_-_Ad.pdf PDF
25-021-ITB_Access_System_Upgrade_-_Exh_B_-_Contract_&_Bonds.pdf PDF
25-021-ITB_Technical_Specs_281000_Access_Control_-_DCM.pdf PDF
25-021-ITB_Access_System_Upgrade_-_Exh_A_-_Proposal_Forms.pdf PDF
25-021-ITB_IDF.MDF_Location_Data_with_Totals.pdf PDF
25-021-ITB_Access_System_Upgrade_-_Installation_Specs.pdf PDF
25-021-ITB_Bidders_List.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Buy_American_Certification-Construction_Projects.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
EEO_Certification.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Q4_2024_-_Business_Case_-_Matrix_Access_System_Upgrade.pdf PDF
Affirmative_Action_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Matrix Access System Upgrade

Current Situation/Background Information

The current system consist of several legacy (dating back to 1990's install) panels containing various components such as remote control modules, alarm cards, control boards etc. All panels currently rely on copper lines (outdated technology) for data instead of fiber and network drops.

Additionally, we currently have magstripe card readers at the majority of gates and doors throughout the entire airport, which are outdated and use badges that are easily duplicated, thereby potentially putting us at risk for security breaches.

The older technology in our panels is leading to more widespread (instead of isolated) outages in the system that affect widespread areas resulting in negative impacts to normal operations. There is little documentation/as-built drawings on the actual installation of the current system, which hinders troubleshooting efforts by our technicians and increases outage time.

Project Definition

Project Information: Upgrade the Matrix access control system hardware by

• Replacing outdated components within all panels throughout the system

• Providing network drops at all locations that currently rely on copper lines for data

• Replace all magstripe card readers with more secure iclass/magstripe combo card readers

The business objectives: Upgrade our Matrix access system hardware to meet current security access standards, increase reliability and align with best practices.

Project Justification: The current system is prone to failure, is not easily restored to service in an outage, and requires a high-level of contingency support during outages due to the large amount of the system that becomes non-functional during an outage. The current hardware also only allows for swipe card technology which is below industry standard for security best practices.

Project Approach

Engage with our Matrix provider to provide us with upgraded control boards and access points. Document the system configuration for future troubleshooting.

Alternatives

Continue to replace boards and access devices as they fail leaving the airport vulnerable to long duration access control outages.

Continue to use swipe badge technology leaving the airport more vulnerable to security breaches.

Recommendation

Replace all outdated control boards and update all access control devices to be iClass/biometric capable.

Cost

Design: N/A

Construction/Installation: $493,114

CVG provided data pulls: $50,000

Contingency (min 10%): $50,000

Force Labor: $10,000

Miscellaneous: $1,000

Total Cost: $604,114

Project Funding

CAPEX

Project Schedule

2024 Q4 - Appropriations

2025 Q1 - Solicitation

2025 Q2 - Award and NTP

2026 Q2-Q3 - Project completion and closeout

Known Risks & Limitations

N/A

Strategic Plan Fit Sustainability FitMaster Plan Fit

Approvals:

Candace McGraw

Dil Gruffydd

Executive Sponsor Shannon Oldfield

Concurrence Leader Brian Cobb

Business Unit Leader Steve Listerman

Sponsor/Originator Casey Kinosz Casey Kinosz (Oct 10, 2024 12:53 EDT) Stephen Listerman (Oct 10, 2024 13:43 EDT)

Brian Cobb (Oct 10, 2024 14:55 EDT)

Dilwyn Gruffydd (Oct 10, 2024 15:58 EDT)

Candace McGraw (Oct 10, 2024 16:07 EDT) Candace McGraw https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3 https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3 https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3 https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3 https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3 https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAyyBH7s-F0Rq6uONlky_3UzVklAg8Rut3

2024-10-11T07:32:19-0700
Agreement certified by Adobe Acrobat Sign

File details come from the government source that posted it. Updated .