21-Special Conditions and Supplemental Specs R1 20250910 LIJ LAD 9.12.25.pdf
PDF 975 KB Posted
- Attached to
- Roadway Resurfacing and Repair Contract
- Solicitation number
- IFB-25-00314
- Issued by
- Hillsborough County, Florida
About this file
This document is a Special Conditions and Supplemental Specifications contract for a Roadway Resurfacing & Repair Contract issued by Hillsborough County, Florida, dated September 10, 2025. The contract seeks qualified contractors to perform roadway infrastructure work throughout the county on an "as needed" basis, with work potentially including milling and resurfacing roads, modifying curbs, repairing ADA curb ramps, removing and replacing speed humps, performing utility coordination, regrading, sodding, earthwork, pavement markings, and signage. The work will be ordered through individual work orders, and the contractor will be responsible for providing all necessary labor, materials, and equipment to complete various infrastructure improvements.
The contract does not guarantee a minimum amount of work and emphasizes that actual quantities may significantly vary from estimated amounts. Payment will be based on actual field measurements and unit prices, with the total purchases not exceeding the awarded contract amount. The contract includes specific technical specifications for work performance, such as using Florida Department of Transportation (FDOT) standard specifications, maintaining two-way traffic during construction, coordinating with local authorities, and following specific work hours. Permits for right-of-way use and temporary traffic control will be provided at no cost, and the contractor must have an ISA Certified/Licensed Arborist on staff to ensure proper tree and landscape management during construction activities.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 10, 2025
Special Conditions and Supplemental Specifications
Section 1 – Special Conditions
1.01R Scope
These Special Conditions and Supplemental Specifications modify or supplement the General Terms and Conditions, and other provisions of the Contract Documents. To the extent such provisions are not modified or supplemented herein; all provisions remain in full force and effect.
Hillsborough County (COUNTY) is seeking qualified contractors for the Roadway Resurfacing & Repair Contract. The CONTRACTOR shall furnish all labor, materials and equipment for the accomplishment of all work as described in the Contract Documents & Specifications, as shown on the Plans (if available), and as directed by the Project Manager in accordance with the expressed or obvious intent of the Contract.
Work performed under this Contract will be at various locations throughout the COUNTY. Any work authorized under this term contract will be ordered by the COUNTY on an “as needed” basis.
If available, external plan sheets, construction plan sets, or sketches may be supplied to the CONTRACTOR with the Work Order at the Project Manager’s discretion. The CONTRACTOR is required to render any and all infrastructure and appurtenances associated with or disturbed by the work to an operable condition as determined by the COUNTY.
A. Description of Work:
The work performed under this contract may include, but may not be limited to:
Milling and Resurfacing roads throughout the COUNTY using Superpave Asphaltic Concrete Structural, Friction courses, and/or Full Depth Reclamation;
Modification of curbs to facilitate construction;
Repair, replace, and/or retrofit curb ramps to meet Americans with Disabilities Act
(ADA) compliance requirements;
Removal and replacement of speed humps;
Removal of turf and grade work when required;
Incidental repair of irrigation sprinkler systems;
Utility coordination incidental to the construction;
Incidental coordination with municipalities in the COUNTY according to current inter-local agreements;
Incidental work and coordination of temporary construction traffic control within railroad rights-of-way;
Restoration and cleanup of construction sites;
Incidental street and driveway sweeping;
Remove overgrown grass and debris along edge of pavement and on adjacent shoulder;
Regrading:
Sodding;
Earthwork;
Pavement Markings; and Signage.
1.02R Workmanship and Materials
This project is to be constructed utilizing Hillsborough County Public Works Standard Specifications for Construction October 2023 Edition (or latest version); Florida Department of Transportation (FDOT) FY 2025 Standard Plans for Road Construction (or latest version); FDOT Standard Specifications for Road and Bridge Construction FY 2025-26 (or latest version); with the exception of Division I Section 1 through 9 and Division II Sections 100 through 103 and 105;
Manual of Uniform Traffic Control Devices 11th Edition (or latest version); Hillsborough County Water, Wastewater and Reclaimed Water Technical Specifications October 2023 Edition (or latest version) and Hillsborough County Water, Wastewater and Reclaimed Water Technical Manual October 2023 Edition (or latest version); Hillsborough County Stormwater Management Technical Manual October 2023 Edition (or latest version); Tampa Electric Company Standard Electric Service Requirements, latest edition, available from Tampa Electric Company; and the Supplemental Specifications herein. Any conflict between the documents shall be resolved in accordance with the requirements of the Hillsborough County General Terms and Conditions.
A The use of the term “Department” in the FDOT Specifications is replaced by COUNTY except in those instances where the FDOT is the controlling organization.
B The terms Engineer, Project Manager and Project Representative are interchangeable between the various Contract Documents.
C If the CONTRACTOR desires to utilize materials, means, or methods which in accordance with the FDOT specifications requires Quality Control testing and approval by the Engineer, the testing shall be performed at the expense of the CONTRACTOR, and reviewed for acceptance by the COUNTY. The COUNTY also reserves the right to require testing above and beyond the FDOT specified LOT testing in situations when the testing of LOT quantities will not provide a reasonable assurance of the quality of the work. This additional testing by the CONTRACTOR will be at no additional cost to the COUNTY.
D At the CONTRACTOR’s option he may submit a Value Engineering Change Proposal, also know as a Cost Savings Initiative Proposal (CSIP), or hereinafter referred to as a VECP or CSIP in accordance with FDOT Standard Specifications for Road and Bridge Construction, Section 4-3.9, Value Engineering Incentive, or Cost Savings Initiative Proposal. The COUNTY reserves the right to reject at its discretion any VECP or CSIP submittal and the CONTRACTOR shall remain obligated to perform the WORK in accordance with the terms of the existing Contract.
E. Control of Materials: The County will accept approved FDOT Quality Product List (QPL) products and materials unless stated to the contrary herein.
1.03R Project Sign
Project identification signs shall be provided by the COUNTY and placed by the CONTRACTOR as per Specification 01560-1.08.
Six (6) mobile project identification signs shall be provided, placed, and removed by the CONTRACTOR at various active project locations. The sign(s) shall be maintained in good working condition and shall be replaced by the CONTRACTOR when damaged. The cost to provide the project identification signs shall be included in the Maintenance of Traffic pay item(s).
At the commencement of construction, the CONTRACTOR shall display the signs and relocate the signs as required by the COUNTY PROJECT REPRESENTATIVE. The CONTRACTOR is responsible for the care and custody of the project identification signs. Damage to, or theft of, the project identification signs shall be reported to the COUNTY PROJECT REPRESENTATIVE by the CONTRACTOR within 24 hours. The Cost of relocating and maintaining the signs shall be considered incidental to the project. The signs will be fabricated per the specifications provided as Attachment A.
1.04R Project Locations Work will be performed at various locations throughout Hillsborough County.
1.05R Sequence of Work The COUNTY reserves the right to arrange the sequence of Project Locations. Work may be removed, or additional work may be added to the contract, not to exceed the Awarded Contract Price.
The CONTRACTOR shall make whatever investigations it deems necessary as to the actual field conditions and to comply with the requirements of the Contract documents.
1.06R Schedule
The CONTRACTOR’s project schedule shall encompass the project’s entire construction duration specified in the CONTRACT and may not indicate a shorter duration. Additionally, the schedule shall reflect the construction phasing specified in the CONTRACT and shall include all WORK, including work to be performed by others such as coordination, material acquisition, utility relocation, COUNTY submittal reviews, permit reviews and approvals, etc.
Bar Chart: The bar chart schedule as described in Section 01310 of the Standard Specifications shall be required under this contract for each project location (Work Order (WO)/Purchase Order (PO)), and as well as an overall bar chart schedule for all active projects, with regular updates as requested by the Project Manager.
CPM: The CPM schedule as described in Section 01311 of the Standard Specifications shall not be required under this contract.
1.07R Special Work Hours The Standard work site operation hours within Hillsborough County to be considered by Bidders in preparing their bids shall be as follows:
8:00AM to 5:00PM - Low volume roadways such as subdivisions or any similar locations.
9:00AM to 4:00PM - High volume roadways (collector and arterial roadways) congested areas, and any similar locations.
9:00PM to 6:00AM - High volume roadways (level “F” roadways) congested areas, and any similar locations.
Monday through Friday, excluding County-observed holidays and weekends. No work shall proceed outside these hours without 72 hours prior notice (minimum) and written authorization by the County’s PROJECT MANAGER. However; the COUNTY reserves the right to establish work hours based on traffic volumes, congestion, or other situations that will interfere with the normal flow of traffic.
Temporary Traffic Control Permits will be issued by the COUNTY, as described later in these Supplemental Specifications. The TTC Permits indicate the allowable hours for operation within the actual roadway limits for each road or portion thereof in each project’s work order(s). The CONTRACTOR may request alternative work hours, based on the allowable hours established by the TTC Permit(s). The approval of alternate work hours for each project is subject to the same authorization described above and will be based on a standard 8-hour shift as provided by the normal work hours. These provisions allow daytime and nighttime shifts, based on the allowable hours indicated by the TTC Permit. Further changes to the approved work hours require a formal request by the CONTRACTOR for the TTC Permit to be amended by the COUNTY and the aforementioned written authorization by the County’s PROJECT MANAGER. If approved, an amended TTC Permit will be issued to the CONTRACTOR.
As long as the work is on schedule, the PROJECT MANAGER is not obliged to consider a shift longer than 8 hours or additional workdays beyond those described above. However, if the work is deemed to be behind schedule, the PROJECT MANAGER may approve longer shifts and/or additional shifts based on the approval of a recovery schedule submitted by the CONTRACTOR.
At the discretion of the PROJECT MANAGER, additional costs incurred by the COUNTY for overtime wages and/or employing additional staff are subject to reimbursement by the CONTRACTOR to the COUNTY.
1.08R Contract Estimated Quantities Unit quantities indicated in the Bid Proposal section are provided as a means of comparing bid proposals and as a basis for award. However, these quantities are estimated, and actual unit quantities may vary during the term of this contract. The COUNTY does not guarantee a minimum usage on this contract.
Bidders are cautioned against predicating their bid prices on an assumed scope of work or estimated bid quantities. The amount of award represents only the upper dollar limit beyond which no further work shall be ordered, except as may be approved by the BOCC, through Change Order. It is not known how much or how little work will be ordered during the term of this contract.
The CONTRACTOR acknowledges that actual quantities may be significantly more or less than those indicated on the bid. The CONTRACTOR agrees that he will not make any claim for damages or for loss of profits because of a difference between the quantities shown on the bid form and the quantities of work actually ordered.
Total purchases shall not exceed the amount awarded by the Board, and no work shall be commenced which is not provided for by the provisions of the contract.
Basis for payment shall be actual field measurement, not estimated bid or plan quantities. The dollar amount of payment shall be determined by multiplying the contract unit price for an item by the field measured actual quantity.
Because quantities are estimated and actual requirements will not be determined until time of need, Items 5.8 and 5.9 of the General Terms and Conditions are hereby modified to remove the necessity for formal change order in the event of quantity overruns or under runs, provided that total purchases do not exceed the amount of award.
1.09R Incidental Items Miscellaneous or incidental items such as dewatering, cutting, patching, grading, saw-cutting, electrical hardware, bolts, nuts, fittings, etc., or other ancillary items may be required to complete the construction as indicated on the plans or in the scope of work. If no specific bid item is shown, such miscellaneous or incidental items are to be included in the unit price (s) for the item (s) with which they are associated. Separate payment for miscellaneous incidental items shall not be made by the COUNTY. All components shown and described on the bid documents are to be included in the bid items shown on the bid form.
1.10R Permits A. Pursuant to the Section 218.80, Florida Statutes, Hillsborough County discloses that the permits and fees listed below are the responsibility of the CONTRACTOR.
PERMIT COST
Right-of-Way Use Permit $0.00 (fee waived) Hillsborough County Temporary Traffic Control $0.00 (fee waived)
B. All permits required to perform the work included in the contract are the responsibility of the
CONTRACTOR.
1.11R Utility Coordination
Utility relocations are not anticipated; however, should the need arise, the CONTRACTOR shall coordinate its work with that of the utility companies. The contractor shall protect from any damage all existing structures, underground piping, benchmarks, trees, and other facilities. The CONTRACTOR will be held responsible for damage to such existing facilities. In the event of interruption of water, wastewater or other utility services as a result of accidental breakage, exposure, or lack of support, the CONTRACTOR shall promptly notify the proper authority and cooperate with the authority in the prompt restoration of service. If water or wastewater service is interrupted and the CONTRACTOR is performing or assisting the repair work, the CONTRACTOR shall work continuously until the service is restored. Do not begin work around fire hydrants until the local fire authority has approved provisions for continued service.
- End of Section -
Section 2 – Supplemental Specifications
2.01R Office Facilities
No field offices are required.
2.02R Maintenance of Traffic (Section 102) Under no circumstances will road closure be permitted unless otherwise approved by the PROJECT MANAGER. As a minimum, two (2) way traffic shall be maintained at all times unless otherwise approved by the PROJECT MANAGER. Daytime and overnight lane closures shall be in accordance with all applicable permits, policies and Section 1 Special Conditions Article 1.07R Special Work Hours. Lane closures on roadways under FDOT’s jurisdiction shall be coordinated with FDOT by the CONTRACTOR. Similarly, lane closures involving other authorities and municipalities, where the County’s roads intersect or are continuous with roads under their jurisdiction, will be coordinated with that entity by the CONTRACTOR. This may include expressway authorities, cities, and adjacent counties. All associated costs for coordination, plans and/or permit(s) preparation, submittal and securing approval, are to be included in this Pay Item.
2.03R Traffic Control Officer Requirement (Section 102) As per FDOT Standard Specifications for Road and Bridge Construction FY 2025-26 (or latest version): When needed, and approved by the County’s PROJECT MANAGER, the use of an off-duty law enforcement officer will be paid by the hour. The total hours actually worked at the site by each individual officer will be entered for payment daily. Travel time to and from the site are not included in the daily payment. A line item is added to the bid pages to address the support of an off-duty law enforcement officer. An example of the form to be used to document the number of daily hours worked for each officer is attached to these Supplemental Specifications as Exhibit 1.
2.04R Selective Clearing & Grubbing, Areas with Trees to Remain (Section 110) Clearing & Grubbing shall be performed in accordance with FDOT Specification Section 110.
Additionally, specified plowing of the surface shall include the removal of the top layer of organic material beginning from the original ground line and if applicable stockpiling of the material for future use on the project. No additional compensation shall be provided for this work or associated work.
2.05R Storage of Construction Materials and Equipment (Section 01600)
Supplemental to the provisions in the Contract Terms and Conditions, if the CONTRACTOR intends to store or stage materials, equipment, construction debris, etc. on private or public property outside of the right of way, the CONTRACTOR shall obtain permission via a written agreement.
The CONTRACTOR shall provide the COUNTY with a copy of the written agreement prior to any utilization of the property. The written agreement shall specify the terms, identify the parties involved, and be signed by authorized individuals representing the property owner and the CONTRACTOR. If the property is a County facility, the COUNTY REPRESENTATIVE will assist with obtaining written permission to the extent possible. Areas utilized by the CONTRACTOR for storing or staging materials, equipment, and other items will be fully restored to their original condition at the expense of the CONTRACTOR. Restoration will occur immediately after the CONTRACTOR’s last use of the area.
2.06R Residential Irrigation (Sprinkler) System Repair (Section 01530) The construction activities associated with road reconstruction and resurfacing could impact existing irrigation systems that are within or near the County’s right-of-way. The CONTRACTOR is responsible at his own expense for immediate repairs to these systems which result from construction activity in their vicinity. Generally, these repairs are anticipated to be PVC pipeline break repairs (typically ½” to 2” diameter pipe) and damaged sprinkler head repair and/or replacement. The repair work will be coordinated with the affected residents or entities responsible for the irrigation system and accomplished to their satisfaction.
2.07R Pedestrian Facilities A. All pedestrian facilities shall be constructed in accordance with the Americans with
Disabilities Act (ADA) and the Department of Transportation Regulation 49 CFR, Part 37.
B. Sidewalks and curb ramps shall be constructed in accordance with the FDOT Design Standards 2013 (or the latest edition at time of bid opening) Index 304. Residential sidewalks adjacent to driveways shall be six (6) inches depth up to the first construction joint, which shall be a distance of five (5) feet measured from the edge of the driveway.
Sidewalks/Ramps adjacent to roadways shall be six (6) inches in depth up to the first construction joint which shall be a minimum distance of six (6) feet measured from the edge of pavement, or back of curb. The construction joint may not transect the detectable warning surface.
C. Detectable warning surfaces, as defined by the latest edition of FDOT Standard
Specifications for Road and Bridge Construction - Specification 527, will be utilized in lieu of tactile surfaces. Detectable warning surfaces must be capable of supporting vehicular traffic and no waivers to the warranty are acceptable. All references to tactile surfaces in the Hillsborough County Standard Specifications for construction shall be interpreted as referring to detectable warning surfaces. In order to meet ADA visual contrast requirements, the standard color for application on Hillsborough County maintained roads is red, unless otherwise directed by the Project Manager. If field conditions exist in which red would not create sufficient contrast, the Project Manager should be notified in order to determine if another color should be utilized. On FDOT maintained roads, the color requirements may vary and should be confirmed prior to placement.
Acceptable Materials for Detectable Warning Surfaces:
1. Top Guard Detectable Warning by Roadway Concepts
2. Proprietary epoxy-based system supplied and installed by Vanguard of Florida.
3. Alternate materials and methods which fully meet contract specifications, and which have been approved for the FDOT Qualified Products List, may be used if approved by the Project Manager. Only those materials and methods which are compatible with traffic loads (including warranty) will be considered.
D. Typical Layout of Ramp Pay Item is below:
2.08R Standard Speed Humps and Speed Cushion As per detail in the Exhibit 2 of this contract. Cost for additional materials needed, survey, adjustment of grade, shall be included in the Price for REMOVE AND REPLACE SPEED HUMP PER COUNTY INDEX 010. No additional payment will be provided for any item necessary for the completion of this item as detailed in the Index 010 – Exhibit 2 of this Contract.
2.09R Millings (Section 327) The CONTRACTOR is responsible for delivery of millings to the nearest County maintenance yard.
All associated costs are to be included in the milling bid items in the BP sheets. If no County entity is willing to accept the millings, the CONTRACTOR will take possession of them and immediately remove the millings from project site at no cost to the County.
2.10R (BID ITEM #11-10) - PAVEMENT CEMENT CONCRETE (6-INCH-THICK MIN., 4000
PSI), INCLUDING MACRO SYNTHETIC FIBER REINFORCEMENT (1.5 LBS/CY, 1.5-
INCH FORTA-FERRO) (DRIVEWAYS AND SIDEWALKS) (INCLUDES GRADING AND
ROOT PRUNING)
Work includes:
(1) The Installation of Pavement Cement Concrete (6-inch-thick min 4000 PSI), including Macro
Synthetic Fiber Reinforcement (1.5 LB/CY), for sidewalk, ADA ramps, and driveway applications.
(2) Large trees are expected near, under, and beside the existing neighborhood sidewalks. Tree root and tree branch pruning, as needed for the sidewalk replacement, are to be included within this pay item. This includes, all labor, materials, and equipment for Excavation, Trimming and disposal of tree roots and branches, clean backfill and compaction, and Restoration of disturbed lawn areas within two (2) feet of barrier.
(3) Contractor shall have and maintain an ISA Certified/Licensed Arborist on staff or under contract throughout the contract term to ensure the performance of the Contractor under the terms and conditions of this Agreement. ANSI-A300 (Part 1) American National Standard for Tree Care Operations – Tree, Shrub, and Other Woody Plant Management-Standard Practices (Pruning) and the International Society of Arboriculture’s companion publication Best Management Practices – Tree Pruning shall be used to guide tree trimming/root pruning.
(4) Tree root barrier will not be measured separately for payment and is included in this pay item.
This includes: The furnishing and installation of barrier along trees near driveways, sidewalks, ramps and as directed by the Engineer.
(5) Irrigation systems are expected near, under, and beside the existing neighborhood sidewalks.
All irrigation Repairs, including labor, materials, and equipment, are to be included within this pay item.
Unit of Measurement is per Square Yard (SY), installed and accepted.
2.11R Measurement & Payment This Section modifies or clarifies items in the FDOT Standard Specifications for Road and Bridge Construction FY 2025-26 (or latest version) and the Hillsborough County Public Works Standard Specifications for Construction October 2023 Edition (or latest version), with respect to this contract.
Removal of Existing Concrete (Item 110 4 10): This pay item is intended for miscellaneous concrete removal only, as needed by the County.
Intersection Valley Gutter, Concrete (Item 520-3): Payment for this item will be based on detail TD-6 (Intersection Valley Gutter Typical Details), included in the Exhibit 3 of this contract. No additional payment will be provided for any item necessary for the completion of this item.
FDOT Standard Specifications for Road & Bridge Construction FY 2025-26 (or latest version), Section 570, Performance Turf, Article 570-3 Construction Methods:
The sod type installed by the CONTRACTOR will match the predominant sod type that exists adjacent to the areas that are to receive new sod. Questions regarding which sod type is appropriate should be directed to the PROJECT REPRESENTATIVE. All other provisions of Section 570 apply.
FDOT Standard Specifications for Road & Bridge Construction FY 2025-26 (or latest version), Section 660, Vehicle Detection System: Article 660-6 Method of Measurement and Article 660-7 Basis of Payment:
The method of measurement for traffic loop assemblies is Furnish and Install. Many traffic loop assemblies in Hillsborough County’s traffic systems may only require connection of the new loop lead into the first pull box. However, there are traffic signals on County roads that are operated and maintained by other municipalities. The Contractor is cautioned about predicating their price on a limited scope of work. Some traffic loop assemblies may require significantly more work to satisfy the Specifications, such as installing additional signal cables in conduits, cutting and epoxy sealing signal cables in asphalt, loop lead-in installation, and any other work required to produce a complete and accepted installation by the jurisdictional owner and operator of the traffic signals. Payment will be per traffic loop assembly type (AS). All other provisions of Section 660 apply.
FDOT Standard Specifications for Road & Bridge Construction FY2025-26 (or latest version), Section 711, Thermoplastic Pavement Markings: Article 711-9 Method of Measurement and Article 711-10 Basis of Payment:
All types of thermoplastic stripes will be paid in linear feet (LF). Solid stripes will be paid as the total length of the unbroken solid stripe. Skip stripes will be paid as the total length of the skip stripe, from the beginning of the first thermo stripe to the end of the last thermo stripe in the series.
All configurations of skip traffic stripes, including 10-30, 3-9, 2-4, and 6-10 are paid as TRAFFIC STRIPE SKIP (THERMO) (6”), and either white or yellow. All other provisions of Section 711 apply.
Hillsborough County Public Works Standard Specifications for Construction October 2023 Edition, (or latest version) Sections 101 – 1.02 Payment for Mobilization and Section 101-2.01 Basis of Payment:
Payment for Mobilization shall be based on lump sum Price per individual work orders as shown in the contract bid pages. All other provisions of Section 101 apply.
Hillsborough County Public Works Standard Specifications for Construction October 2023 Edition, ( or latest version) Maintenance of Traffic Section 102-5.01 Basis of Payment:
Payment for Maintenance of Traffic shall be based on lump sum Price per individual work orders as shown in the contract bid pages. All other provisions of Section 102 apply.
2.12R Tree Trimming (Section 01530) This Bid Item will be employed only when needed to provide vertical and horizontal clearance for the paving train vehicles. Work shall be in conformance with the Hillsborough County Public Works Standard Specifications for Construction October 2023 Edition (or latest version), Protection of Existing Facilities Section 01530-1.07. The Tree Trimming Bid Item will include all manpower and equipment required to neatly trim trees and any other plant growth within the right-of-way, and to remove and dispose of the generated material as required by law. This bid item is meant to be all inclusive, and compensation will be on an hourly basis, as coordinated with and approved by the PROJECT REPRESENTATIVE. The hourly rate will apply from the time the CONTRACTOR’s crew actively commences the trimming operation until the generated material is loaded for immediate disposal or is neatly stacked for disposal at a later time. The hourly rate recorded for tree trimming is exclusive of startup time and time spent removing stacked and stored material that was not loaded for immediate disposal as a continuous operation. All material generated by the tree trimming, including remnants, will be removed from the project site by the end of each workday. The CONTRACTOR is not authorized to perform work under this Bid Item without prior consent of the PROJECT REPRESENTATIVE.
2.13R THERMOPLASTIC, REMOVE EXISTING THERMOPLASTIC PAVEMENT MARKINGS
Removal of existing thermoplastic pavement markings to be removed per TRANSPORTATION DESIGN MANUAL BULLETIN 23-01. (See Exhibit 4)
2.14R Restoration of Site
Upon completion of any work, the CONTRACTOR shall be responsible for cleaning and restoring the site. This includes removing all unused materials and excess soil. The area shall be left in generally the same condition as before performance of the work.
2.15R Full Depth Reclamation (FDR) See specification requirements outlined in Exhibit 5 (Section 01800 Full Depth Reclamation with Asphalt Emulsion Technical Specifications). No additional payment will be provided for any item necessary for the completion of this contract as detailed in the specifications.
- End of Section -