This document is a Standard Operating Procedure (SOP) for the Dig Permit Program at the Edward Hines VA Hospital in Hines, Illinois, dated May 6, 2015. The purpose of the program is to establish a formal process for obtaining approval and safely executing excavation work while minimizing risks to underground utilities and infrastructure. The SOP defines specific responsibilities for key personnel, including the Engineering Service Chief, Project Planning Chief, Dig Permit Program Manager, and Execution Agent.

The program requires the Execution Agent to request a Dig Permit, prepare a work sketch, secure a professional utility locator, mark utilities within 24 hours of excavation, and complete the Hines Form 1532. The Program Manager must inspect utility markings, compare them to existing drawings, sign the permit, and maintain a digital copy for at least two years. The procedure references OSHA 1926.651 and USACE EM 385-1-1 safety requirements, and aims to coordinate work that may disrupt installation services, traffic flow, or routine activities while preventing potential accidents during excavation.

View the file

Other files

File Type Posted
S06 36C25226B0001 0003.docx DOCX document
S06 36C25226B0001 0002.docx DOCX document
S06 36C25226B0001 0001.docx DOCX document
P07 WAGE DETERMINATION COOK IL20250009 11-2025.pdf PDF
1e. Cutting Welding and Other Hot Work.pdf PDF
1j. OIT Horizontal Cable Requirements.pdf PDF
1k. Fire Protection Code Reviews.pdf PDF
1l. Asbestos Survey Glossary -when applicable.pdf PDF
8b. Building 13 Signage Legend.pdf PDF
8c. Building 113 Signage Legend.pdf PDF
8d. Building 128 Signage Legend.pdf PDF
8f. Building 217 Signage Legend.pdf PDF
8i. Site Wayfinding and Building Signage Legend.pdf PDF
8j. Signage Legend for Bldgs 1-230,CBOCs.pdf PDF
9 Buildings 13 113 Drawings.pdf PDF
15 Building 228 Signage Drawings-1.pdf PDF
16 Building 228 Signage Drawings-2.pdf PDF
19 Building 200 Signage Drawings-2.pdf PDF
27 Bldg 1 Signage Drawings-1.pdf PDF
33 Bldgs 2-9 Drawings.pdf PDF
36 Buildings 203 220 230 Drawings.pdf PDF
P09 578-15-008 SOW 2026 R2 120125.docx DOCX document
1c. Pre-Construction Checklist Rev 07.27.2021 V2.pdf PDF
1i. Hines Parking Designations.pdf PDF
2 Hines VA Campus Site Plan.pdf PDF
3 Infection Control Risk Assessement.pdf PDF
6 578-15-008 Specifications 112825.pdf PDF
8h. Building 228 Signage Legend.pdf PDF
11 Building 217 Signage Drawings-1.pdf PDF
13 Building 217 Signage Drawings-3.pdf PDF
25 Building 200 Signage Drawings-8.pdf PDF
26 Building 200 Signage Drawings-9.pdf PDF
34 Bldgs 16-18 Drawings.pdf PDF
35 Bldgs 20-48 Drawings.pdf PDF
37 CBOCs Drawings.pdf PDF
S02 Solicitation 36C25226B0001 Final.docx DOCX document
1a. Hines VA Campus Site Plan.pdf PDF
1b. Hines Underground Utility Plan.pdf PDF
1g. Above Ceiling Entry and Wall Construction Permits.pdf PDF
1h. Contractor Badging - Fingerprint Request Form 2025.pdf PDF
1m. Infection Control Barrier Sample.pdf PDF
1n. Hines COVID-19 Guidelines.pdf PDF
1o. No Smoking Policy 10-1-19.pdf PDF
1p. Emergency Contact List - Template.pdf PDF
8a. Building 12 Signage Legend.pdf PDF
8e. Building 200 Signage Legend.pdf PDF
8g. Building 221 Signage Legend.pdf PDF
12 Building 217 Signage Drawings-2.pdf PDF
18 Building 200 Signage Drawings-1.pdf PDF
23 Building 200 Signage Drawings-6.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Hospital Engineering Service SOP Dig Permit Hines, IL 60141 May 6, 2015

DIG PERMIT PROGRAM SOP

1. PURPOSE: The purpose of this plan is to clearly define the process to obtain installation approval to excavate, withdraw from, insert into, or otherwise penetrate any ground-level surfaces within the area of responsibility at Edward Hines, VA Hospital and areas under our purview.

As underground work is carried out through the installation, the risk of damaging critical infrastructure and utilities is significant. The process defined herein seeks to minimize these risks by proactively identifying the existence of utilities in the area of excavation and affording an opportunity to develop adequate precautions to safeguard said utilities.

2. RESPONSIBILITIES:

a. Engineering Service Chief :

The Engineering Service Chief shall support the Dig Permit Program and ensure the process is kept up to date by reviewing the process and analyzing the impact on utilities throughout an execution year. Documentation is not required for this review. However, this SOP must be reviewed and dated once per year. The Service Chief shall report all program violations to the assigned PENTAD member for accountability.

b. Project Planning Chief :

The Project Planning Chief shall officially assign an official Dig Permit Program Manager. The Chief will report the impact of the program and any violations of the program requirements to the Engineering Service Chief. Should the project generating the violation be managed by the Hines Project Planning Section, the Chief shall report this violation to the appropriate contracting agency for contractor enforcement.

c. Dig Permit Program Manager:

The Dig Permit Manager shall ensure personnel involved in any work requiring participation in this permit program adhere to the requirements of the program. The Program Manager shall report any violations to the permit to the Safety Service Chief and the Project Planning Chief.

d. Execution Agent:

The Execution Agent is defined as any party partaking on actions that require this permit.

The Agent shall adhere to all requirements of the permit program and actively participate in method resolution to support the protection of underground utilities and infrastructure.

VA Hospital Engineering Service SOP Dig Permit Hines, IL 60141 May 6, 2015

3. PROGRAM REQUIREMENTS:

a. The Execution Agent shall contact the Program Manager and request a Dig Permit.

b. The Program Manager shall issue a blank permit in the form of a Hines Form 1532.

c. The Program Manager shall explain the process to the Execution Agent, and collect preliminary information from the Agent to include,

a. Expected excavation date

b. General area of work

c. Approximate duration of work.

d. Execution Agent shall prepare a sketch depicting the general area of excavation and its boundaries.

e. Execution Agent shall secure a professional utility locator vendor and locate all utilities in the immediate area of excavation and no less than 6 feet beyond the excavation area.

Utilities shall not be marked more than 24 hours prior to the planned excavation date.

f. Execution Agent shall complete the Hines Form 1532 with the exception of the Engineering signature.

g. Execution Agent will notify the Program Manager

h. The Program Manager shall inspect the markings and compare to existing utility drawings.

i. The Program Manager shall sign Hines Form 1532 confirming that utilities have been located to the maximum extent possible.

j. The program Manager shall retain a copy of the completed permit.

k. The Execution Agent shall notify the Program Manager when all excavation work is completed, backfilled and compacted (if applicable).

l. The Program Manager shall close the permit and maintain a digital copy of the permit for no less than 2 years after completion of the excavation.

4. REFERENCES:

• Hines Form 1532

• OSHA 1926.651, Specific Excavation Requirements

• USACE EM 385-1-1, Safety and Health Requirements Manual

Russell Thomason Chief, Engineering Service

DATE PREPARED

1. Clearance requested to proceed with work at on Work Order No. , Contract No. , involving excavation or utility disturbance per attached sketch. This area has has not been staked or clearly marked.

2. TYPE OF WORK INVOLVED

A. PAVEMENTS D. FIRE PROTECTION & DETECTION SYSTEMS G. AIRCRAFT OR VEHICULAR TRAFFIC FLOW

B. DRAINAGE SYSTEMS E. UTILITY OVERHEAD UNDERGROUND H. SECURITY

C. RAILROAD TRACKS F. COMM OVERHEAD UNDERGROUND I. OTHER

3. DATE CLEARANCE REQUIRED (NO LESS THAN 72 HOURS) 4. DATE CLEARANCE APPROVED (FOR P2 USE ONLY)

5. SIGNATURE OF REQUESTOR (INSTALLATION POC) 6. POC TELEPHONE NUMBER 7. POC ORGANIZATION

SAFETY

FIRE PROTECTION

GEMS

POLICE

OI&T

PAVEMENTS AND GROUNDS

ENGINEERING- HTM

ENGINEERING- PROJECT PLANNING

ENGINEERING- M&O

OTHER

11. COMMERCIAL UTILITY COMPANY

TELEPHONE

GAS

ELECTRIC

WATER

12. OTHER (SPECIFY)

14. APPROVING OFFICIAL 15. DATE SIGNED

(NAME AND SIGNATURE OF CHIEF OF PROJECT PLANNING OR ENGINEERING SERVICE CHIEF)

HINES FORM 1532, MAY 2015 VERSION

HINES ENGINEERING- DIG PERMIT

(SEE INSTRUCTIONS ON REVERSE)

9. REMARKS (USE REVERSE FOR ADDITIONAL COMMENTS)8. SERVICE/SECTION 10. REVIEWER NAME

13. PERMIT APPROVAL APPROVED DISAPPROVED

HINES FORM 1532, MAY 2015 VERSION (REVERSE)

INSTRUCTIONS

The Hine Engineering- Dig Permit is used for any work (contract or in-house) that may disrupt aircraft or vehicular traffic flow, installation utility services, protection provided by fire or intrusion alarm systems, or routine activities of the installation. This form is used to coordinate the required work with key installation activities and keep customer inconvenience to a minimum. It is also used to identify hazardous work conditions in an attempt to prevent accidents. The Dig Permit request is processed just prior to starting work. If delays are encountered and the conditions at the job site change (or may have changed) this permit must be reprocessed.

16. REMARKS (This section must describe the specific measures to be taken before and during work accomplishment. Specific comments concerning the approved method of excavation, hand or powered equipment, must be included.)

Dig Permit SOP 2015
DIG PERMIT FORM
Sheet1
Chief, Engineering Service:
DATE 1:
1 Clearance requested to proceed with work at:
Contract No:
involving excavation or utility disturbance:
has: Off
has not been staked or clearly marked: Off
2 TYPE OF WORK INVOLVED:
D FIRE PROTECTION DETECTION SYSTEMS:
G AIRCRAFT OR VEHICULAR TRAFFIC FLOW:
E UTILITY:
OVERHEAD:
UNDERGROUND:
H SECURITY:
F COMM:
OVERHEAD_2:
UNDERGROUND_2:
I OTHER:
DATE 2:
DATE 3:
5 SIGNATURE OF REQUESTOR INSTALLATION POC:
6 POC TELEPHONE NUMBER:
7 POC ORGANIZATION:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSSAFETY:
10 REVIEWER NAMESAFETY:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSFIRE PROTECTION:
10 REVIEWER NAMEFIRE PROTECTION:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSGEMS:
10 REVIEWER NAMEGEMS:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSPOLICE:
10 REVIEWER NAMEPOLICE:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSOIT:
10 REVIEWER NAMEOIT:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSPAVEMENTS AND GROUNDS:
10 REVIEWER NAMEPAVEMENTS AND GROUNDS:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSENGINEERING HTM:
10 REVIEWER NAMEENGINEERING HTM:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSENGINEERING PROJECT PLANNING:
10 REVIEWER NAMEENGINEERING PROJECT PLANNING:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSENGINEERING MO:
10 REVIEWER NAMEENGINEERING MO:
9 REMARKS USE REVERSE FOR ADDITIONAL COMMENTSOTHER:
10 REVIEWER NAMEOTHER:
11 COMMERCIAL UTILITY COMPANY:
TELEPHONE: Off
GAS: Off
ELECTRIC: Off
WATER: Off
TELEPHONE GAS ELECTRIC WATER:
12 OTHER SPECIFY:
13 PERMIT APPROVAL APPROVED DISAPPROVED:
APPROVED:
DISAPPROVED:
14 APPROVING OFFICIAL NAME AND SIGNATURE OF CHIEF OF PROJECT PLANNING OR ENGINEERING SERVICE CHIEF:
15 DATE SIGNED:
16 REMARKS This section must describe the specific measures to be taken before and during work accomplishment Specific comments concerning the approved method of excavation hand or powered equipment must be included: