20-25 523 Bid Proposal Spreadsheet.xlsx

XLSX spreadsheet 30 KB Posted

Attached to
IRON BRIDGE PUMP STATION REHABILITATION
Solicitation number
CIZ-DWU 25 523
Issued by
Uvalde County, Texas

About this file

This is a bid proposal spreadsheet for Dallas Water Utilities' Iron Bridge Pump Station Rehabilitation project (Contract No. 25-523) located at 4077 Co Rd 3706, Wills Point, Texas. The project encompasses civil, structural, architectural, process-mechanical, electrical, and instrumentation work at the pump station situated on Lake Tawakoni. The base bid section includes eight line items: pump station improvements (1 lump sum), intake gate replacement (4 units), mobilization for confined space work in the flume (1 lump sum), concrete mortar repair (325 cubic feet), concrete crack repair (1,500 linear feet), horizontal split case pump unit modifications with baseframe replacement (6 units), horizontal split case pump unit modifications without baseframe replacement (6 units), and storm water pollution prevention plan and dust control (1 lump sum). Bids were received on April 17, 2026, with completion timing governed by special provisions S-6 and S-12.

The spreadsheet includes three additive alternates: Additive Alternate A1 for Lake Tawakoni silt dredging and mobilization (5,000 cubic yards), Additive Alternate A2 for additional intake gate rehabilitation (1 lump sum), and Additive Alternate A3 for a backup generator (1 lump sum). Bidders were instructed to complete information in designated yellow cells and submit the completed proposal spreadsheet in Excel format (.xls) to Bonfire. All pricing fields in the spreadsheet show $0.00 placeholder values, indicating this is a template awaiting contractor bid submissions with unit prices and total amounts for each line item and alternate.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

DALLAS WATER UTILITIES
PROJECT NAME: IRON BRIDGE PUMP STATION REHABILITATION
CONTRACT NO. 25-523
TIME OF COMPLETION AS PER SPECIAL PROVISIONS S-6 AND S-12
BIDS RECEIVED: APRIL 17, 2026
Instructions to Bidders:
1Bidder to complete information in yellow cells.
2Upload complete Bid Proposal Spreadsheet to Bonfire in Excel (.xls) format.

CONTRACTOR'S NAME (Below)

BASE BID ITEMS
SECTION A
ITEMQTYUNITSDESCRIPTIONUNIT PRICEUNIT PRICE DOLLARS AND CENTS (In Words)TOTAL AMOUNT
11LSPUMP STATION IMPROVEMENTS$0.00$0.00
24EAINTAKE GATE REPLACEMENT$0.00$0.00
31LSMOBILIZATION FOR CONFINED SPACE WORK IN THE FLUME$0.00$0.00
4325CFCONCRETE MORTAR REPAIR$0.00$0.00
51,500LFCONCRETE CRACK REPAIR$0.00$0.00
66EAHORIZONTAL SPLIT CASE PUMP UNIT MODIFICATIONS (BASEFRAME REPLACEMENT WITH PUMP AND MOTOR LEVELING)$0.00$0.00
76EAHORIZONTAL SPLIT CASE PUMP UNIT MODIFICATIONS (PUMP AND MOTOR LEVELING)$0.00$0.00
81LSSTORM WATER POLLUTION PREVENTION PLAN AND DUST CONTROL$0.00$0.00
TOTAL BASE BID$0.00

SECTION B ADDITIVE ALTERNATES

ADDITIVE ALTERNATE A1
ITEMQTYUNITSDESCRIPTIONUNIT PRICEDOLLARS AND CENTS (In Words)TOTAL AMOUNT
A15,000CYLAKE TAWAKONI SILT DREDGING AND MOBILIZATION FOR LAKE TAWAKONI SILT DREDGING$0.00$0.00
TOTAL ADDITIVE ALTERNATE A1$0.00
ADDITIVE ALTERNATE A2
ITEMQTYUNITSDESCRIPTIONUNIT PRICEDOLLARS AND CENTS (In Words)TOTAL AMOUNT
A21LSADDITIONAL INTAKE GATE REHABILITATION$0.00$0.00
TOTAL ADDITIVE ALTERNATE A2$0.00
ADDITIVE ALTERNATE A3
ITEMQTYUNITSDESCRIPTIONUNIT PRICEDOLLARS AND CENTS (In Words)TOTAL AMOUNT
A31LSBACKUP GENERATOR$0.00$0.00
TOTAL ADDITIVE ALTERNATE A3$0.00